Commonwealth Edison Co. v. Diversified Technologies Group, Inc.

887 F. Supp. 1082, 1995 U.S. Dist. LEXIS 7356, 1995 WL 360693
CourtDistrict Court, N.D. Illinois
DecidedMay 25, 1995
DocketNo. 93 C 4138
StatusPublished

This text of 887 F. Supp. 1082 (Commonwealth Edison Co. v. Diversified Technologies Group, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commonwealth Edison Co. v. Diversified Technologies Group, Inc., 887 F. Supp. 1082, 1995 U.S. Dist. LEXIS 7356, 1995 WL 360693 (N.D. Ill. 1995).

Opinion

MEMORANDUM OPINION AND ORDER

ASPEN, Chief Judge:

Plaintiff Commonwealth Edison Company (“ComEd”) brings this two-count complaint against Diversified Technologies Group, Inc. (“Diversified/Maryland”) and Charles E. Jensen d/b/a Diversified Technologies (“Jensen” or “Diversified”) for breach of contract.1 Defendant Jensen has brought two amended counterclaims for breach of contract, alleging that ComEd unduly delayed Diversified’s performance under the contract and wrongfully terminated the agreement. ComEd has moved for summary judgment on Count II of its complaint, and on Counts I and II of Jensen’s counterclaims. For the reasons set forth below, plaintiffs motion is denied.

I. Background

Since 1984 ComEd, a large electricity producer, had been looking for a way to dispose of certain radioactive wastes it produced when decontaminating the Unit One Reactor at the Dresden Nuclear Power Station. These wastes consisted of a liquid solution used to remove radioactive oxides from the inside of pipes (“NS-1”) and radioactive particulates suspended in that solution. ComEd concentrated this NS-1 solution, producing “NS-1 Concentrates” and a vapor containing small amounts of NS-1 and radioactive particles. This vapor was condensed and “demineralized,” meaning it was passed through a demineralization chamber filled with resin beads. The contaminated particulates bonded with the resin beads, yielding clean water and contaminated beads. The resin beads were then suspended in water to form a slurry called “NS-1 Supernatant” or “NS-1 Resin Slurry”. ComEd stored the resulting waste in four tanks: three tanks of NS-1 Concentrates and one tank of NS-1 Resin Slurry. ComEd eventually planned to solidify these wastes in fifty-five gallon drums with a vinyl-ester-styrene binder, and store them at an arid, low-level nuclear waste disposal site. The United States Nuclear Regulatory Commission (“NRC”) approved this plan in an Environmental Impact Statement (“EIS”), concluding that solidification and storage of the solid waste at either the Han-ford, Washington site or the Beatty, Nevada site would be acceptable. Because these two arid waste sites would be closed to ComEd shipments after December 31,1992, the company set out to procure a contractor to perform the necessary solidification before that date.

In June 1990 several of Diversified/Maryland’s representatives, including Vice President Jensen, met with ComEd to discuss solidification of the NS-1 waste. Diversified claimed that it could solidify ComEd’s wastes by this NRC-approved method, and that the process could be completed by the December 31,1992 deadline. On June 13,1990, ComEd distributed a Bid Specification to Diversified and a competitor (which eventually chose not [1085]*1085to bid), wherein ComEd stated that the chosen contractor must comply with (1) the prescribed timetable for solidification,2 (2) the terms of the EIS issued by the NRC, and (3) all applicable regulations and licenses for solidification and storage. Diversified submitted an initial proposal in August 1990, offering to solidify all 2317 cubic feet of the NS-1 waste3 with vinyl-ester-styrene binders for $460.50 per cubic foot of waste plus $90,600 in “Mobilization/Demobilization” costs, for a total of $1,157,580. Complaint, Exb. 2C, at PFI-2A. The initial proposal also indicated that Diversified could complete the project within ten months of the start date, and that the company knew time was of the essence. Although Diversified suggested two alternative means of solidifying the NS-1 Supernatant (“dewatering” and “VERI processing”), ComEd claims that it did not plan on using either of these two methods.4 After this bid was submitted, the parties learned that the amount of liquid that needed to be solidified was more than previously calculated, since the NS-1 Concentrates had to be diluted before they could be properly solidified. Diversified amended its bid to take into account the additional liquid needed for dilution, and agreed to charge $398 per cubic foot of these “Additional NS-1 Dilution Volumes.”

These and other documents were eventually incorporated into ComEd’s Purchase Order to Diversified dated December 11, 1990. The order listed the price for solidification per cubic foot of each kind of waste, and stated that delivery was required in the manner outlined in the Bid Specification. ComEd agreed to pay $425,000 up front for the solidification processing, and Diversified would receive additional payments as work was performed and invoiced.

As Diversified began manufacturing the equipment needed for the project, the parties ran into a series of disputes. First, in July 1991 the parties raised the possibility of solidifying the NS-1 Resin Beads through either dewatering or VERI processing.5 Diversified subsequently obtained NRC approval for VERI processing of the waste in October 1991, and ComEd agreed to use that process to solidify the 600 cubic feet of NS-1 Resin Slurry. In order to utilize this process, however, Diversified would have to remove the liquid from the NS-1 Resin Slurry, and processes it separately. Diversified submitted a separate proposal to demineralize this material, but ComEd hired its on-site demineralization and dewatering provider, Chem-Nuelear Systems, Inc. (“CNSI”), to perform the required work on the additional liquid. In an October 18, 1991 fax transmission, Jensen informed ComEd that Diversified considered the contract with ComEd to include the treatment of all 600 cubic feet of resin slurry, and therefore Diversified would bill ComEd for the additional liquid amounts regardless of which treatment method was used on the NS-1 Resin Slurry and which company treated the additional liquid component.6

Second, Diversified informed ComEd during this same time period that it had obtained favorable results in solidifying samples of the undiluted NS-1 Concentrates.7 [1086]*1086In an October 22, 1991 fax transmission, Jensen told ComEd that if the NS-1 Concentrates did not need to be diluted, the price for processing the waste would be increased from $460.50 per cubic foot to $730 per cubic foot. Although ComEd initially resisted this modification, it agreed in a December 20, 1991 letter to pay the increased figure because of the need to process the waste in time to meet the December 31, 1992 deadline. Jensen responded in a January 7,1992 letter, blaming ComEd for the delays in the project8 and suggesting that but for the assistance of Diversified, “this project may well have failed to meet the 1992 deadline.” Plaintiffs 12(M) ¶53.

Finally, the parties disagreed about how the solidified waste should be tested before shipping. Apparently, the State of Nevada (which regulates the Beatty storage site) requires all solidified drums of radioactive waste to be physically tested for free standing liquid. In order to comply with this regulation, ComEd demanded that a “drum tipper” be included in Diversified’s solidification system. However, Diversified did not believe that such an apparatus was required by Nevada, and therefore did not initially develop its system to incorporated it. Consequently, after Diversified put the drum tipper in its system, it invoiced ComEd for the additional cost. This invoice was disputed by ComEd because it believed that the cost of such measures was included in the contract price.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frank Lumpkin v. Envirodyne Industries, Inc.
933 F.2d 449 (Seventh Circuit, 1991)
Haisma v. Edgar
578 N.E.2d 163 (Appellate Court of Illinois, 1991)
Borys v. Rudd
566 N.E.2d 310 (Appellate Court of Illinois, 1991)
Case v. Forloine
639 N.E.2d 576 (Appellate Court of Illinois, 1993)
Arrow Master, Inc. v. Unique Forming Ltd.
12 F.3d 709 (Seventh Circuit, 1993)
Del Raine v. Williford
32 F.3d 1024 (Seventh Circuit, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
887 F. Supp. 1082, 1995 U.S. Dist. LEXIS 7356, 1995 WL 360693, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commonwealth-edison-co-v-diversified-technologies-group-inc-ilnd-1995.