Commonwealth of Virginia v. Asphalt Roads

Court of Appeals of Virginia·Decided March 3, 1998·No. 1665971·Unpublished

Opinion

COURT OF APPEALS OF VIRGINIA

Present: Judges Baker, Willis and Overton Argued at Norfolk, Virginia

COMMONWEALTH OF VIRGINIA, DEPARTMENT OF TRANSPORTATION AND WILLIAM E. LANDSIDLE, COMPTROLLER OF THE COMMONWEALTH MEMORANDUM OPINION * BY

v. Record No. 1665-97-1 JUDGE JERE M. H. WILLIS, JR.

MARCH 3, 1998

ASPHALT ROADS & MATERIALS CO., INC.

FROM THE CIRCUIT COURT OF THE CITY OF VIRGINIA BEACH Frederick B. Lowe, Judge

Mark S. Paullin, Assistant Attorney General (Richard Cullen, Attorney General, on briefs), for appellants.

Jack Rephan (Beth Hirsch Berman; Hofheimer, Nusbaum, McPhaul & Samuels, P.C., on brief), for appellee.

The Commonwealth of Virginia, Department of Transportation (VDOT) appeals a judgment of the trial court granting additional compensation to Asphalt Roads & Materials Co., Inc. (Asphalt) on behalf of its subcontractors, Kevcor Corporation (Kevcor) and M.M. Gunter & Sons, Inc. (Gunter). VDOT contends that the trial court erred: (1) in awarding additional compensation for backfill material and for disposal of unsuitable material; (2) in awarding "undercut" compensation for excavation that was not "undercut"; (3) in failing to limit damages for "undercut" to the amount claimed by Asphalt; (4) in awarding damages for

*

Pursuant to Code § 17-116.010 this opinion is not designated for publication.

construction delays without proof of the actual costs incurred by those delays; (5) in admitting hearsay evidence from an industry manual to calculate equipment-related damages; and (6) in incorrectly calculating days lost at a worksite operated by Gunter. Asphalt contends that the trial court erred in denying damages for unabsorbed overhead. For the reasons that follow, we affirm in part, reverse in part, and remand.

Asphalt contracted with VDOT to widen Landstown Road in Virginia Beach. The contract incorporated by reference the 1991 VDOT Road and Bridge Specifications (Specifications), the project plans and drawings, the 1989 VDOT Standards, and VDOT's project

proposal.

Asphalt filed an administrative construction claim

requesting additional compensation for itself and on behalf of Kevcor and Gunter. See Code § 33.1-386. The Commonwealth Transportation Commissioner allowed part of the claim. Asphalt then filed this action seeking recovery for "such portion of the claims as were denied by the Commissioner." See Code § 33.1-387. The trial court denied Asphalt any further recovery for itself, but allowed further recovery on behalf of Kevcor and Gunter.

I.

Asphalt subcontracted with Kevcor to perform drainage and water and sewer system work. During construction, a VDOT inspector informed Kevcor that material being excavated for the installation of the storm drainage system was unsuitable for use

as backfill. 1 Kevcor requested additional compensation for costs incurred in acquiring off-site and placing suitable backfill material and in disposing of the unsuitable excavated material. VDOT responded that according to the specifications, the bid price for the pipes and backfill included these associated costs. However, VDOT paid Kevcor additional compensation for backfill material, based upon the plan dimensions and the contract unit price for select borrow. 2 VDOT also allowed additional

compensation for disposal of the unsuitable material.

The trial court awarded Asphalt, on behalf of Kevcor,

additional compensation of $53,500.26 for backfill imported to the site and $98,286.12 for off-site disposal of the unsuitable excavated material. 3 VDOT contends that the contract bars recovery of additional compensation for these items. We agree.

Our resolution of this issue turns upon a reading of the parties' contract. Because the parties presented for our review all of the evidence necessary to construe the contract, its

1 Specifications § 101.02 defines "backfill" as "Material used to replace or the act of replacing material removed during construction . . . ."

2 Specification § 101.02 defines "select borrow" as "borrow material that has specified physical characteristics." "Borrow" refers to suitable material from sources outside the roadway. Id.

3 The trial court had jurisdiction over this matter "as to such portion of the claim as was denied by the Commissioner." Code § 33.1-387. Contrary to the assertion made by Asphalt, the trial court had the authority to determine not only the amount of any award, but also whether Asphalt was entitled to an award.

meaning and effect is a question of law, capable of interpretation by us on appeal. See Fry v. Schwarting, 4 Va. App. 173, 180, 355 S.E.2d 342, 346 (1987).

Section 302 of the Specifications controls construction of drainage structures. Measurement and payment for installation of

drainage structures is governed by § 302.04, which states:

Pipe shall be paid for at the contract unit price per linear foot. This price shall include excavating, when not a pay item;

sheeting; shoring; dewatering; disposing of surplus and unsuitable material; backfill material; and restoring existing surfaces.

Section 520 of the Specifications addresses installation of

water and sanitary sewer facilities. Section 520.06 states:

Water mains, water service lines, sanitary sewer pipe, and sanitary sewer force mains will be measured in linear feet of pipe through all valves and fittings, complete-in-place, and will be paid for at the contract unit price per linear foot.

This price shall include excavating; testing;

disinfecting; backfilling; compacting;

dewatering; disposing of surplus and unsuitable material; . . .; and restoring property.

Asphalt argues that the foregoing provisions are ambiguous when considered in conjunction with the other terms of the contract and the surrounding circumstances.

Asphalt claims that Specifications §§ 302.04 and 520.06 must be interpreted with reference to § 303.06, which governs the measurement and payment of earthwork. Specifications § 303.06(d)

states in part that:

Furnishing and placing backfill material . . . will be included in the price for

excavation and will not be measured for separate payment unless specific material is a pay item for backfill or unless suitable material is not available within the construction limits. When a specific material is a pay item, the unit of measure of the material will be in accordance with the unit specified in the Contract. When suitable backfill material is not available within the construction limits, the material furnished and placed by the Contractor will be paid for in accordance with Section 109.05. 4

The backfilling and unsuitable material disposal concerned in this case were not "pay items." Specifications § 101.02 defines "pay item" as "a specifically described unit of work for which a price is provided in the Contract."

4 Specifications § 109.05 states in part that:

Extra work performed in accordance with the requirements and provisions of Section 104.03 will be paid for at the unit prices or lump sum specified in the work.

Specifications § 104.03 states that:

The Contractor shall perform unforeseen work for which there is no price specified in the Contract whenever it is deemed necessary or desirable. Such work shall be performed in accordance with these specifications and as directed by the Engineer and will be paid for in accordance with Section 109.05.

Asphalt argues on appeal that these sections do not encompass "minor structure excavation," which is measured and paid for under § 303.06. However, the record does not indicate that Asphalt set forth that claim with particularity to the Commissioner. Because the Commissioner had no opportunity to deny additional compensation for minor structure excavation, the trial court would not have jurisdiction to hear the claim. Code § 33.1-387.

Free access — add to your briefcase to read the full text and ask questions with AI

Commonwealth of Virginia v. Asphalt Roads, (Va. Ct. App. 1998).

Commonwealth of Virginia v. Asphalt Roads (Commonwealth of Virginia v. Asphalt Roads) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Smith v. Smith
351 S.E.2d 593 (Court of Appeals of Virginia, 1986)
McMunn v. Tatum
379 S.E.2d 908 (Supreme Court of Virginia, 1989)
CSX Transportation, Inc. v. Casale
441 S.E.2d 212 (Supreme Court of Virginia, 1994)
Fry v. Schwarting
355 S.E.2d 342 (Court of Appeals of Virginia, 1987)
Kern v. Commonwealth
341 S.E.2d 397 (Court of Appeals of Virginia, 1986)
Lutes v. Alexander
421 S.E.2d 857 (Court of Appeals of Virginia, 1992)
Pebble Building Co. v. G. J. Hopkins, Inc.
288 S.E.2d 437 (Supreme Court of Virginia, 1982)
Chantilly Construction Corp. v. Department of Highways & Transportation
369 S.E.2d 438 (Court of Appeals of Virginia, 1988)
Wyckoff Pipe & Creosoting Co. v. Saunders
9 S.E.2d 318 (Supreme Court of Virginia, 1940)
Papuchis v. Commonwealth
422 S.E.2d 419 (Court of Appeals of Virginia, 1992)