Commonwealth v. Croner, Inc.

618 A.2d 1135, 152 Pa. Commw. 144, 1992 Pa. Commw. LEXIS 727
CourtCommonwealth Court of Pennsylvania
DecidedDecember 4, 1992
Docket1789 C.D. 1990; 2676 C.D. 1991 and 233 C.D. 1992
StatusPublished

This text of 618 A.2d 1135 (Commonwealth v. Croner, Inc.) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commonwealth v. Croner, Inc., 618 A.2d 1135, 152 Pa. Commw. 144, 1992 Pa. Commw. LEXIS 727 (Pa. Ct. App. 1992).

Opinion

LORD, Senior Judge.

These cases present appeals by the Department of Environmental Resources (DER) from decisions by the Environmental Hearing Board (EHB) which, on cross motions for summary judgment, invalidated certain regulations of DER because they violated the terms of a statute.

This same case was previously appealed to this Court and the facts have been meticulously outlined in the opinion rendered in that appeal. Croner, Inc. v. Dept. of Environmental Resources, 139 Pa. Commonwealth Ct. 43, 589 A.2d 1183 (1991). We quote from that opinion those basic facts necessary for an understanding of the instant opinion. We said:

Croner is a coal mine operator. In April 1982, Croner submitted ‘Module 16: Blasting Plan’ to the department. The plan included a notarized signed release from John J. and Evelyn Hartman. The affidavit provides in pertinent part:
To Whom It May Concern,
We, the undersigned, John H. Hartman and Evelyn Hartman, do hereby grant permission to Croner, Inc. the right to conduct overburden blasting operations within the 300 foot barrier surrounding our buildings.
We do hereby also grant the right to Croner, Inc. to exceed the one inch per second particle velocity requirement and the 132 DB air overpressure requirement so [147]*147mining operation can be achieved to remove the coal near our buildings.
The area is covered by S.M.P., # 56663094, Brothersvalley Township, located near Twp. Rte. T-145.
On April 28, 1987, the department approved Croner’s blast plan, as part of the surface mining permit previously issued to Croner, subject to the following conditions:
1. When the Scale distance falls below sixty (60) at the Hartman residence or any dwelling, a peak particle velocity of one (1) inch per second and an air over pressure of 132 dBL must be maintained.
2. John and Evelyn Hartman cannot release the vibration limit of one (1) inch per second and 132 dBL air over pressure when blasting oceúrs closer than 300 feet to their dwelling.

Croner, 139 Pa. Commonwealth Ct. at 45-46, 589 A.2d at 1184.

In addition, Croner I at 47-48, 589 A.2d at 1185, outlined the interrelationship between the federal law, the Surface Mining Control and Reclamation Act, 30 U.S.C. § 1201 et seq., and The Pennsylvania Surface Mining Conservation and Reclamation Act.1 When Congress enacted the federal SMCRA providing for comprehensive surface coal mining and reclamation regulation, it authorized states to retain primary jurisdiction over such regulation by submitting a state regulatory program to the United States Office of Surface Mining for approval. The federal SMCRA requires states wishing to retain primary jurisdiction over regulation in this field to issue regulations consistent with those issued by the United States Secretary of the Interior. The United States Code of Federal Regulations, in turn, sets forth minimum standards of environmental protection adopted by the secretary pursuant to his regulatory authority under the federal SMCRA.2

[148]*148In previous proceedings, the EHB had determined that it had no jurisdiction to decide certain constitutional questions and that Croner, the mine operator, had waived any contention that certain regulations were violative of a section of SMCRA.

This court on appeal held (1) the EHB had jurisdiction to decide the constitutional question and (2) Croner had not waived the issue that certain regulations were violative of the statute.

Hence, we entered the following order:

NOW, April 8, 1991, the decision of the Environmental Hearing Board dated July 26, 1990, at No. 87-206-E, is reversed and this case is remanded. On remand, the board is to consider whether 25 Pa.Code § 87.127 creates a class distinction with no rational basis, and whether 25 Pa.Code § 87.127 violates a statutory right set forth in 52 P.S. § 1396.4b(c).

Pursuant to this order, the EHB, based on affidavits and a stipulation of facts, determined that the regulations were violative of the statute, found it unnecessary to consider the constitutional question, denied DER’s motion for summary judgment and granted Croner’s motion for summary judgment. The EHB decision, while unanimous in disposing of the summary judgment motions, contained a concurring and dissenting opinion. Reargument was then allowed and the original conclusion was sustained with a further opinion.

The crux of the controversy in this appeal involves Section 3 of the SMCRA, 52 P.S. § 1396.4b(c), which states'

From the effective date of this act, as amended hereby, no operator shall conduct surface mining operations (other than borrow pits for highway construction purposes) within one hundred feet of the outside line of the right-of-way of any public highway or within three hundred feet of any occupied dwelling, unless released by the owner thereof, nor within three hundred feet of any public building (emphasis added),

and the regulation at 25 Pa.Code § 87.127

(e) An airblast shall be controlled so that it does not exceed the noise level specified in this subsection at a [149]*149dwelling, public building, school, church or commercial or institutional structure, unless the structure is owned by the person who conducts the surface mining activities and is not. leased to another person. The lessee may sign a waiver, relieving the operator from meeting the airblast limitations of this subsection.
(h) In blasting operations, except as otherwise authorized in this section, the maximum peak particle velocity may not exceed 1 inch per second at the location of a dwelling, public building, school, church, or commercial or institutional building or other structure designated by the Department. Peak particle velocities shall be recorded in three mutually perpendicular directions. The maximum peak velocity shall be the largest of any of three measurements. The Department may reduce the maximum peak particle velocity allowed, if it determines that a lower standard is required because of density of population or land use, age or type of structure, geology or hydrology of the area, frequency of blasts or other factors.
(i) The maximum peak particle velocity limitation of subsection (h) does not apply at the following locations:
(1) At structures owned by the person conducting the mining activity, and not leased to another party.
(2) At structures owned by the person conducting the mining activity, and leased to another party, if a written waiver by the lessee is submitted to the Department prior to blasting.

In considering these two provisions,3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Croner, Inc. v. Department of Environmental Resources
589 A.2d 1183 (Commonwealth Court of Pennsylvania, 1991)
Commonwealth v. Glasgow Quarry, Inc.
351 A.2d 689 (Commonwealth Court of Pennsylvania, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
618 A.2d 1135, 152 Pa. Commw. 144, 1992 Pa. Commw. LEXIS 727, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commonwealth-v-croner-inc-pacommwct-1992.