Community Properties, Inc. v. Neely

611 S.W.2d 947, 1981 Tex. App. LEXIS 3252
CourtCourt of Appeals of Texas
DecidedFebruary 5, 1981
DocketNo. 1412
StatusPublished
Cited by4 cases

This text of 611 S.W.2d 947 (Community Properties, Inc. v. Neely) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Community Properties, Inc. v. Neely, 611 S.W.2d 947, 1981 Tex. App. LEXIS 3252 (Tex. Ct. App. 1981).

Opinion

MOORE, Justice.

Appellees, Clyde Neely and wife, Annie May Neely, siied appellants, Community Properties, Inc., and Mesa Village Apartment Company, for damages caused by the diversion of surface water by appellants onto a 3.1-acre tract of land owned by the Neelys and occupied by them as their home. Appellees alleged that appellants constructed a large apartment complex on property adjacent to their home and in so doing materially altered the natural flow of surface water causing it to flow across their property which resulted in damage to their yard, sidewalk, and driveway. Pleading in the alternative, appellees alleged that the continual flooding of their property consti[949]*949tuted a temporary nuisance and sought damages for the loss of the rental value of two apartments situated on the property and damages for personal discomfort and annoyance. Pleading further in the alternative, appellees alleged that the flooding of their property was a permanent nuisance and sought damages for the depreciation in the market value of their property. Appel-lees further alleged in the alternative that appellants were guilty of negligence per se in impounding and diverting the surface water from the apartment complex onto their property. In addition, appellees sought exemplary damages and prayed for an injunction against appellants to prevent them from diverting the flow of the surface water. Appellants answered with a general denial.

The jury found (a) that appellants diverted or impounded the natural flow of surface water on their own property in a manner that caused damage to the property of Mr. & Mrs. Neely as a result of the overflow of the water so diverted or impounded, (b) that damage to the Neely property was “permanent,” (c) that the difference in the market value of the Neely property before and after July 1978 was $40,000, (d) that the diversion of the water from appellants’ apartment complex onto the property of the Neelys constituted a nuisance, (e) that the nuisance was temporary, (f) that the difference in the rental value of the Neely property before and after July 1978 was zero, and (g) that Mr. & Mrs. Neely each suffered damages in the amount of $1,000 as a result of personal discomfort, inconvenience, and annoyance. The jury further found that appellants, after learning that the water from the apartment complex was flowing onto the Neely property, failed to take adequate action to prevent the condition from occurring again; that appellants acted with “malice” in failing to take adequate action; and that the Neelys should be awarded exemplary damages in the amount of $20,-000. Pursuant to the foregoing findings, the trial court rendered judgment on the verdict in favor of the Neelys for the total sum of $62,000, from which judgment appellants perfected this appeal.

Appellants’ second point merits first consideration. Under this point, appellants seek a reversal on the ground that the trial court erred in submitting Special Issue No. 2 over their objection because said issue required the jury to find whether the damage to the Neely property was “temporary” or “permanent.” Appellants objected to the submission of the issue in the form adopted by the trial court on the ground that the evidence, as a matter of law, established that the injury to the Neely property was temporary only. Therefore, they argue that the court erred in submitting the issue of permanency to the jury. After a careful review of the record and the authorities cited by the parties, we are of the opinion that reversible error is presented.

The record reveals that on or about September 22, 1977, appellant, Community Properties, Inc. (CPI), filed an application with the city of Austin, Texas, for a permit to construct an apartment project to be known as Mesa Village Apartments. In the course of this construction project, CPI secured the proper authorization from the city of Austin and other regulatory agencies regarding the environmental impact upon the surrounding property, including surface water diversion, caused by the construction of the apartment complex. Such authorization specifically included a requirement that CPI construct retention ponds to contain water run off so that it would be discharged onto adjacent property at no greater quantity or velocity than had been the case in the natural state. The water was to be held in retention ponds by the use of dirt berms about two feet high. The retention ponds were to be drained with eight inch pipes installed under the berms. Several of the drainage pipes were installed so that they pointed toward the Neely property.

During July 1978, while the apartment complex was still under construction, a heavy rain storm caused temporary drainage facilities on the apartment property to be washed out which resulted in the flow of water across the Neely property. Appellants were contacted by Neelys’ counsel and [950]*950steps were taken to repair the berms which had been washed out. Over the course of the next eight or ten months, rains again washed out the dikes and retention ponds on three or four separate occasions. In each instance, appellants repaired the retention ponds and commenced making some changes in the drainage system in an effort to alleviate the problem. The evidence shows that even during moderate rains the water draining out of the retention ponds washed across Neely Street situated in front of the Neely home and then onto their front yard.

In their testimony, the Neelys claimed damages to their yard, trees, grass, sidewalk, driveway, and to Neely Street which was situated on the 3.1-acre tract. On one occasion, they testified that their front porch was covered with two inches of water. There is no evidence, however, that any water ever entered their home or their apartment house nor is there any evidence that either structure was damaged by water. With regard to personal injury suffered by the Neelys, Mrs. Neely testified that she was suffering with cancer and that the overflow of water and the fear of her home being flooded had annoyed her to such an extent that she was continually nervous and unable to eat or sleep properly. Mr. Neely testified that the overflow was such an annoyance to him that he could no longer live there. Both Mr. and Mrs. Neely acknowledged that the overflow occurred only when it rained.

As the construction of the apartment complex neared completion in December 1978, appellants’ consulting engineer, G. W. Thompson, was instructed to address the run-off problem and prepare a plan to resolve the situation. After Thompson’s plan had been approved by the city of Austin, he commenced work on the project. He decreased the size of the retainage ponds, put rock in the drainage area, and installed traffic stops in the parking area, which he testified were designed to decrease the amount and the velocity of the water draining toward the Neely property. He testified that such work had stopped the drainage into the retention ponds by fifty percent. He further testified that at the time of trial on August 13, 1979, his plans had not been completed and that when completed the drainage problem would meet the requirements of the city of Austin.

Both parties offered expert testimony on the question of whether the overflow could be abated or terminated. W. C. Cotton, an expert witness called by the Neelys, testified that the problem could be abated by the construction of an underground storm sewer constructed on the edge of Neely Street at a cost of $34,638.00. Isom Hale, an expert witness called by appellants, likewise testified that the water problem could be solved by the construction of a storm sewer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Amoco Production Co., Inc. v. Thompson
657 S.W.2d 824 (Court of Appeals of Texas, 1983)
Neely v. Community Properties, Inc.
639 S.W.2d 452 (Texas Supreme Court, 1982)
Burk Royalty Co. v. Walls
616 S.W.2d 911 (Texas Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
611 S.W.2d 947, 1981 Tex. App. LEXIS 3252, Counsel Stack Legal Research, https://law.counselstack.com/opinion/community-properties-inc-v-neely-texapp-1981.