Commonwealth v. Bessette

217 N.E.2d 893, 351 Mass. 148, 1966 Mass. LEXIS 624
CourtMassachusetts Supreme Judicial Court
DecidedJune 15, 1966
Docket1
StatusPublished
Cited by5 cases

This text of 217 N.E.2d 893 (Commonwealth v. Bessette) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commonwealth v. Bessette, 217 N.E.2d 893, 351 Mass. 148, 1966 Mass. LEXIS 624 (Mass. 1966).

Opinion

Ctjttee, J.

Bessette, one LeBlanc, and one Paquette were charged in indictments, 1 returned in November, 1961, *149 with conspiracy to violate art. 65 of the “Standard Specifications” 2 of the Division of Waterways (the division) of the Department of Public Works (the department) in connection with certain dredging contracts. To each contract the Commonwealth through the department and the division was a party. See Commonwealth v. Bessette, 345 Mass. 358. Bessette, who in 1959 and 1960 was the head of the division, was found guilty on each indictment. Our discussion of the motions to quash the indictments will be clarified by a brief summary of the background of the case shown by the evidence.

The commissioners of the department on June 1, 1960, after a considerable delay voted to award, upon three sets of bids, 3 dredging contracts to the low bidders, as follows: contract No. 2074 (Popponesset Bay and Creek, Mashpee) *150 to Marine Dredging Corp. (Dredging); contract No. 2038 (Buttermilk Bay, Wareham) to Marine Development Company (Development); and contract No. 2063 (Parker’s River, Yarmouth) also to Development. The contracts were thereafter executed.

Contract No. 2074 was the culmination of a long effort to have the Popponesset area dredged. Interests controlled by the Chaces had planned a real estate development on land surrounding Popponésset Creek. In 1949 and 1955 applications to dredge the creek at private expense had not been approved. Subsequent efforts were made by the Chace interests to get the department to do such dredging on a basis by which, at least in 1956, the Chace interests were to contribute to Mashpee the town’s share of the expense. Similar efforts were made in 1958 before the Legislature. See 1958 Senate Bill No. 303; 1958 House Bills Nos. 554, 3257; St. 1958, c. 647. On September 10,1959, an engineer for the division was instructed by Bessette to make a survey for a “harbor of refuge for small boats” in the Popponesset area, and eventually a project at Pop-ponesset was adopted.

Sometime in February, 1960, one Buswell, an employee of the Chaces, partners in Development, told Bessette that Development wanted to exchange contracts-Nos. 2038 (Buttermilk Bay) and 2063 (Parker’s River), both later awarded to Development, for No. 2074 (Popponesset) which was later awarded to Dredging. Bessette made suggestions with respect to this exchange.

In May, 1960, Wilson, an officer in various Chace enterprises, and Dr. LeBlanc, a director of Dredging, met. Wilson told Dr. LeBlanc that he would not let Dredging place dredged material from Popponesset Creek on the Chace land. Dr. LeBlanc on May 31, I960, saw Bessette in Well-fleet. On June 1, Dr. LeBlanc with Paquette, Dredging’s president and treasurer, met Wilson again. At this conference, it was agreed that Development would do the Pop-ponesset job and Dredging would do the “other two jobs . . . with a price differential ... in favor of” Develop *151 ment. An attorney for the Chaces on June 1, 1960, drew up a memorandum 4 and subsequently a more formal letter agreement dated June 2, 1960, to similar effect was executed.

After the meeting on June 1, Wilson reported by telephone to Bessette “about swapping the contract[s].” The contracts were awarded on June 1.

During the summer of 1960 efforts were made to obtain departmental permission for Development to subcontract to Dredging contracts Nos. 2038 and 2063, and for Dredging to subcontract contract No. 2074 to Development. Despite a subordinate’s adverse recommendation on contract No. 2074, Bessette recommended approval of the requests to subcontract all three contracts. The commissioners denied these requests.

The voluminous record need not be more fully stated. We recognize, of course, that, although it is not necessary for us to consider the evidence in detail, the trial judge would have been warranted in concluding (a) that Bessette delayed recommending award of the contracts until the low bidders agreed to assign and “swap” them; (b) that the awards followed promptly upon the “swap” arrangement; (c) that Bessette was fully informed about that arrangement; (d) that Bessette never told the commissioners of the actual arrangement but instead took precautions to conceal it in the face of the commissioners’ specific refusal to allow the “swap”; (e) that Bessette, for reasons not wholly plain from the evidence, was actively supporting Development’s efforts to do the dredging at Popponesset in which the Chaces had a special interest because of their land ownership; and (f) that these actions were in some degree pursuant to an understanding with representatives of Development. It could have been found that art. 65 had been employed steadily for the protection of the Commonwealth’s interests as a part of the division’s contracting policy for *152 many years. There was other evidence which tended to cast doubt on the propriety of the transactions.

There was evidence that the work called for by the Parker’s Eiver and the Popponesset Bay contracts had been fully completed in accordance with the areas and quantities prescribed by the contracts and that payment for each contract had been approved and made. Payment for the work done at Buttermilk Bay had not been made.

The cases are before us (a) on three bills of exceptions dealing with the denial of motions to quash the indictments which were heard by one judge of the Superior Court and (b) upon a substitute bill of exceptions allowed by a different judge who presided at the actual trial. The substitute bill included exceptions to the denial (a) of the motions to quash, and (b) of motions for findings of not guilty, which we need not consider.

1. The three identical motions to quash assert principally that each indictment sets forth no offence. They also assert that there is no averment of any “prejudice to the general public or oppression of any individual.”

In Commonwealth v. Dyer, 243 Mass. 472, 485, it was said, “It is the consensus of opinion that conspiracy as a criminal offence is established when the object of the combination is either a crime, or if not a crime, is unlawful, 5 or when the means contemplated are either criminal, or if not criminal, are illegal, provided that, where no crime is contemplated either as the end or the means, the illegal but non-criminal element involves prejudice to the general welfare or oppression of the individual of sufficient gravity to be injurious to *153 the public interest.” See Commonwealth v. Hunt, 4 Met. 111, 123 (see, however, pp. 127-136); Commonwealth v. Waterman, 122 Mass.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth v. Cabral
819 N.E.2d 951 (Massachusetts Supreme Judicial Court, 2005)
In re the Enforcement of a Subpoena
753 N.E.2d 145 (Massachusetts Supreme Judicial Court, 2001)
Commonwealth v. Brown
460 N.E.2d 606 (Massachusetts Supreme Judicial Court, 1984)
Commonwealth v. Gill
363 N.E.2d 267 (Massachusetts Appeals Court, 1977)
Commonwealth v. Kelley
268 N.E.2d 132 (Massachusetts Supreme Judicial Court, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
217 N.E.2d 893, 351 Mass. 148, 1966 Mass. LEXIS 624, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commonwealth-v-bessette-mass-1966.