Compagno

2 Pelt. 204
CourtLouisiana Court of Appeal
DecidedApril 3, 1919
DocketNo. 7443
StatusPublished

This text of 2 Pelt. 204 (Compagno) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Compagno, 2 Pelt. 204 (La. Ct. App. 1919).

Opinions

CHARLSS F. CLAIB0RK3, JUDGE.

On March 8th., 1917, plaintiff, Mrs. J. Compagno, the owner, made a written contract with Edwin L. Markel, contractor, to sheet a building for the price of $2770.40, payable in five installments of $554.08 each; the fourth payment "when the house is accepted and completed", and the fifth and last payment "forty-five days after".

The United States Fidelity and Guaranty Company signed Jiarkel's, the contractor's, bond for $1385.20.

Markel erected the building. By a writing dated June 29th., 1917, recorded in the mortgage office on the next day, June 30th., Mrs. Compagno stated:

"Notice is hereby given to all whom it may concern that I did on the 18th. day of May, 1917 accept tht-completed building erected by Edwin L. Markel, contractor &o.".

Mrs. Compagno made four payments to Markel, amounting to $2216, leaving unpaid only the fifth and last payment of $554.5?.The payments were made on March 16, 22, 31st. and the fourth payment on May 18th,, 1917.

But the men who furnished the materials towards the building claimed that they had not been naid. The following materialmen filed sworn accounts with Mrs. Compagno and recorded them in the mortgage office, viz:

lo June 29th., 1917, F. \V. Devoe and
C. T. Reynolds & Co. 13.30
2o " " " Geo. H. Baindei 215.00
3o " " " John H. Gaignard 185.00
4o " " " Salmon Brick & lumber Co. 33.50
5o " " " Henry Scheibe 67.65
6° " " " Carolina Portland Cement Co. 43.25
7o " " " Jordy Bros. Slate Co. 225.00
[206]*20680. June 29th., 1917, Miller-Goll Manfg. Co. 380.82
9o " " " J. Iff. Thompson 117.31
10. " 38th., " W. W. Carre 543.66
llo July 2nd., " Jos. B. CraBto 34,00
Making a total of & j.BdB.42

Thereupon Mrs. Compagno filed these concursus proceeding?, deposited the last installment of $554.08 remaining in her hands in the registry of the Court, for distribution among the mater-ialmen; she cited^surety and all the materialmen, and asked to be relieved of all further liability, and that the privileges recorded by the materialmen be cancelled.

lo Devoe & Raynolds answered claiming a judgment against the owner and the surety with privilege.

2o Haindel prayed for judgment against the owner, the contractor and his surety.

3o Gaignard charges that the payments were made in anticipation, that the contract and bond were not recorded within the time required by law, and he prays for judgment against the owner, the contractor, and his surety.

4o The Salmen Brick and Lumber Co. prayed for judgment against the owner, the contractor and his surety,

5o Scheibe answered that the payments were made in anticipation and prayed for judgment also against the above named three parties.

6o The Carolina Portland Cement Company aver that the payments were made in anticipation, that the other accounts were not served in time upon the owner, and asks for judgment also against all three above parties.

7o Jordy Brothers allege that the contract and bond were not recorded in time and they pray for judgment against all. three parties also.

8o The Miller - Goll Manufacturing Company charges that the contract and bond were not recorded in time and that therefore the owner is liable to it as well as the contractor and surety.

9o J. ',T. Thompson makes the. seme allegations and nr ayer.

[207]*20710o So do the. Carre Company.

llo Crasto excepted that the petition set forth no cuase of action and that the Court tos without jurisdiction because he had filed suit upon his claim in the City Court and had obtained against' lírs. Compagno a judgnent from which an appeal was presently pending before the Court of Appeal* Tho judgnent fails to pass upon thebe points, and Crasto has not appealed nor prayed for an amendment of the judgnent. We cars* not consider his exceptions.

For answer he demands judgnent against the plaintiff and the surety.

Edwin I. ICarkel, through his trastee in bankruptcy, alleged that the contract was for $2855, and plaintiff having paid only $2216.32, remains owing him $638.68 which he claims both against the owner and his own surety.

The Surety Company pleaded vagueness, non-joinder of defendants, and no cause of action. ' These exceptions were not pressed upon appeal and must be considered as abandoned.

For answer the Surety Company admitted the building contract and its signature to the bond, but denied that the . payments had been made or that they had been made as they be- . came due , and averred that there had been alterations and extra work done.by the contractor for which the plaintiff was responsible; it admitted tha acceptance of the building as alleged.; it denied that the materialmen'had "given credit for all the materials returned or payments made respectively to than", and it prayed for judgnent against the plaintiff dismissing her suit.

Howard J. Jonee intervened claiming to have done work apd furnished, materials necessary for the electric wiring of the building amounting to $45.50 less a part payment of $5.Cb for which he prayed judgnent.

The matter was referred to a commissioner.

He did not pass upon the question of the liability of the owner to the materialmen, for the reason, as stated by him, that the sum deposited in Court and the amount for which the surety was liable were more than sufficient to pay all claims [208]*208as reduced by him. Tlie liability of the owner has not been pressed in this Court and we shall not pass upon it either.

The Commissioner found that at the time the material-men in this cause were supplying itarkel with materials to execute the contract in this case^ I/aiksl had on hand seven several contracts for which they were supplying him; and that while the materialmen were careful to identify the particular building to which the materials went, they kept with the contractor only one general account which was charged with all mo/cerials furnished and credited with all payments made, without inquiring from what source the contractor derived the money paid ’oy him and without imputing the payment to.the materials furnished to any particular building, and without directions from the contractor as to what building to credit.

Under the circumstances the Comissioner was of opinion that the payments made by the contractor to the furnishers of materials during the time of this contract from liarch 8th. to Stay 13th. ahould be distributed in the proportion of one-seventh each among all the materialmen who had furnished materials during that time. The Commissioner was guided by the following authorities quoted by him, viz: 6 N. S., 113; 3 R., 361; 2 A., 24; 3 A., 351; 4 A., 509; 9 A., 455; 13 A., 294; 36 A., 312; 115 La., 1051.

Some of those decisions maintain the proposition that payments must be imputed proportionally to debts of an equal nature and all due.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marks v. Drovers' National Bank
6 A. 774 (Supreme Court of Pennsylvania, 1886)
Reading & Pottsville R. v. Balthaser
13 A. 294 (Supreme Court of Pennsylvania, 1888)
Schuey v. Schaeffer
18 A. 544 (Supreme Court of Pennsylvania, 1889)
Smith's Estate
25 A. 315 (Supreme Court of Pennsylvania, 1892)
Henderson v. Allegheny Heating Co.
36 A. 312 (Supreme Court of Pennsylvania, 1897)
Leonard v. Leonard
11 A. 447 (Supreme Court of Pennsylvania, 1887)
Potts ex rel. Wollerton v. Smith
3 Rawle 361 (Supreme Court of Pennsylvania, 1832)
Beal v. Alexander
7 La. 349 (Supreme Court of Louisiana, 1844)
Cox v. Rees
10 La. 232 (Supreme Court of Louisiana, 1836)
Pargoud v. Griffing's Administrator
10 La. 356 (Supreme Court of Louisiana, 1836)
Forstall & Co. v. Blanchard
12 La. 1 (Supreme Court of Louisiana, 1838)
Lang v. Their Creditors
14 La. 237 (Supreme Court of Louisiana, 1840)
Hughes v. Mattes
104 La. 231 (Supreme Court of Louisiana, 1900)
Burbank v. Buhler
108 La. 39 (Supreme Court of Louisiana, 1902)
Metoyer v. Trezzini
6 Rob. 124 (Supreme Court of Louisiana, 1843)
Collier v. Stanbrough
6 Rob. 230 (Supreme Court of Louisiana, 1843)
Coles v. First Baptist Church
35 A. 907 (Supreme Court of New Jersey, 1896)

Cite This Page — Counsel Stack

Bluebook (online)
2 Pelt. 204, Counsel Stack Legal Research, https://law.counselstack.com/opinion/compagno-lactapp-1919.