Commonwealth Edison Co. v. Allied Chemical Nuclear Products, Inc.

684 F. Supp. 1429, 6 U.C.C. Rep. Serv. 2d (West) 434, 1988 U.S. Dist. LEXIS 3898, 1988 WL 43800
Procedural entryThis page is a short order in Commonwealth Edison Co. v. Allied Chemical Nuclear Products, Inc.. Read the opinion of the Court — 684 F. Supp. 1434
District Court, N.D. Illinois·Decided April 28, 1988·No. 79 C 2866·Published

Opinion

MEMORANDUM OPINION AND ORDER

ASPEN, District Judge:

In this diversity breach of contract case, plaintiff Commonwealth Edison Company (“Edison”) sued defendant Allied-General Nuclear Services (“AGNS”) for breach of an agreement for nuclear fuel recovery *1430 services (“Contract”). Currently before the Court is AGNS’s motion for partial summary judgment on storage and waste costs. For the reasons set forth below, we deny AGNS’s motion for partial summary judgment under Fed.R.Civ.P. 56(c) on this issue.

I.

We relate the factual background of this case briefly in order to place the legal issue we decide in context. On February 15, 1974, Edison and AGNS entered into a Contract for nuclear fuel recovery services. Nuclear fuel reprocessing involves the removal of uranium and plutonium from fuel assemblies which have been used in commercial nuclear power reactors. The recovered material was then to be recycled and fabricated into fresh fuel.

Under the Contract, AGNS agreed to reprocess spent nuclear fuel assemblies from certain of Edison’s nuclear reactors during a defined period of time and to deliver recovered products back to Edison. At the time the Contract was executed, AGNS had not completed building its fuel reprocessing plant, and it had not been licensed to reprocess nuclear fuel by the Nuclear Regulatory Commission (“NRC”). The Contract also provided that under certain circumstances prior to AGNS’s commencement of commercial operations, it was required to deliver to Edison uranium and plutonium equivalent to that which would have been recovered from Edison’s nuclear fuel subject to reprocessing under the Contract. This uranium and plutonium is called “equivalent fissile material” of “EFM.”

At some point after the Contract was executed, AGNS ceased work on its fuel reprocessing plant, and thereafter certain events occurred which resulted in the delay of government licensing of reprocessing plants. Some of these invents include the decision in National Resources Defense Counsel v. NRC, 539 F.2d 824 (2d Cir.1976) (prohibiting NRC from acting on applications for commercial licenses prior to the NRC’s final Generic Environmental Statement on Mixed Oxide Fuel (“GESMO”) report), and the indefinite postponement of further GESMO hearings by the NRC’s GESMO Hearing Board on April 12, 1977.

By letter dated July 27, 1977, Edison, pursuant to Section 16.1(b) of the Contract, requested that AGNS provide EFM based on certain fuel discharges. AGNS refused, asserting that the Contract had been voided by government action. This lawsuit was filed in 1979. On March 14, 1986, Edison filed an amended complaint. AGNS subsequently filed a motion to dismiss the amended complaint. AGNS argued that storage and waste-related costs could not be recovered under Count I because the Contract expressly allocated these costs to Edison. In her December 2, 1986 opinion, Judge Susan Getzendanner rejected this argument but unfortunately 1 indicated in dicta that AGNS might have had better luck if it had argued that the passage of title provision in Section 16 of the Contract was a critical price term. Understandably, AGNS jumped at this suggestion and filed the present motion for partial summary judgment.

II.

Summary judgment is appropriate only where the moving party demonstrates that no genuine issue of material fact exists, and it is accordingly entitled to judgment as a matter of law. Fed.R.Civ.P. 56(c). The moving party bears the burden of clearly establishing the absence of a triable fact issue. Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.Ct. 2548, 2553, 91 L.Ed.2d 265 (1986).

At Judge Getzendanner’s suggestion, AGNS argues that under Section 16, “Facility Contingency Plan,” assuming this is an alternative performance obligation, the passage of title provision is a critical price *1431 term. The pertinent part of Section 16 provides the following:

[If Edison has requested that recovered products be provided before the recovery-plant is in operation] then [AGNS] shall deliver to destinations specified by Edison, in a timely manner, fissile material equivalent to that which would have been recovered from the fuel so made available in such quantities as the fuel would have yielded upon processing hereun-der_ Title to equivalent fissile material delivered to Edison shall pass to Edison upon delivery. Title to irradiated fuel which such equivalent material substitutes for shall pass to [AGNS] upon delivery of such equivalent fissile material.

(Emphasis added). AGNS contends that as long as the title provision is a critical price term, it had no obligation to take title to the irradiated fuel because it never transferred title of the EFM to Edison. AGNS argues that “[l]ike a trade-in automobile, title to Edison’s irradiated fuel was to pass to AGNS, along with a cash payment, as consideration for EFM.” Thus, “because AGNS has not delivered EFM, it has never become entitled to receive an interest in Edison’s discharged fuel and is not responsible for expenses incurred in storing and disposing of the fuel.” (AGNS Memo in Support at 4, 6).

Edison contends that the title provision is not a critical price term but is part of the consideration for Edison’s performance under the Contract. In the alternative, Edison contends that, even if the title could be construed to be a critical price term, AGNS would still be liable for the storage costs of the irradiated fuel as incidental damages under the Uniform Commercial Code (“UCC”) for AGNS’s wrongful refusal to accept title. Because we agree with Edison, as set forth below, that AGNS would be liable for the storage costs of the irradiated fuel even under its price term theory, we deny AGNS’s motion for partial summary judgment. Additionally, because we find that AGNS would be liable for the storage costs even under their price term theory, we need not address the issue of whether the title provision is a price term in the first place.

Under UCC § 2-304, “price can be payable in money or otherwise.” 2 As consideration for the purchase of an automobile, for example, a payment of cash and the trade-in of a used automobile each constitutes a portion of the price. Harney-Morgan Chevrolet Olds Co. v. Rabin, 118 Ill.App.3d 602, 603, 74 Ill.Dec. 100, 103, 455 N.E.2d 130, 133 (3rd Dist.1983). Thus, AGNS argues that the irradiated fuel was merely a “trade-in” on the EFM. However, § 2-304 also provides that if the price “is payable in whole or in part in goods each party is a seller of the goods which he is to transfer.” § 2-304(1). Accordingly, a “trade-in” is a “sale of the goods traded-in, and the buyer is a seller with respect to the traded-in items.” 2 R. Anderson, Uniform Commercial Code § 2-304:10 (3d ed. 1982).

Free access — add to your briefcase to read the full text and ask questions with AI

Commonwealth Edison Co. v. Allied Chemical Nuclear Products, Inc., 684 F. Supp. 1429, 6 U.C.C. Rep. Serv. 2d (West) 434, 1988 U.S. Dist. LEXIS 3898, 1988 WL 43800 (N.D. Ill. 1988).

684 F. Supp. 1429 (Commonwealth Edison Co. v. Allied Chemical Nuclear Products, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

McGinnis v. Wentworth Chevrolet Co.
645 P.2d 543 (Court of Appeals of Oregon, 1982)
Petroleo Brasileiro, SA, Petro. v. Ameropan Oil Corp.
372 F. Supp. 503 (E.D. New York, 1974)
GREAT WESTERN SUGAR v. Mrs. Allison's Cookie Co.
563 F. Supp. 430 (E.D. Missouri, 1983)
Harney-Morgan Chevrolet Olds Co. v. Rabin
455 N.E.2d 130 (Appellate Court of Illinois, 1983)
Shokai Far East Ltd. v. Energy Conservation Systems, Inc.
628 F. Supp. 1462 (S.D. New York, 1986)
McGinnis v. Wentworth Chevrolet Co.
668 P.2d 365 (Oregon Supreme Court, 1983)
Neri v. Retail Marine Corp.
285 N.E.2d 311 (New York Court of Appeals, 1972)