Con Co, Inc. v. Wilson Acres Apartments, Ltd.

289 S.E.2d 633, 56 N.C. App. 661, 1982 N.C. App. LEXIS 2486
CourtCourt of Appeals of North Carolina
DecidedApril 6, 1982
Docket813SC385
StatusPublished
Cited by6 cases

This text of 289 S.E.2d 633 (Con Co, Inc. v. Wilson Acres Apartments, Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Con Co, Inc. v. Wilson Acres Apartments, Ltd., 289 S.E.2d 633, 56 N.C. App. 661, 1982 N.C. App. LEXIS 2486 (N.C. Ct. App. 1982).

Opinion

WEBB, Judge.

At the outset we note that this action involves multiple parties. Judge Rouse found there was no just reason for delay as to both summary judgments. The judgments are appealable pursuant to G.S. 1A-1, Rule 54(b). See Industries, Inc. v. Insurance Co., 296 N.C. 486, 251 S.E. 2d 443 (1979).

The facts which are not in dispute show that the plaintiff was a first tier subcontractor on the Wilson Acres apartment project. Article 2, Part 2 of Chapter 44A of the General Statutes provides for the perfecting of liens by subcontractors. A lien in favor of a subcontractor may arise either directly under G.S. 44A-18 and G.S. 44A-20 or by subrogation under G.S. 44A-23. If a subcontractor attempts to perfect a lien by subrogation, he is bound by any defenses available against the contractor. See Mace v. Construction Corp., 48 N.C. App. 297, 269 S.E. 2d 191 )1980). In this case the contractor made an agreement with the landowner that it would not perfect a lien against the real estate. The plaintiff is bound by this agreement. It cannot perfect a lien by subrogation. Summary judgment was properly allowed as to the plaintiffs claim for a contractor’s lien.

The waiver of the right to establish a lien by the prime contractor does not affect plaintiffs right to perfect a lien as a subcontractor under G.S. 44A-18 which provides:

“Upon compliance with this Article:
(1) A first tier subcontractor who furnished labor or materials at the site of the improvement shall be entitled to a lien upon funds which are owed to the con *664 tractor with whom the first tier subcontractor dealt and which arise out of the improvement on which the first tier subcontractor worked or furnished materials.
* * *
(6) The liens granted under this section are perfected upon the giving of notice in writing to the obligor as hereinafter provided and shall be effective upon the receipt thereof by such obligor.”

G.S. 44A-20 provides:

“(a) Upon receipt of the notice provided for in this Article the obligor shall be under a duty to retain any funds subject to the lien or liens under this Article up to the total amount of such liens as to which notice has been received.
(b) If, after the receipt of the notice to the obligor, the obligor shall make further payments to a contractor or subcontractor against whose interest the lien or liens are claimed, the lien shall continue upon the funds in the hands of the contractor or subcontractor who received the payment, and in addition the obligor shall be personally liable to the person or persons entitled to liens up to the amount of such wrongful payments, not exceeding the total claims with respect to which the notice was received prior to payment.
* * *
(d) If the obligor is an owner of the property being improved, the lien claimant shall be entitled to a lien upon the interest of the obligor in the real property to the extent of the owner’s personal liability under subsection (b), which lien shall be enforced only in the manner set forth in G.S. 44A-7 through 44A-16 and which lien shall be entitled to the same priorities and subject to the same filing requirements and periods of limitation applicable to the contractor.”

Under this statute when a subcontractor notifies the owner of a claim against the contractor and the owner disburses money to the contractor after such notification, the owner is liable to the subcontractor to the extent of the funds disbursed and the subcontractor may perfect a lien on the realty of the owner. In the *665 instant case the papers show that the plaintiff notified the owner of a claim against the contractor prior to payment by the owner to the contractor. This would create a debt from Wilson Acres Apartments to Con Co, Inc. and if properly perfected, would create a lien on the land of Wilson Acres Apartments in favor of the plaintiff.

Wilson Acres Apartments, Ltd. argues that the notice was not properly given under G.S. 44A-20 because the plaintiff filed the lien claim before giving actual notice to the obligors. It contends the lien could not have arisen until notice was given and by filing the lien claim before notice was given, it is of no effect. We cannot so hold. We do not believe the fact that the lien claim was filed before the notice was actually served should make a difference. The claim did not ripen into a lien upon the land until Wilson Acres paid McGowan Builders after being notified of the claim. The plaintiff had to file the claim for the lien within 120 days of the last work performed in order to comply with the statute in perfecting the lien. We hold that the fact that the plaintiff did not give actual notice of the claim until after it had filed the claim in the office of the clerk of superior court did not void the claim of lien which was filed in the clerk’s office. If Wilson Acres had moved to strike the claim before paying McGowan Builders, it might be a different case.

The appellees also contend that the plaintiff may not bring this action because it is not the real party in interest. They say this is so because by its own allegations in the complaint, the plaintiff shows that Ellis Morall, Inc. had contracted to complete the work for plaintiff and Ellis Morall, Inc. should be the party who brings this action. The plaintiff has also alleged that McGowan Builders, Inc. breached the contract by refusing to allow Ellis Morall, Inc. to complete the work. Plaintiff alleged that because of the material breach by McGowan of the Ellis Morall, Inc. contract, the plaintiff had elected to treat the contract as rescinded. If the plaintiff can prove these allegations, it is the proper party to bring this action.

We hold the superior court was in error in granting the motion for summary judgment for Wilson Acres Apartments as to the plaintiffs claim for a debt against Wilson Acres Apartments and for its claim of lien as a first tier subcontractor on the real property of Wilson Acres Apartments.

*666 As to the claim against Kennedy Mortgage Company, we hold the defendant’s motion for summary judgment was properly allowed. Kennedy Mortgage Company financed the construction of the property. Plaintiff argues that Kennedy Mortgage Company is an obligor within the meaning of G.S. 44A-18(6) and G.S. 44A-20 so that when it advanced money to Wilson Acres Apartments after being notified of the plaintiffs claim, it became obligated to the plaintiff for its claim. G.S. 44A-17 provides:

“Unless the context otherwise requires in this Article:
* * *
(3) ‘Obligor’ means an owner, contractor or subcontractor in any tier who owes money to another as a result of the other’s partial or total performance of a contract to improve real property.”

G.S. 44A-7 provides:

“Unless the context otherwise requires in this Article:
* * *

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pete Wall Plumbing Co. v. Sandra Anderson Builders, Inc.
721 S.E.2d 663 (Court of Appeals of North Carolina, 2011)
Watson Electrical Construction Co. v. Summit Companies, LLC
587 S.E.2d 87 (Court of Appeals of North Carolina, 2003)
Electric Supply Co. of Durham, Inc. v. Swain Electrical Co.
403 S.E.2d 291 (Supreme Court of North Carolina, 1991)
CON CO. INC. v. Wilson Acres Apartments, Ltd.
294 S.E.2d 206 (Supreme Court of North Carolina, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
289 S.E.2d 633, 56 N.C. App. 661, 1982 N.C. App. LEXIS 2486, Counsel Stack Legal Research, https://law.counselstack.com/opinion/con-co-inc-v-wilson-acres-apartments-ltd-ncctapp-1982.