Complete Construction, LLC v. Frog Eyes, LLC

CourtMissouri Court of Appeals
DecidedNovember 22, 2022
DocketWD84051
StatusPublished

This text of Complete Construction, LLC v. Frog Eyes, LLC (Complete Construction, LLC v. Frog Eyes, LLC) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Complete Construction, LLC v. Frog Eyes, LLC, (Mo. Ct. App. 2022).

Opinion

In the Missouri Court of Appeals Western District

COMPLETE CONSTRUCTION, LLC, ) Appellant, ) v. ) WD84051 ) FROG EYES, LLC, et al., ) FILED: November 22, 2022 Respondents. )

APPEAL FROM THE CIRCUIT COURT OF JACKSON COUNTY THE HONORABLE JOEL P. FAHNESTOCK, JUDGE

BEFORE DIVISION TWO: LISA WHITE HARDWICK, PRESIDING JUDGE, THOMAS N. CHAPMAN AND JANET SUTTON, JUDGES

Complete Construction, LLC (“CCS”) appeals from the circuit court’s entry

of a judgment in favor of Frog Eyes, LLC (“Frog Eyes”) on breach of contract,

fraudulent misrepresentation, and negligent misrepresentation claims. CCS

contends the court erred in certifying the judgment as final pursuant to Rule

74.01(b) because it failed to resolve all claims and establish all rights and liabilities

within the “judicial unit.” Alternatively, CCS argues that the court erred in

denying its motion to offset the damages awarded on the breach of contract claim

based on a $250,000 settlement that Frog Eyes entered into with CCS’s insurer.

Because no final judgment has been entered, we dismiss the appeal for lack of

jurisdiction. FACTUAL AND PROCEDURAL HISTORY

In August 2016, Frog Eyes entered into a contract with CCS for general

construction work on commercial property Frog Eyes owned in Kansas City. In

November 2017, CCS sued Frog Eyes, asserting claims of breach of contract,

enforcement of mechanic’s lien, violation of Missouri’s Prompt Pay Act, fraud,

tortious interference with a business expectancy, negligent misrepresentation,

and unjust enrichment relating to the construction project. In the same petition,

CCS also sought damages relating to the project against Crossroads Financial

Management, Inc.; Doug Elstun, the owner of Frog Eyes and Crossroads Financial

Management, Inc.; David Herron d/b/a/ Herron & Partners, the architect on the

project; and Hawthorne Bank, which financed the construction work.

In response, Frog Eyes asserted a counterclaim against CCS for breach of

contract, fraud, gross negligence, trespass to chattels, and prima facie tort.

Several subcontractors on the construction project became involved in the

case, seeking damages and enforcement of their mechanic’s liens. Quality One

Stucco, LLC intervened and asserted claims against the existing parties and added

KCG, Inc. and Lennox Industries as parties. KCG, Inc. and Lennox Industries filed

responsive pleadings, answers, crossclaims, counterclaims, and third-party

petitions. Some of the subcontractors moved to join additional parties, including

MPWOB Trustee Services, LLC, which held the deed to the property in trust.

Green Field Energy Group, Inc. intervened as a third-party plaintiff. The circuit

2 court consolidated another pending matter, Apex Construction Systems, LLC v.

Frog Eyes LLC, et al., Case No. 1816-CV10614, into the case.

The parties agreed to bifurcate the trial by first trying claims between Frog

Eyes and CCS and saving the subcontractors’ claims for a later date. A jury trial

was held on some of the claims, specifically CCS’s claims of breach of contract,

fraudulent misrepresentation, and negligent misrepresentation against Frog Eyes,

and Frog Eyes’ claims for breach of contract, fraudulent misrepresentation and

prima facie tort against CCS.

The jury returned a verdict in favor of Frog Eyes on all of CCS’s claims and

on Frog Eyes’ breach of contract and fraudulent misrepresentation claims. The

jury found in favor of CCS on Frog Eyes’ prima facie tort claim. The jury awarded

Frog Eyes $782,316 in damages on the breach of contract claim.

Frog Eyes moved for entry of a final judgment based on the jury trial

verdict. CCS objected to the entry of a final judgment on the grounds that (1) the

verdict did not fully resolve at least one claim and establish all rights and liabilities

of the parties with respect to that claim, and (2) the verdict did not resolve a

discrete judicial unit required for certification of a final judgment. Specifically,

CCS asserted that the numerous remaining parties’ claims must be resolved

before a final judgment is entered because the claims “arise from the same set of

facts, and the same transactions and occurrences.” CCS also contended that it

had the right to seek a reduction of the jury’s verdict based on statements by Frog

3 Eyes that it had received a $250,000 settlement from CCS’s insurer to resolve

certain claims.

After briefing on these issues, the circuit court entered a judgment in favor

of Frog Eyes on all of CCS’s claims and on Frog Eyes’ counterclaims of breach of

contract and fraudulent misrepresentation, and in favor of CCS on Frog Eyes’

prima facie tort claim. The court awarded Frog Eyes damages of $782,316 on the

breach of contract claim and no damages on the fraudulent misrepresentation

claim. The court expressly determined that there was no just reason to delay

entry of the judgment and certified it as final under Rule 74.01(b). CCS appeals.

FINALITY OF THE JUDGMENT

Before we can address the merits of CCS’s appeal, we must first determine

if a final judgment exists. Wilson v. City of St. Louis, 600 S.W.3d 763, 765 (Mo.

banc 2020). The existence of a final judgment is a prerequisite for appellate

review under Section 512.020.1 Id. If the circuit court's judgment is not final, we

must dismiss the appeal. Id.

A “final judgment” pursuant to Section 512.020(5) must: (1) “be a judgment

(i.e., it must fully resolve at least one claim in a lawsuit and establish all the rights

and liabilities of the parties with respect to that claim)” and (2) “be ‘final,’ either

because it disposes of all claims (or the last claim) in a lawsuit, or because it has

been certified for immediate appeal pursuant to Rule 74.01(b).” Id. at 771.

1 All statutory references are to the Revised Statutes of Missouri 2016, as updated by the 2020 Cumulative Supplement. 4 Pursuant to Rule 74.01(b), the circuit court may certify for immediate appeal

a judgment on fewer than all claims upon finding there is “no just reason for

delay” of the appeal. Rule 74.01(b). The circuit court’s determination in this

regard is not dispositive, however. Wilson, 600 S.W.3d at 771 (citations omitted).

Rather, it is the “content, substance, and effect of the order.” Id. (citations

omitted). Whether a judgment is eligible for certification under Rule 74.01(b) is a

question of law. Taylor v. Curators of Univ. of Mo., 602 S.W.3d 851, 854, n.4 (Mo.

App. 2020).

A judgment may be certified under Rule 74.01(b) “only if it disposes of a

‘judicial unit’ of claims, meaning it: (a) disposes of all claims by or against at least

one party, or (b) it disposes of one or more claims that are sufficiently distinct

from the claims that remain pending in the circuit court.” Id. “[W]here a

dispositive ruling does not wholly resolve all claims brought by or against a

particular party, it only involves a discrete ‘judicial unit’ if it disposes of one or

more claims that are sufficiently distinct from the claims that remain pending in

the circuit court.” Id. (citations omitted).

In this case, the judgment does not meet either of the criteria to be certified

under Rule 74.01(b). First, the judgment does not dispose of all claims by or

against at least one party because Frog Eyes’ counterclaims against CCS for gross

negligence and trespass to chattels remain pending. Frog Eyes argues that it

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
Complete Construction, LLC v. Frog Eyes, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/complete-construction-llc-v-frog-eyes-llc-moctapp-2022.