Commercial Restoration, LLC v. Nanaki, LLC

Louisiana Court of Appeal·Decided December 30, 2024·No. CA-0024-0251·Unknown

Opinion

STATE OF LOUISIANA

COURT OF APPEAL, THIRD CIRCUIT

24-251

COMMERCIAL RESTORATION COMPANY, LLC VERSUS NANAKI, LLC ******************

APPEAL FROM THE

THIRTY-THIRD JUDICIAL DISTRICT COURT PARISH OF ALLEN, NO. 2021-71 HONORABLE JUDI F. ABRUSLEY, DISTRICT JUDGE

*****************

CHARLES G. FITZGERALD

JUDGE

******************

Court composed of Shannon J. Gremillion, Van H. Kyzar, and Charles G. Fitzgerald, Judges.

REVERSED IN PART;

AFFIRMED AS AMENDED.

John W. Joyce Stephen R. Klaffky Barrasso Usdin Kupperman Freeman & Sarver, LLC 909 Poydras Street, Suite 2350 New Orleans, Louisiana 70112 (504) 589-9700 Counsel for Third Party Defendant/Appellant:

AmGUARD Insurance Company

Wells T. Watson Baggett McCall, LLC Post Office Box 7820 Lake Charles, Louisiana 70606-7820 (337) 478-8888 Counsel for Third Party Plaintiff/Appellee:

Nanaki, LLC

Michael Reese Davis Hymel, Davis & Petersen, LLC 10602 Coursey Boulevard Baton Rouge, Louisiana 70816 (225) 298-8118 Counsel for Third Party Plaintiff/Appellee:

Nanaki, LLC

Kevin Sloan Gauthier Murphy & Houghtaling, LLC 3500 North Hullen Street Metairie, Louisiana 70002 (504) 456-8600 Counsel for Third Party Plaintiff/Appellee:

Nanaki, LLC

FITZGERALD, Judge.

This is a Hurricane Laura case. AmGuard Insurance Company appeals a final judgment awarding its insured Nanaki LLC policy limits, bad-faith penalties and fees, and consequential damages.

ISSUES

On appeal, AmGuard presents the following issues:

1. Whether Nanaki, which owed a duty to mitigate, can recover damages for estimated costs of mitigation it never performed.

2. Whether Nanaki can recover full replacement cost value for property not repaired or replaced where the policy states: “We will not pay on a replacement cost basis for any loss or damage . . . [u]ntil the lost or damaged property is actually repaired or replaced[,]” and can recover the replacement cost of all furniture, fixtures, and equipment based on unsupported testimony that “more than half” was damaged.

3. Whether Nanaki can recover more business income than it would have earned but for the property damage under a policy that covers only “actual loss of Business Income” and defines business income as the net income “that would have been earned or incurred if no physical loss or damage had occurred[.]”

4. Whether AmGUARD had satisfactory proof of loss and acted in bad faith when it had conflicting reports of the scope of damage, proposed a solution Nanaki’s adjuster considered reasonable, repeatedly requested material information that Nanaki withheld, and received false and misleading information instead.

5. Whether the district court manifestly erred in finding AmGUARD caused lost profits when Nanaki spent only 3% of the $2.5 million paid by AmGUARD to restore the property and in awarding an amount not proven with reasonable certainty, and erred as a matter of law in failing to deduct the avoided expenses of operating the hotel while it was closed.

FACTS AND PROCEDURAL HISTORY Nanaki is owned by Paul Singh and his wife. At all relevant times, Nanaki owned the Days Inn & Suites hotel in Kinder, Louisiana. The Days Inn consists of two buildings with 129 guest rooms. On August 27, 2020, the hotel was badly damaged by Hurricane Laura.

AmGuard issued an all-risk, replacement-cost policy to Nanaki which covered the damages to the Days Inn caused by Hurricane Laura. The policy limit for Building 1 was $3,247,296.48, and the policy limit for Building 2 was $1,916,541.24. The insurance policy contained Business Personal Property (BPP) and contents limits of $250,000.00 for each building. It also had a $50,000.00 limit for Other Structures. Finally, it covered Business Interruption with no limit for a period of one year plus thirty days.

The day after the hurricane, Nanaki filed its claim with AmGuard. Nanaki then attempted to mitigate damages by hiring Commercial Restoration Company LLC (CRC). On September 30, 2020, Nanaki entered a Restoration & Rebuild Agreement with CRC to restore the hotel to its pre-hurricane condition. But two days later, Nanaki—concerned about the cost of the potential repairs—requested that CRC stop work. CRC’s bill for a few days’ work was $166,477.97. CRC ultimately filed suit against Nanaki for payment of this sum. 1 Within a week of terminating CRC, Nanaki hired public adjuster Pinnacle Limited. Pinnacle recommended a second mitigation company, Rainbow International. And in mid-September 2020, Nanaki entered a mitigation contract with Rainbow designated a Not to Exceed Agreement. Rainbow agreed to remove sheetrock, insulation, and drywall from “all areas of building” and complete “dehumidification and air movement to bring interior to dry standard: for a sum not to exceed $594,000.00.”

However, Rainbow stopped working in November 2020. Paul Singh explained that Rainbow initially underestimated the magnitude of the damages. A

1 In response, Nanaki filed a third party demand against AmGuard. The judgment from this incidental action is now before us on appeal.

few months into the job, Rainbow requested a change in work scope. It then issued a 230-page mitigation estimate of $1,139,376.76.

Turning now to AmGuard’s adjustment of Nanaki’s claim. On September 5, 2020, Engle Martin & Associates inspected the damage to the Days Inn. Engle Martin was an independent adjusting firm hired by AmGuard. Four days after inspecting the property, Engle Martin submitted a preliminary report to AmGuard with a final estimate of damages expected within two weeks. The initial report estimated building damages of $1,000,000.00 and business interruption of $400,000.00. The report then stated: “Due to the severity and size of the loss, we are requesting authority to engage a building consultant to thoroughly investigate the loss property and provide a detailed repair recommendation and estimate of repairs.” (Emphasis in original). Finally, the report recommended that AmGuard advance $100,000.00 to Nanaki to assist with mitigation. This sum was paid to Nanaki as a building advance on September 16, 2020. AmGuard, however, fired Engle Martin before it completed its final estimate.

The adjustment of Nanaki’s claim was then handled by AmGuard estimating supervisor Corey Massaro, who took over the claim from Engle Martin on September 11, 2020. Massaro inspected the property on September 24, 2020, October 14, 2020, and December 2, 2020. After his first inspection, Massaro obtained an estimate for roof replacement in the amount of $162,506.73. Two weeks later, AmGuard advanced this sum to Nanaki.

Meanwhile, on October 7, 2020, Nanaki adjuster Pinnacle provided Massaro with an estimate of $353,633.82 for BPP damages. One day later, Pinnacle supplemented the estimate by adding $81,628.07 for new mattresses. Seven days after that, AmGuard advanced $50,000.00 to Nanaki towards BPP coverage.

Around this time, Massaro hired Hillman Consulting LLC, an industrial hygiene firm, to measure and map areas of elevated moisture throughout the hotel. Hillman provided a report to AmGuard on October 13, 2020. The report noted elevated moisture and apparent microbial growth in many areas of the hotel and made recommendations for drying and removal.

Ten days later, on October 23, 2020, Pinnacle provided Massaro with an estimate of loss of $1,923,331.64 for Building 1 and $1,661,262.44 for Building 2 (or $3,584,594.08 for both buildings). The estimate consisted of 588 pages and entailed gutting both buildings. Although the estimate did not include the cost of demolition or removal, Pinnacle had estimated $1,025,000.00 for that work four days earlier.

Free access — add to your briefcase to read the full text and ask questions with AI

Commercial Restoration, LLC v. Nanaki, LLC, (La. Ct. App. 2024).

Commercial Restoration, LLC v. Nanaki, LLC (Commercial Restoration, LLC v. Nanaki, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
Louisiana Bag Co., Inc. v. Audubon Indem. Co.
999 So. 2d 1104 (Supreme Court of Louisiana, 2008)
State v. Foret
628 So. 2d 1116 (Supreme Court of Louisiana, 1993)
Sevier v. United States Fidelity & Guar. Co.
497 So. 2d 1380 (Supreme Court of Louisiana, 1986)
Domingue v. Bodin
996 So. 2d 654 (Louisiana Court of Appeal, 2008)
Morton M. Goldberg Auction Galleries, Inc. v. Canco, Inc.
650 So. 2d 801 (Louisiana Court of Appeal, 1995)
Rabalais v. Nash
952 So. 2d 653 (Supreme Court of Louisiana, 2007)
J.R.A. Inc. v. Essex Insurance Co.
72 So. 3d 862 (Louisiana Court of Appeal, 2011)
Aghighi v. Louisiana Citizens Property Insurance Corp.
119 So. 3d 930 (Louisiana Court of Appeal, 2013)
Aghighi v. Louisiana Citizens Insurance Corp.
124 So. 3d 1102 (Supreme Court of Louisiana, 2013)
Mason v. Shelter Mutual Insurance Co.
209 So. 3d 860 (Louisiana Court of Appeal, 2016)
Maloney Cinque, L.L.C. v. Pacific Insurance Co.
89 So. 3d 12 (Louisiana Court of Appeal, 2012)
Oubre v. Louisiana Citizens Fair Plan
92 So. 3d 345 (Supreme Court of Louisiana, 2012)
Wing v. N. O. Public Service, Inc.
132 So. 526 (Louisiana Court of Appeal, 1931)