Complete Gen. Constr. v. Koker Drilling, Unpublished Decision (9-12-2002)

CourtOhio Court of Appeals
DecidedSeptember 12, 2002
DocketNo. 02AP-63 (REGULAR CALENDAR).
StatusUnpublished

This text of Complete Gen. Constr. v. Koker Drilling, Unpublished Decision (9-12-2002) (Complete Gen. Constr. v. Koker Drilling, Unpublished Decision (9-12-2002)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Complete Gen. Constr. v. Koker Drilling, Unpublished Decision (9-12-2002), (Ohio Ct. App. 2002).

Opinion

DECISION
{¶ 1} Third-party defendant-appellant, the city of Westerville, appeals from a judgment of the Franklin County Court of Common Pleas granting the summary judgment motion of third-party plaintiff-appellee, Complete General Construction Company.

{¶ 2} This appeal arises out of the city of Westerville's ("Westerville") construction of a bridge over Alum Creek as part of the Polaris/Maxtown Connector road project ("bridge project"). In March 1998, Complete General Construction Company ("Complete General") entered into a contract with Westerville to serve as the general contractor on the bridge project. As contemplated by the contract, Complete General subsequently entered into numerous subcontracts, including one with Koker Drilling Company ("Koker") for the installation of 40 drilled shafts that were required to establish the foundations for the piers that would support the bridge.

{¶ 3} Koker commenced work on its subcontract on July 13, 1998, intending to drill approximately one shaft per day in order to complete the work on schedule. However, the first three shafts that Koker drilled were rejected by Westerville as defective. By late November 1998, Koker had failed to drill even a single shaft that met the requirements of its subcontract. Consequently, Complete General terminated Koker's contract and hired a replacement subcontractor to drill the 40 shafts.

{¶ 4} On December 2, 1998, Complete General sued Koker for breach of contract. On January 25, 1999, Koker filed an answer, together with a counterclaim that asserted claims for breach of contract and unjust enrichment. On April 22, 1999, Complete General responded to Koker's counterclaim by filing a third-party complaint against Westerville for breach of contract, which alleged that Westerville was liable for all or part of any liability Complete General was found to have to Koker. On May 28, 1999, Westerville filed its answer to Complete General's third-party complaint together with a counterclaim. Westerville's counterclaim alleged that Complete General had "failed to honor its indemnification and hold harmless obligations [under sections 1119.06 and 1124.1 of the contract] by failing to resolve the dispute with its subcontractor Koker at no expense to Westerville and asserting affirmative claims against Westerville related to Koker's work."

{¶ 5} On June 19, 2000, Westerville moved for summary judgment on Complete General's third-party complaint. On July 14, 2000, Complete General moved for summary judgment on its claims against Koker and on Koker's counterclaim. However, before the trial court could rule on any of the pending summary judgment motions, Koker voluntarily dismissed its counterclaim. In response, Complete General voluntarily dismissed its third-party complaint against Westerville.

{¶ 6} On May 1, 2001, Westerville filed a motion for summary judgment on its third-party counterclaim seeking to recover the attorney fees it expended in defending against Complete General's third-party complaint. On May 24, 2001, Complete General moved for summary judgment on Westerville's claims against it. On November 13, 2001, the trial court issued a decision denying Westerville's motion for summary judgment, and on January 9, 2002, the court entered final judgment in the case. Westerville appeals from the trial court's decision and entry assigning the following error:

{¶ 7} "The Trial Court Committed Reversible Error By Concluding That The City of Westerville May Not Recover Its Attorney Fees From Complete General Construction Company."

{¶ 8} Preliminarily, because this matter arises out of the trial court's grant of summary judgment pursuant to Civ.R. 56, we review the trial court's determination independently, and without deference. Brown v. Scioto Cty. Bd. of Commrs. (1993), 87 Ohio App.3d 704, 711. In conducting our review, we apply the same standard as the trial court. Maust v. Bank One Columbus, N.A. (1992), 83 Ohio App.3d 103, 107. In accordance with Civ.R. 56, summary judgment may only be granted if, viewing the evidence most strongly in favor of the nonmoving party, no genuine issue of fact exists, the moving party is entitled to judgment as a matter of law, and reasonable minds can only come to a conclusion which is adverse to the nonmoving party. Harless v. Willis Day Warehousing Co. (1978), 54 Ohio St.2d 64.

{¶ 9} Westerville presents two related but distinct arguments in support of its claim to recover the attorney fees it expended in defending against Complete General's third-party complaint. First, Westerville argues that it is entitled to recover its attorney fees as compensatory damages resulting from Westerville's breach of the hold harmless provisions contained in sections 1119.06 and 1124.1 of the contract. Second, Westerville argues that section 1124.1 expressly requires Complete General to indemnify it for any attorney fees it expends as the result of claims brought by subcontractors. Complete General contends, however, that Westerville has waived its claim to recover its attorney fees as contract damages because it did not present this argument before the trial court. It is true that Westerville did not seek to recover its attorney fees as contract damages in its motion for summary judgment. However, Westerville's complaint plainly requests such relief, and Westerville's memorandum contra Complete General's motion for summary judgment can be read to request such relief. Therefore, we conclude that Westerville has not waived its right to argue that it is entitled to recover its attorney fees as contract damages on appeal.

{¶ 10} In addressing Westerville's claim to recover its attorney fees as contract damages, we initially note that the "American Rule," under which each party is responsible for paying its own attorney fees, Sorin v. Bd. of Edn. (1976), 46 Ohio St.2d 177, 179, does not prevent Westerville from recovering its attorney fees as compensatory damages resulting from a breach of contract. Shanker v. Columbus Warehouse Ltd. Partnership (June 6, 2000), Franklin App. No. 99AP-772. Nonetheless, in order to succeed on its claim to recover its attorney fees as contract damages, Westerville must establish that Complete General breached the hold harmless provisions of either section 1119.06 or 1124.1 when it filed its third-party complaint seeking to hold Westerville liable for any liability it might have to Koker. With respect to section 1119.06, Westerville claims that Complete General's third-party action breached this section because the hold harmless provision of the section required Complete General, as the general contractor, to hold Westerville, as the project owner, harmless for all subcontractor related claims arising out of the bridge project. In support of this argument, Westerville quotes the following portion of section 1119.06:

{¶ 11} "The CONTRACTOR will indemnify and save the OWNER or the OWNER'S agents harmless from all claims growing out of the lawful demands of SUBCONTRACTORS, laborers, workman, mechanics, materialmen, and furnishers of machinery and parts thereof, equipment, tools, and all supplies, incurred in the furtherance of the performance of the WORK. * * *"

{¶ 12} The interpretation of a written contract is a matter of law to be determined by the court. Alexander v. Buckeye Pipe Line Co. (1977),

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. Scioto Cty. Bd. of Commrs.
622 N.E.2d 1153 (Ohio Court of Appeals, 1993)
Maust v. Bank One Columbus, N.A.
614 N.E.2d 765 (Ohio Court of Appeals, 1992)
Skivolocki v. East Ohio Gas Co.
313 N.E.2d 374 (Ohio Supreme Court, 1974)
Sorin v. Board of Education
347 N.E.2d 527 (Ohio Supreme Court, 1976)
Alexander v. Buckeye Pipe Line Co.
359 N.E.2d 702 (Ohio Supreme Court, 1977)
Harless v. Willis Day Warehousing Co.
375 N.E.2d 46 (Ohio Supreme Court, 1978)
Kelly v. Medical Life Insurance
509 N.E.2d 411 (Ohio Supreme Court, 1987)
Aultman Hospital Ass'n v. Community Mutual Insurance
544 N.E.2d 920 (Ohio Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
Complete Gen. Constr. v. Koker Drilling, Unpublished Decision (9-12-2002), Counsel Stack Legal Research, https://law.counselstack.com/opinion/complete-gen-constr-v-koker-drilling-unpublished-decision-9-12-2002-ohioctapp-2002.