Concord Township v. United States

625 F.2d 1068
CourtCourt of Appeals for the Third Circuit
DecidedJune 23, 1980
DocketICC Finance Docket No. 28334); No. 79-1887
StatusPublished
Cited by19 cases

This text of 625 F.2d 1068 (Concord Township v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Concord Township v. United States, 625 F.2d 1068 (3d Cir. 1980).

Opinion

OPINION OF THE COURT

GIBBONS, Circuit Judge.

This is a petition pursuant to 28 U.S.C. § 2342(5) (1976) to review an order of the Interstate Commerce Commission (Commission) granting the Octoraro Railway, Inc. (OCTR) a Certificate of Public Convenience and Necessity for a freight rail service over a 41.7 mile line between Colora, Maryland and Wawa, Pennsylvania.1 The petition challenges only the grant of authority to operate the easterly nine mile portion of the line between Chadds Ford Junction, Pennsylvania, and Wawa. Petitioners are Concord Township and the Nicholas Newlin Foundation which are located in the nine mile segment, and a number of other property owners whose properties are located along the line between Concordville (situated between Chadds Ford Junction and Wawa) and Wawa. They contend that the Commission erred in determining that public convenience and necessity would be enhanced by the grant to OCTR of a certificate to operate over the disputed nine mile segment, and that it also erred in concluding that an environmental impact statement was unnecessary. We conclude that the petition for review should be granted. Since the applicable law and the scope of review differ with respect to the petitioners’ separate contentions, we consider them separately.

I. FACTUAL AND PROCEDURAL BACKGROUND

On November 8, 1976, OCTR filed an application with the Commission pursuant to section 1(18) of the Interstate Commerce Act,2 for a Certificate of Public Convenience and Necessity to operate a freight railroad on the line described above. The right of way for this proposed freight line was a former Penn Central Transportation Company branch line, which had provided freight and passenger service from 1859 to 1948, and only freight service from 1948 until September, 1971. In that month, Hurricane Agnes caused a huge flood in the area, making the line totally inoperable. An application for abandonment was filed with the Commission in March, 1972. The Commission’s jurisdiction over that railroad abandonment proceeding terminated with the enactment of the Regional Rail Reorganization Act, 45 U.S.C. §§ 701-794 (Supp. 1979), and the Penn Central abandonment petition was consequently dismissed without Commission action on the merits. Thereafter, the United States Railway Commission excluded this branch line from the Final System Plan for Conrail. In 1976, the Southeastern Pennsylvania Transportation Authority (SEPTA), an agency of the Commonwealth, acquired the inoperative right-of-way under section 206(c)(1)(D) of the Regional Rail Reorganization Act, 45 U.S.C. § 716(c)(1)(D), with funds supplied by the federal Urban Mass Transit Authority (UMTA). SEPTA leased the right-of-way to the Board of Commissioners of Chester County, Pennsylvania, and they in turn leased the line to OCTR, a private corporation, for the purpose of establishing and operating a freight service on the line.

Verified statements on the need for the service were evaluated under the Commission’s Modified Procedure. See 49 C.F.R. § 1100.43 (1979). On October 25, 1978, Commission Review Board Number 5 approved the application for operation between Colora, Maryland, and Chadds Ford Junction, Pennsylvania, but denied authority to operate from Chadds Ford Junction eastward to Wawa. Administrative appeals from the Review Board’s decision were filed by OCTR, the operator of the freight service, and by SEPTA, the actual owner of the right-of-way. Some of the petitioners opposed these appeals. In May of 1979, the [1071]*1071Commission, by a divided vote, modified the Review Board’s decision to authorize freight service over the entire line. This petition for review followed.

Repairs have been made to the westerly portions of the right-of-way between Colora and Chadds Ford Junction, funded from several public and private sources. The easterly segment is still inoperable. A freight service is now being provided by OCTR over the westerly segment.

II. THE DETERMINATION OF SHIPPER NEED

The governing statute provides that a rail carrier may be authorized to operate a line

only if the Commission finds that the present or future public convenience and necessity require or will be enhanced by the construction or acquisition (or both) and operation of the railroad line.

49 U.S.C. § 10901(a). The sine qua non for such a finding is evidence of shipper need, actual or prospective. This application was supported by eleven shippers located along the segment of the line west of Chadds Ford Junction, by the Korman Corporation, a landowner with undeveloped property along the easterly segment, by the Commissioners of Chester County, and by the State of Maryland. The disputed segment, of course, is not located in Maryland. Reviewing the evidentiary submissions, Review Board No. 5 concluded:

[T]he OCTR has presented no evidence indicating that there is any need for service on the Chadds Ford Junction to Wawa segment of the line. . No shippers have come forward to demand service. The only potential shipper in this segment, the Korman Corporation, is years away from having a facility in need of rail service. According to the [Concord] Township, there are no other industries in the segment that need rail service. There is no economic development planned in the [Concord] Township that can use the OCTR. The OCTR’s response that the existence of the railroad service will attract service is speculative. .
SEPTA does not know when and if the segment of the line will be rebuilt. SEPTA has no immediate plans to rebuild the two bridges between Concordville and Wawa and restore that segment of the line. OCTR cannot provide rail service until repairs are made. We cannot issue a certificate authorizing operations over this segment until we have more definite information about restoration of service.

ICC F.D. No. 28334 at 2, 3 (Sept. 19, 1978). In contrast with these findings about the easterly segment, Review Board No. 5 found that “we have financial projections of the line west of Chadds Ford Junction; we have evidence of shippers’ need for the service over that segment; and that portion of the line is the only one operable at this time.” Id. at 3. The Board concluded that it should grant a Certificate for freight service only over the westerly segment. Its reasons are clear. First, the only evidence of shipper need relates to the westerly segment. Second, financial projections for operations over the easterly segment cannot be made because there is no clear indication when, if ever, that segment will be rebuilt.

The Commission majority reversed the Board. As to demonstrating shipper need, it concluded that SEPTA’s expressed intention to reconstruct the eastern segment, at some time in the future for commuter passenger service, was sufficient to demonstrate their commitment to funding.3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Raymond Proffitt Foundation v. U.S. Army Corps of Engineers
175 F. Supp. 2d 755 (E.D. Pennsylvania, 2001)
Citizens Advy. Comm. on Priv. Pris. v. Usdoj
197 F. Supp. 2d 226 (W.D. Pennsylvania, 2001)
Concerned Citizens Alliance, Inc. v. Slater
176 F.3d 686 (Third Circuit, 1999)
Concerned Citizens Alliance, Inc. v. Rodney Slater
176 F.3d 686 (Third Circuit, 1999)
Township of Belleville v. Federal Transit Administration
30 F. Supp. 2d 782 (D. New Jersey, 1998)
Clairton Sportsmen's Club v. Pennsylvania Turnpike Commission
882 F. Supp. 455 (W.D. Pennsylvania, 1995)
Kansas City Area Transportation Authority v. 4550 Main Associates, Inc.
742 S.W.2d 182 (Missouri Court of Appeals, 1987)
Sierra Club v. Froehlke
630 F. Supp. 1215 (S.D. Texas, 1986)
County of Bergen v. Dole
620 F. Supp. 1009 (D. New Jersey, 1985)
Ashwood Manor Civic Ass'n v. Dole
619 F. Supp. 52 (E.D. Pennsylvania, 1985)
Township Of Springfield v. Drew Lewis
702 F.2d 426 (Third Circuit, 1983)
Township of Springfield v. Lewis
702 F.2d 426 (Third Circuit, 1983)
Simmons v. United States
698 F.2d 888 (Seventh Circuit, 1983)
Hovsons, Inc. v. Secretary of Interior of US
519 F. Supp. 434 (D. New Jersey, 1981)
Illinois v. United States
666 F.2d 1066 (Seventh Circuit, 1981)
People v. United States
666 F.2d 1066 (Seventh Circuit, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
625 F.2d 1068, Counsel Stack Legal Research, https://law.counselstack.com/opinion/concord-township-v-united-states-ca3-1980.