Commonwealth of Massachusetts v. New York State Board on Electric Generation Siting & the Environment

197 A.D.2d 97, 610 N.Y.S.2d 341
CourtAppellate Division of the Supreme Court of the State of New York
DecidedApril 14, 1994
StatusPublished
Cited by4 cases

This text of 197 A.D.2d 97 (Commonwealth of Massachusetts v. New York State Board on Electric Generation Siting & the Environment) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commonwealth of Massachusetts v. New York State Board on Electric Generation Siting & the Environment, 197 A.D.2d 97, 610 N.Y.S.2d 341 (N.Y. Ct. App. 1994).

Opinion

OPINION OF THE COURT

Crew III, J.

In October 1988, respondent Inter-Power of New York, Inc. filed an application with respondent New York State Board on Electric Generation Siting and the Environment (hereinafter the Siting Board), pursuant to Public Service Law former article VIII,1 for a certificate of environmental compatibility and public need to construct a 210-megawatt coal-fired cogeneration facility (hereinafter the project or the facility) in the Town of Halfmoon, Saratoga County. The application in-[100]*100eluded, inter alia, a power sales contract entered into by Inter-Power and Niagara Mohawk Power Corporation, an electrical utility and would-be purchaser of the power to be generated by the proposed facility. The contract was entered into in 1988 pursuant to an order issued by the Public Service Commission (hereinafter PSC) and required, inter alia, that the facility be operational by December 31, 1993. Inter-Power’s application also included a brief description and analysis of the possible alternatives to the proposed project.

Inter-Power’s application was deemed complete on March 29, 1989 and a series of public hearings followed. Ultimately, in March 1991, the Administrative Law Judge (hereinafter ALJ) who presided over the hearings issued a recommended decision, wherein he concluded that a natural gas-fired facility was preferable to a coal-fired facility and, therefore, recommended that the proposed facility not be certified. In May 1991, the Siting Board voted 5 to 2 to approve Inter-Power’s application but thereafter rescinded its decision due to, inter alia, the Department of Environmental Conservation’s discovery of certain errors in the base line inventory of emission sources that Inter-Power had utilized in modeling the air quality studies for the project. The Siting Board then ordered additional hearings on air quality issues and Inter-Power was permitted to submit, over petitioners’ objections, additional air quality analyses. Additionally, the Siting Board removed the ALJ who had presided over the initial hearings and replaced him with another ALJ.

While these additional hearings were pending, it became apparent that Inter-Power was not going to be able to meet the December 31, 1993 in-service deadline imposed under its 1988 contract with Niagara Mohawk, and petitioners requested a hearing on, inter alia, how this would impact Inter-Power’s application. The Siting Board denied this request but, inter alia, permitted the parties to brief this issue at a later date. The Siting Board thereafter voted to approve Inter-Power’s application and, by decision and order dated September 24, 1992, granted Inter-Power the requested certificate pursuant to Public Service Law former article VIII. The certificate was subject to a number of conditions, however, including Inter-Power’s ability to obtain a power sales contract on or before December 31, 1992. The Siting Board’s decision further provided that it would leave to the PSC the review and resolution of any outstanding contract issues.

Thereafter, the Siting Board granted Inter-Power’s numer[101]*101ous requests for additional time in which to obtain a power sales contract, ultimately imposing a deadline of March 12, 1993. When it became apparent that Inter-Power again would be unable to meet the required deadline, the Siting Board decided to "shelve” the certificate. Under the terms of the Siting Board’s decision, the certificate would lapse on September 13, 1994 unless Inter-Power could, inter alia, obtain a revised power sales contract, justify the contract prices and demonstrate that the health and environmental impacts identified in previous studies had not changed materially since March 12, 1993. Petitioners’ subsequent request for a rehearing was denied.

Petitioners Commonwealth of Massachusetts, State of Vermont and Sierra Club, Inc. thereafter commenced a proceeding in this Court (proceeding No. 1) pursuant to Public Service Law former § 148 to challenge the Siting Board’s grant of a certificate to Inter-Power, and petitioner Concerned Citizens for the Environment, Inc. commenced a separate proceeding (proceeding No. 2) seeking similar relief. The Siting Board’s subsequent application for a stay of these proceedings until it was determined whether Inter-Power would be able to obtain a contract within the requisite period of time was denied by this Court.

Although petitioners have challenged the Siting Board’s determination on a number of substantive and procedural grounds, petitioners’ arguments essentially distill to whether the Siting Board properly discharged the statutory duties imposed upon it by Public Service Law former article VIII. As such, before we address the specific challenges raised by petitioners, a brief review of the relevant statutory provisions is in order.

Public Service Law former article VIII has been characterized as a "one-stop certification” statute (Governor’s Mem, 1978 McKinney’s Session Laws of NY, at 1838) and was designed to "provide for the expeditious resolution of all matters concerning the location of major steam electric generating facilities [within the State] in a single proceeding” (L 1972, ch 385, § 1). Under the terms of Public Service Law former article VIII, a developer seeking a certificate of environmental compatibility and public need must first submit to the Siting Board an application containing, inter alia, a description of the proposed site and facility (see, Public Service Law former § 142 [1] [a]), a description of alternate practical sources of power to the proposed facility, together with a [102]*102description of the comparative advantages and disadvantages of each source (see, Public Service Law former § 142 [1] [b]), estimated cost information, including the total generating cost per kilowatt-hour (see, Public Service Law former § 142 [1] [d]), and a statement explaining the need for the facility (see, Public Service Law former § 142 [1] [e]). The application must also include a $150,000 fee to be used to establish a fund to defray expenses incurred by municipal and other local parties to the proceeding (see, Public Service Law former § 142 [6]).

Once the Chair of the Siting Board determines that the application is complete, public hearings are scheduled before a presiding and associate ALJ who, at the conclusion of the hearing, issue a recommended decision (see, Public Service Law former §§ 143, 145). The Siting Board then reviews the record and renders a decision either granting or denying the application in question (see, Public Service Law former § 146 [1], [2]). Before the Siting Board may grant the requested certificate, it must first "find and determine” several factors including, inter alia, (1) the public need for the facility, (2) the nature of the probable environmental impact of the facility,

(3) that the facility represents the minimum adverse environmental impact and is compatible with the public health and safety, (4) that the facility is consistent with the long-range planning objectives for electric power in the State, and (5) that the facility is in the public interest (see, Public Service Law former § 146 [2] [a]-[g]). Assuming the statutory criteria have been satisfied, the Siting Board may issue a certificate authorizing construction of the proposed facility.

We now turn to the specific arguments advanced by petitioners.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

TransGas Energy Systems., LLC v. New York State Board on Electric Generation Siting & Environment
65 A.D.3d 1247 (Appellate Division of the Supreme Court of New York, 2009)
Inter-Power of New York, Inc. v. Niagara Mohawk Power Corp.
208 A.D.2d 1073 (Appellate Division of the Supreme Court of New York, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
197 A.D.2d 97, 610 N.Y.S.2d 341, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commonwealth-of-massachusetts-v-new-york-state-board-on-electric-nyappdiv-1994.