Complete Prototype Services, Inc. v. Penda Corporation

CourtDistrict Court, W.D. Wisconsin
DecidedNovember 22, 2024
Docket3:23-cv-00247
StatusUnknown

This text of Complete Prototype Services, Inc. v. Penda Corporation (Complete Prototype Services, Inc. v. Penda Corporation) is published on Counsel Stack Legal Research, covering District Court, W.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Complete Prototype Services, Inc. v. Penda Corporation, (W.D. Wis. 2024).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF WISCONSIN

COMPLETE PROTOTYPE SERVICES, INC.,

Plaintiff, OPINION and ORDER v.

23-cv-247-jdp PENDA CORPORATION,

Defendant.

This case arises from orders that defendant Penda Corporation placed with plaintiff Complete Prototype Services, Inc., for certain parts that would eventually be used in cars manufactured by General Motors. Complete Prototype contends that, after it had completed production of the parts that Penda ordered, Penda wrongfully refused to accept shipment or pay for the parts. It brings claims against Penda for breach of contract, conversion, unjust enrichment, and account stated. Penda moves for summary judgment on all claims. Dkt. 26. The fundamental reasoning behind each of Complete Prototype’s four claims is that it is unfair for Penda to refuse to pay for parts that Complete Prototype manufactured at Penda’s request. But the parties’ contract for the parts allowed Penda to terminate the order for any undelivered goods. The parties agree that Complete Prototype had not shipped the parts when Penda canceled its order, and Complete Prototype does not challenge the enforceability of the contract. Because the parties’ contract allowed Penda to terminate or modify orders before delivery, the court will grant Penda’s motion for summary judgment on the breach of contract claim. The unjust enrichment claim fails because the parties had a contract for the parts. And the remaining claims fail because Complete Prototype cannot show that the elements of conversion or account stated claims are met here, so the court will grant Penda’s motion. UNDISPUTED FACTS The following facts are undisputed unless otherwise noted. In 2017, defendant Penda Corporation submitted numerous purchase orders to plaintiff

Complete Prototype Services, Inc. for parts that would be used for a project for General Motors that was called the High Desert program. On September 21, 2017, Penda informed Complete Prototype that General Motors had issued a “Stop Build – Stop Ship notification” for the High Desert program and directed Complete Prototype to stop building or shipping productions for any outstanding purchase orders. Dkt. 30-21, at 3–4. Penda had two purchase orders in production with Complete Prototype when it sent that email: P.O. No. 259412 and P.O. No. 260132.1 The delivery dates for those orders were to be in October and November. Complete Prototype had begun production for the orders but had not shipped the parts for

either order before it received Penda’s September 21, 2017, email. The parties dispute whether Complete Prototype had completed manufacturing the parts for the two orders. On October 24, 2017, Penda informed Complete Prototype that it wanted to cancel P.O. No. 259412 and asked Complete Prototype to confirm whether the parts for P.O. No. 259412 had been shipped. Dkt. 30-20. Complete Prototype responded, “The PO in question cannot be canceled at this time, we were told to stop building assemblies on 9/21/17 . . . and by then assemblies and details were already completed.” Dkt. 35-4. (The parties do not say whether they discussed P.O. No. 260132.)

1 Complete Prototype’s complaint alleged that Penda owed it payment for three additional purchase orders. Dkt. 3-3. But Complete Prototype admits that Penda paid the invoices Complete Prototype sent for those purchase orders, so they are no longer at issue. General Motors formally terminated the High Desert program and implemented an obsolescence process for suppliers to submit claims for parts that had been produced for the High Desert program. Dkt. 30-23. At some point in 2019 General Motors conducted an audit of Complete Prototype’s inventory as part of the obsolescence process, the details and findings

of which the parties dispute. Complete Prototype demanded payment from Penda for the purchase orders that were outstanding when General Motors stopped the High Desert program. Penda said that any payment it made to its suppliers would depend on the result of Penda’s obsolescence claim with General Motors. When Complete Prototype learned that General Motors had paid Penda, it followed up with Penda to demand payment. The parties’ settlement negotiations were unsuccessful, and, in July 2022, Complete Prototype filed this lawsuit. Complete Prototype is a Michigan corporation with its principal place of business in

Michigan. Penda is a Delaware corporation with its principal place of business in Wisconsin. Complete Prototype asks the court to award more than $337,497.26 in damages. Because the parties have diverse citizenship and the amount in controversy is greater than $75,000, the court may exercise jurisdiction under 28 U.S.C. § 1332.

ANALYSIS Complete Prototype brings four state law causes of action against Penda: (1) breach of contract; (2) conversion; (3) unjust enrichment; and (4) account stated. Dkt. 3-1. Penda moves for summary judgment on each of Complete Prototype’s claims, which the parties agree are

governed by Wisconsin law. Summary judgment is appropriate only if there is no genuine dispute as to any material fact. Fed. R. Civ. P. 56(a). A genuine issue of material fact exists if “the evidence is such that a reasonable jury could return a verdict for the nonmoving party.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). In evaluating summary judgment motions, courts must view the

facts and draw reasonable inferences in the light most favorable to the non-moving party. Scott v. Harris, 550 U.S. 372, 378 (2007). A. Breach of contract The contracts at issue in this case were formed when Complete Prototype accepted the offers set out in Penda’s purchase orders: Complete Prototype would produce the goods requested in the purchase order and, in exchange, Penda would pay for the manufactured goods. Purchase order Nos. 259412 and 260132 both contain the following statement:

ALL ORDERS ARE SUBJECT TO BUYER TERMS & CONDITIONS UNLESS APPROVED BY THE BUYER IN WRITING. THE TERMS & CONDITIONS ARE SUPPLIED TO ALL SELLERS ON THE PENDA WEBSITE, BEGINNING OF EACH CALENDAR YEAR, AND ARE AVAILABLE UPON REQUEST. Dkt. 30-5; Dkt. 30-7. Complete Prototype does not dispute that this statement incorporates all provisions of Penda’s terms and conditions, and it does not challenge the enforceability of the incorporated terms and conditions. Those terms and conditions provide that “[t]he date of payment shall be . . . computed from the later of (a) Buyer’s receipt of an acceptable invoice, or (b) Buyer’s receipt of the products, together with any required documents, in apparent good order.” Dkt. 29-4, ¶ 2. The terms also contain a termination provision that states, “Buyer may, at any time, terminate or modify all or any part of the undelivered or unperformed portion of this order by written or telegraphic notice, or verbal notice confirmed in writing.” Id., ¶ 12. Taken together, these provisions mean that Penda was not obligated to pay Complete Prototype until after delivery and that Penda could cancel its order any time before the goods were delivered. Complete Prototype had not shipped any of the parts for order Nos. 259412 and 260132 when Penda directed it to stop production and shipping on any outstanding orders for

the High Desert Program on September 21, 2017. Penda was not obligated to pay for undelivered goods, so its refusal to pay for completed parts that Complete Prototype had not shipped when Penda terminated the order did not breach the parties’ contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
Carroll v. Stryker Corp.
658 F.3d 675 (Seventh Circuit, 2011)
John Anderson v. Patrick Donahoe
699 F.3d 989 (Seventh Circuit, 2012)
S & M Rotogravure Service, Inc. v. Baer
252 N.W.2d 913 (Wisconsin Supreme Court, 1977)
Estate of Newgard Ex Rel. Newgard v. Bank of America
2007 WI App 161 (Court of Appeals of Wisconsin, 2007)
H. A. Friend & Co. v. Professional Stationery, Inc.
2006 WI App 141 (Court of Appeals of Wisconsin, 2006)
Mohns Inc. v. BMO Harris Bank National Association
2021 WI 8 (Wisconsin Supreme Court, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
Complete Prototype Services, Inc. v. Penda Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/complete-prototype-services-inc-v-penda-corporation-wiwd-2024.