Complete Solar, Inc.; T.J. Rodgers; And Brian Wuebbels v. Andy Phu

CourtTexas Court of Appeals, 8th District (El Paso)
DecidedJune 2, 2026
Docket08-26-00024-CV
StatusPublished

This text of Complete Solar, Inc.; T.J. Rodgers; And Brian Wuebbels v. Andy Phu (Complete Solar, Inc.; T.J. Rodgers; And Brian Wuebbels v. Andy Phu) is published on Counsel Stack Legal Research, covering Texas Court of Appeals, 8th District (El Paso) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Complete Solar, Inc.; T.J. Rodgers; And Brian Wuebbels v. Andy Phu, (Tex. Ct. App. 2026).

Opinion

COURT OF APPEALS EIGHTH DISTRICT OF TEXAS EL PASO, TEXAS ————————————

No. 08-26-00024-CV ————————————

Complete Solar, Inc.; T.J. Rodgers; and Brian Wuebbels, Appellants v. Andy Phu, Appellee

On Appeal from the 433rd District Court Comal County, Texas Trial Court No. C2024-0958D

M E MO R A N D UM O P I N I O N

Appellee Andy Phu sued Appellant Complete Solar Inc.,1 and two of its corporate officers,

T.J. Rodgers and Brian Wuebbels, (collectively, the Complete Solar Defendants)2 for, among other

1 Phu initially named “Complete Solaria d/b/a Complete Solar” as the defendant in the lawsuit. However, Complete Solar, Inc. informed both the trial court in its answer to the petition and this Court in its docketing statement that this was incorrect. Our caption therefore reflects its name as Complete Solar, Inc. 2 In one of its most recent pleadings in the trial court, Complete Solar identified T.J. Rodgers and Bryan Wuebbels as “the current CEO and former COO of Complete Solar, respectively.” things, deceptive trade practices, common law fraud, negligent misrepresentation, and breach of

contract with respect to a contract for solar panels. Approximately nine months after answering

Phu’s petition, the Complete Solar Defendants filed a motion to compel arbitration, pointing to an

arbitration agreement in the parties’ contract. The trial court denied the motion, and the Complete

Solar Defendants appealed.3 We conclude that the trial court erred by denying the motion.

I. FACTUAL AND PROCEDURAL BACKGROUND

A. Phu’s lawsuit

Phu entered into a contract with Complete Solar on September 16, 2022, for the installation

of solar panels at his residence (the Solar Contract). According to Phu’s lawsuit, he wished to

cancel the contract in December 2022 when installation work had not yet begun, but he was

convinced by Mag Solar, a company acting as Complete Solar’s agent, to go forward with the

installation.4

Phu contends that Complete Solar and Mag Solar used a contractor named The Real

Brady’s LLC d/b/a Lonestar Skypower (the Real Brady’s), to install the solar panels. According to

Phu, the panels were installed incorrectly, and although they passed city inspection, he alleges that

they failed inspection by his local city utility at least six times, and he was denied a permit to

operate the panels.

3 This case was transferred pursuant to the Texas Supreme Court’s docket equalization efforts. Tex. Gov’t Code § 73.001. We follow the precedent of the Third Court of Appeals to the extent it might conflict with our own. See Tex. R. App. P. 41.3. 4 In the trial court, Complete Solar acknowledged that it had an agency relationship with Mag Solar, pointing to a “Master Authorized Sales Agent and Independent Contractor Agreement” (the Agent Agreement) the two companies signed on March 28, 2023. The Agent Agreement authorized Mag Solar to offer Complete Solar’s residential solar solutions directly to consumers. The Solar Contract was signed by Brydon March on Complete Solar’s behalf as the “contractor.” March is identified in the record as Mag Solar’s corporate officer.

2 He further claims that, despite knowing the panels were not properly installed and

nonoperational, the company from which he obtained a loan to finance the purchase of the panels,

Dividend Solar Finance LLC (Dividend), “strong-armed” him into signing a form indicating they

were installed so he could obtain a lower interest rate on his loan. According to Phu, despite the

nonfunctionality of the panels, he was still required to make payments to Dividend, and although

Complete Solar was initially “refunding” the payments, they ceased doing so.

Phu filed his original petition in the trial court on May 28, 2024, naming as defendants: the

Complete Solar Defendants, Mag Solar, and one of its corporate officers, Brydon March;

Dividend; and the Real Brady’s. In the petition, Phu alleged that Complete Solar had breached the

Solar Contract by not ensuring that the panels were properly installed and operational. Phu alleged

that the various defendants made misrepresentations and/or failed to disclose material information

to induce him into entering into the Solar Contract and to not cancel it; engaged in common law

fraud; committed violations of the Deceptive Trade Practices Act (the DTPA); and “engaged in a

civil conspiracy to defraud Mr. Phu and scam him in their solar panel scheme.” Phu sought

economic and actual damages, damages for mental anguish, treble damages for the DTPA

violations, and exemplary damages based on fraud allegations. He also sought a judgment

declaring that the Solar Contract is “null and void” and sought attorney’s fees. Phu later amended

his petition, raising substantially similar claims.

The Complete Solar Defendants filed a joint answer on September 18, 2024, generally

denying Phu’s allegations. On an unspecified date, Phu served on the Complete Solar Defendants

(1) a request for admissions; (2) a request for production; and (3) interrogatories. Although the

Complete Solar Defendants responded to the requests in January 2025, it does not appear that any

additional discovery requests were made until May 19–20, 2025, when Phu served notices of

3 deposition on Complete Solar Defendants, Dividend, and March, which all the defendants moved

to quash.5

On May 23, 2025, counsel for the Complete Solar Defendants emailed Phu’s attorney and

informed him that the Solar Contract contained “mediation and arbitration clauses” requiring the

parties to submit their disputes to mediation and then to arbitration if the mediation was

unsuccessful. The email stated, “Assuming you are not amenable to private mediation, then

arbitration is the proper forum,” and asked if Phu would agree to submit the case to arbitration.

Phu’s attorney responded by email dated May 27, 2025, stating he was opposed to arbitration. He

stated, however, that “we would be open to mediation paid for by your client,” and “might be open

to mediation [if] each side pays.” He stated that he would confer with his client and reach out with

a phone call after that. No additional emails or other correspondence are contained in the record

on this subject, but it does not appear that mediation took place before the Complete Solar

Defendants moved to compel arbitration.

B. The first motion to compel arbitration

The Complete Solar Defendants moved to compel arbitration on June 10, 2025, providing

a copy of the parties’ Solar Contract that was signed by both Phu, as the homeowner, and March,

as the “contractor” on September 16, 2022.6 They pointed to the following arbitration agreement

contained in an addendum to the Solar Contract:

5 The Complete Solar Defendants’ motion to quash was based in part on the contention that Rodgers and Wuebbels did not have any “personal involvement” in the transaction. Complete Solar also argued that the depositions were scheduled “unilaterally” without consultation with their attorneys to confirm their availability. 6 The signature page of the Solar Contract also included the printed name, “Josh Webb / Director of Sales Operations,” but his signature is not on the contract and he is not named as a defendant. Despite March signing, Mag Solar did not move to compel arbitration.

4 Mediation and arbitration of all disputes. The parties hereto understand and agree that private mediation and arbitration of any dispute between them arising out of this agreement is a fair and efficient process.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Prima Paint Corp. v. Flood & Conklin Mfg. Co.
388 U.S. 395 (Supreme Court, 1967)
Buckeye Check Cashing, Inc. v. Cardegna
546 U.S. 440 (Supreme Court, 2006)
J.M. Davidson, Inc. v. Webster
128 S.W.3d 223 (Texas Supreme Court, 2003)
Low v. Henry
221 S.W.3d 609 (Texas Supreme Court, 2007)
In Re Merrill Lynch Trust Co. FSB
235 S.W.3d 185 (Texas Supreme Court, 2007)
In Re U.S. Home Corp.
236 S.W.3d 761 (Texas Supreme Court, 2007)
Perry Homes v. Cull
258 S.W.3d 580 (Texas Supreme Court, 2008)
In Re Fleetwood Homes of Texas, L.P.
257 S.W.3d 692 (Texas Supreme Court, 2008)
Forest Oil Corp. v. McAllen
268 S.W.3d 51 (Texas Supreme Court, 2008)
In Re Morgan Stanley & Co., Inc.
293 S.W.3d 182 (Texas Supreme Court, 2009)
In Re 24R, Inc.
324 S.W.3d 564 (Texas Supreme Court, 2010)
Garza v. Texas Alcoholic Beverage Commission
89 S.W.3d 1 (Texas Supreme Court, 2002)
London v. London
192 S.W.3d 6 (Court of Appeals of Texas, 2006)
Northwest Construction Co. v. Oak Partners, L.P.
248 S.W.3d 837 (Court of Appeals of Texas, 2008)
Daughety v. National Ass'n of Homebuilders of the United States
970 S.W.2d 178 (Court of Appeals of Texas, 1998)
In Re Dillard Department Stores, Inc.
181 S.W.3d 370 (Court of Appeals of Texas, 2005)
Nationwide of Bryan, Inc. v. Dyer
969 S.W.2d 518 (Court of Appeals of Texas, 1998)
In Re Service Corporation Intern.
85 S.W.3d 171 (Texas Supreme Court, 2002)
N-S-W Corp. v. Snell
561 S.W.2d 798 (Texas Supreme Court, 1977)
EZ Pawn Corp. v. Mancias
934 S.W.2d 87 (Texas Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Complete Solar, Inc.; T.J. Rodgers; And Brian Wuebbels v. Andy Phu, Counsel Stack Legal Research, https://law.counselstack.com/opinion/complete-solar-inc-tj-rodgers-and-brian-wuebbels-v-andy-phu-txctapp8-2026.