Commonwealth v. Michael D. Thompson.

CourtMassachusetts Appeals Court
DecidedMarch 20, 2024
Docket23-P-0196
StatusUnpublished

This text of Commonwealth v. Michael D. Thompson. (Commonwealth v. Michael D. Thompson.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commonwealth v. Michael D. Thompson., (Mass. Ct. App. 2024).

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

23-P-196

COMMONWEALTH

vs.

MICHAEL D. THOMPSON.

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

The defendant was convicted of larceny over $1,200 by false

pretenses in a jury-waived trial in the District Court. At the

close of the Commonwealth's case and again at the close of all

the evidence, the defendant moved for a required finding of not

guilty. The judge denied both motions, and ultimately found the

defendant guilty. After being sentenced to a six-month

commitment in the house of correction, the defendant filed a

renewed motion for a required finding of not guilty, which was

denied. On appeal, the defendant argues that the judge erred in

denying his motions for a required finding of not guilty because

the Commonwealth failed to present sufficient evidence to

sustain his conviction. We affirm.

Background. We summarize the background of this case in

the light most favorable to the Commonwealth. See Commonwealth v. Latimore, 378 Mass. 671, 676-678 (1979). Ken Dedominici owns

Speedway Amusements LLC, located in East Bridgewater. The

defendant owned ASK Construction Company (ASK). In early June

2019, Dedominici met the defendant at his East Bridgewater

property to discuss erecting a building on the site. The

defendant gave Dedominici a proposal for the project that

included a "building deposit" of $21,355 and a "building payoff"

of $72,611.75. As part of these deposits, Dedominici gave the

defendant a check in the amount of $16,000 (check one) on or

around August 15, 2019, with the defendant's company ASK as the

recipient, and later a second check on or around September 10,

2019, also made out to ASK, in the amount of $5,355 (check two).

Dedominici and the defendant agreed that the defendant would

send the money from these checks to Chief Buildings (Chief), a

company specialized in the creation of steel buildings. Based

on his conversations with the defendant before he wrote checks

one and two, Dedominici understood that his upfront payment was

necessary so that Chief could create engineer-stamped drawings

of the building and begin construction of the building offsite. 1

The engineer-stamped drawings provided by Chief were necessary

1 Dedominici's testimony was inconsistent regarding whether checks one and two were purely for the purpose of receiving drawings of the building or if they were also intended for Chief to begin construction of the building. Because we essentially conclude that it was the defendant's later actions that were criminal, we need not resolve this inconsistency.

2 in order to obtain building permits. It was agreed that once

Chief delivered the constructed building, the defendant would

then erect the building on site. The defendant provided

Dedominici with the stamped drawings prepared by Chief and the

project appeared to be progressing as expected.

On November 6, 2019, the defendant gave Dedominici an

invoice for $72,611.75. The defendant told Dedominici that "the

building was ready and it was going to be delivered in two

weeks, so [Dedominici] needed to make a final payment so [the

defendant] could pay for the building." The defendant said he

"was a little bit short on the money [and] that it was required,

because Chief required [the defendant] to pay 100 percent of the

building up front to get it delivered." Dedominici paid the

balance owed in the amount of $72,611.75 by check made out to

ASK (check three). The defendant put Dedominici's money into

ASK's general account and used it "for everything from fuel to

truck rentals, equipment rentals, workers' comp insurance,

payroll." Despite Dedominici making the payments to the

defendant, the building was never delivered.

Chief's normal procedure was that a contractor would meet

in person or speak over the phone with a Chief employee to

discuss any drawings or plans they might have for a customer.

The Chief employee would then enter relevant information into a

computer program that would generate a design and a price. This

3 information was then typically used to build the building once

it was paid for by the contractor. If the contractor was a

certified builder authorized to use Chief's computer program

themselves to generate pricing, Chief would not require advanced

payment but typically would accept cash on delivery. Once the

building was built, a Chief employee would contact the

contractor and tell them that the building was ready to be

delivered by Chief.

Around the same time the defendant entered into a contract

with Dedominici, the defendant also became a certified Chief

builder and completed a different project as a certified

builder. Inferentially, then, he knew that obtaining the status

of a certified Chief builder allowed the defendant to enter

building information into the Chief computer program himself and

allowed him to wait until delivery to pay Chief. Accordingly,

at the time the defendant presented Dedominici with an invoice

for $72,611.75, accompanied by a statement that payment of that

amount was required for Chief to deliver the building, the

defendant was aware that such payment was not in fact required.

The defendant entered the measurements of the building into the

Chief computer program, received a price, and alerted Wayne

Hickey, a regional sales manager at Chief, that billing would

"be in order." Chief prepared a standard written agreement for

the defendant to order a building. The defendant signed the

4 form and sent an email message back, and Chief began

constructing the building.

A couple of weeks before November 27, 2019, what Chief

understood to be the anticipated delivery date, and within days

of receiving check three under the premise that it was required

for delivery, the defendant contacted Hickey and stated that the

delivery would have to be postponed. After this conversation,

Hickey was unable to get in touch with the defendant regarding

this project and was in possession of the constructed building.

By November 19, 2019, Hickey had only received $3,600 from the

defendant in relation to the construction of this building.

The building never arrived and was accordingly never

erected. At some point after he told Hickey to stop delivery of

the building and stopped communicating with Hickey, in an effort

to justify the delays, the defendant told Dedominici that his

daughter had died. The defendant's daughter had not, in fact,

died. Although Chief was prepared to deliver the building on or

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth v. Sheline
461 N.E.2d 1197 (Massachusetts Supreme Judicial Court, 1984)
Commonwealth v. Latimore
393 N.E.2d 370 (Massachusetts Supreme Judicial Court, 1979)
Commonwealth v. Long
90 Mass. App. Ct. 696 (Massachusetts Appeals Court, 2016)
Commonwealth v. Barry
116 N.E.3d 554 (Massachusetts Supreme Judicial Court, 2019)
Commonwealth v. O'Laughlin
843 N.E.2d 617 (Massachusetts Supreme Judicial Court, 2006)
Commonwealth v. Whitaker
951 N.E.2d 873 (Massachusetts Supreme Judicial Court, 2011)
Commonwealth v. Oliver
805 N.E.2d 1019 (Massachusetts Appeals Court, 2004)
Commonwealth v. Williams
827 N.E.2d 1281 (Massachusetts Appeals Court, 2005)
Commonwealth v. Cheromcka
850 N.E.2d 1088 (Massachusetts Appeals Court, 2006)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Commonwealth v. Michael D. Thompson., Counsel Stack Legal Research, https://law.counselstack.com/opinion/commonwealth-v-michael-d-thompson-massappct-2024.