This text of 154 B.R. 166 (Commercial Marketing, Inc. v. Atlantic Computer Systems Inc. (In Re Atlantic Computer Systems, Inc.)) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commercial Marketing, Inc. v. Atlantic Computer Systems Inc. (In Re Atlantic Computer Systems, Inc.), 154 B.R. 166, 1993 U.S. Dist. LEXIS 5789, 1993 WL 171256 (S.D.N.Y. 1993).

Opinion

MEMORANDUM OPINION AND ORDER

KRAM, District Judge.

Appellant/Claimant Commercial Marketing, Inc. (“CMI”) appeals from a Memorandum Endorsed decision of the United States Bankruptcy Court for the Southern District of New York (Lifland, C.J.) (the “Bankruptcy Court”), dated June 24, 1992, in which the Bankruptcy Court granted Appellee/Debtor Atlantic Computer Systems Inc.’s (“ACS”) motion for summary judgment and disallowed CMI’s claim in its entirety. 1

BACKGROUND

The following facts are undisputed by the parties. In early 1988, ACS’s British parent, Atlantic Computers, Pic, began examining CMI’s subsidiary, Systems Marketing, Inc. (“SMI”), an IBM computer leasing company, for a proposed purchase of its stock or its assets. A letter of interest was issued in July 1988, a letter of intent was presented to CMI in October 1988, and a further letter of intent dated March 22, 1989, was offered by ACS and accepted by CMI on March 31, 1989. Each of these letters provided that they were either a letter of interest or a letter of intent, and each contained the language “Subject to Contract.” Each letter of intent also contained a “walk-away” provision allowing either party the option to walk away from the deal without liability in the event negotiations were unsuccessful.

Sometime around June 13, 1989, the structure of the acquisition was changed from a purchase of the SMI stock to a portfolio purchase of assets. Thereafter, on June 28, 1989, CMI and ACS entered into an Agreement 2 (the “June Agreement” or the “June 28, 1989 Agreement”) whereby ACS was to purchase certain assets and assume certain liabilities of CMI's *168 subsidiary, SMI. That Agreement stated in part:

[B]oth parties ... subject only to the conditions stated herein, hereby agree as follows:
1. ACS will purchase certain assets of SMI, rather than purchasing the SMI stock (Common Shares), and will treat the transaction as a portfolio purchase.
2. ACS and CMI will cooperate in every regard to execute and deliver, or cause SMI to execute and deliver on or before June 30, 1989, the Portfolio Purchase Agreement pursuant to which title to such assets shall not pass to ACS until expiration of the Hart-Scott-Rodino Act (HSR Act) waiting period.
[[Image here]]
This Agreement is subject to the following conditions (emphasis in original):
1. Final pricing subject to asset adjustments presented by the auditors.
2. Final definitive agreement approved by Boards of Directors of ACI 3 and SMI.

See Agreement, attached to CMI’s Proof of Claim and designated by CMI as D-l for the record on appeal.

Although there is some dispute as to precisely what else transpired between ACS and CMI around the time of the June Agreement, it is clear that: (1) from June 26, 1989 through June 30, 1989, work was done on a final Portfolio Purchase Agreement; (2) employment agreements following standard ACS forms were sent from ACS to SMI and were signed by SMI management personnel; (3) ACS requested short-term financing from Commercial Federal Savings and Loan Association, the parent of SMI and CMI; (4) Commercial Federal Corporation, SMI’s ultimate parent, filed its Hart-Scott-Rodino notification with the Federal Trade Commission and the Justice Department on July 10, 1989; (5) ACS’s Vice President of Acquisitions visited SMI in Phoenix, Arizona and addressed a meeting of SMI employees; (6) in early July, a matter arose regarding a lawsuit between SMI and its former owner, Robert Russell, whereby Commercial Federal Savings and Loan, CMI and SMI agreed to provide ACS with full indemnification regarding the Russell litigation; and (7) an indemnification agreement was included in the Portfolio Purchase Agreement.

On June 29, 1989, a regular meeting of the Board of Directors of ACS was held. At that meeting, an SMI purchase committee with the mandate to recommend the approval or disapproval of the purchase of SMI assets to the full Board was created.

On July 13, 1989, a special meeting of ACI’s Board of Directors was held. It was called specifically to review the proposed transaction between its wholly owned subsidiary, ACS, and SMI. At that meeting, it was decided that the SMI asset purchase was not in ACS’s best interests. Thus, a motion was made, seconded and unanimously adopted formally rejecting the SMI transaction.

ACS’s Board of Directors also held a special meeting on July 13, 1989. At this meeting, the Board unanimously voted to terminate discussions respecting the proposed asset purchase as it was not in the best interest of ACS and rejected the SMI purchase.

CMI and SMI were informed of the Boards’ rejections by letter dated July 13, 1989. The letter, written by Philip E. Hold, the President of ACS at the time, states in relevant part:

This letter is to formally advise you that Atlantic Computer Systems Inc. (Atlantic) has terminated its interest in purchasing either the share capital or certain assets of Systems Marketing, Inc. (SMI).
The Board of Directors has now rejected the transaction, which of itself is fully dispositive of further consideration of the proposed asset purchase most recently under consideration. In addition, there were numerous material unresolved issues, including, but not limited to, the responsibility for leases previously discounted on a recourse basis, the inferior credit quality of unfunded leases *169 and the Russell litigation notice to Atlantic.

See Letter from Philip E. Hold to Mike Minor, President of CMI, and Bill Bresna-han, President of SMI, dated July 13, 1989, attached as Exhibit “J” to Affidavit of John Sager, sworn to on March 3, 1992.

CMI filed suit against ACS in the United States District Court for the District of Arizona on May 18,1990 based upon ACS’s alleged breach of the contract to purchase assets and assume liabilities of CMI’s subsidiary, SMI. This suit was pending and in the discovery stage when, on July 5, 1990, ACS filed a petition for reorganization under Chapter 11 of the Bankruptcy Code. On May 3, 1991, CMI filed a $14,578,891 (estimated) claim in the above-captioned bankruptcy proceeding.

Thereafter, ACS filed an Objection and Notice of Motion to Disallow [CMI’s] Claim and an Affidavit in Support of Objection and Motion to Disallow Claim. A hearing on the Motion to Disallow was held in the Bankruptcy Court on June 24, 1992, and was treated as a Motion for Summary Judgment. On the same day, the Bankruptcy Court issued a Memorandum Endorsed opinion granting ACS’s motion for summary judgment and disallowing CMI's claim. Specifically, the Bankruptcy Court found that the parties did not intend the June 28, 1989 Agreement to be a binding acquisition contract. In fact, the Court found that the express terms of the June Agreement clearly demonstrated an intent not to be bound. Among other things:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Adelphia Business Solutions, Inc.
341 B.R. 415 (S.D. New York, 2003)
In Re Kaplan Breslaw Ash, LLC
264 B.R. 309 (S.D. New York, 2001)