Commercial Investment Co. v. Herman

131 A. 223, 98 N.J. Eq. 589, 13 Stock. 589, 1925 N.J. Ch. LEXIS 23
CourtNew Jersey Court of Chancery
DecidedDecember 11, 1925
StatusPublished
Cited by1 cases

This text of 131 A. 223 (Commercial Investment Co. v. Herman) is published on Counsel Stack Legal Research, covering New Jersey Court of Chancery primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commercial Investment Co. v. Herman, 131 A. 223, 98 N.J. Eq. 589, 13 Stock. 589, 1925 N.J. Ch. LEXIS 23 (N.J. Ct. App. 1925).

Opinion

This is an interpleader suit under the Mechanics' Lien act. The defendant Joseph Herman, trading as Joseph Herman Construction Company, by contract in writing dated June 27th, 1923, and duly filed, agreed to construct for the complainant a two-story and basement mercantile building in Newark, New Jersey, according to plans and specifications of William E. Lehman, the architect. The contract provided that the whole work under the contract should be completed in four months, from July 1st, 1923. The contract price was $45,000, payable upon certificates of the architect, "seventy-five per cent. of the work done in monthly payments, balance upon completion." The contract also contained the following provision:

"Section 13. It is hereby understood and agreed between the parties hereto that should the contract for the aforesaid building be completed before the time allotted, namely, four months from July 1st, then and in that event the contractor is to receive as additional compensation for his endeavor the sum of one hundred dollars ($100) per day for each and every day he completes his contract before the time expressed in this agreement.

"However, should the contractor not complete the work aforesaid in the allotted time, he is then to reimburse the owner for their loss *Page 591 of occupancy in the same sum of one hundred dollars ($100) per day for each day that the building remains uncompleted after time allotted in the contract.

"It is, however, distinctly understood that should any strikes or conditions arise beyond the control of the contractors, the time is waived from this contract."

The contract also provided that the contractor should be allowed an extension of time for any time lost by reason of the act, neglect or default of the owner or any of its representatives, but the clause of the contract containing these provisions also provides, "but no such allowance shall be made unless a claim therefor is presented in writing to the architect within forty-eight hours of the occurrence of such delay."

The defendant contractor encountered financial difficulties, and on December 19th, 1923, an involuntary petition in bankruptcy was filed against him, and he was adjudicated a bankrupt on that day. At this time there was remaining unpaid to the contractor on account of the contract price the sum of $11,075, plus $250 for extra work, or $11,325 in all. Prior to the filing of the petition in bankruptcy many of the subcontractors and materialmen filed stop-notices with the complainant. The total amount of claims represented by these stop-notices was $28,042.20, and, in detail, are as follows:

Decker Building Material Company ...................... $3,800.00
Charles Herman ........................................    800.00
Monahan Stone Company .................................  3,500.00
L. Wortzel, Inc. ......................................  1,900.00
C. Strebinger Sons ....................................    952.00
Newark Comp. Fl. Co., Frank Kaiser ....................    194.00
Messer  Holle. Inc. ..................................    220.00
Essex Sash and Door Co. ...............................  2,125.65
Franklin Lumber Co. ...................................  3,582.67
Newark Glass Company ..................................  3,650.00
Katchen Shaw Iron Works ...............................    611.81
Offenkrantz  Mark ....................................  2,945.00
Elmer D. Wilson .......................................  1,000.00
Birkenmeier  Kuhn Co. ................................    415.80
Nathan Milstein .......................................    990.00
R. Young  Sons .......................................    875.75
Guarantee Roofing Co. .................................    479.52
*Page 592

A composition was effected in the bankruptcy proceedings and all of the above-named claimants, with the exception of Charles Herman, Monahan Stone Company, C. Strebinger Sons, Messer Holle, Incorporated, R. Young Sons and Guarantee Roofing Company, having claims aggregating the sum of $6,827.27, filed claims in the bankruptcy proceedings, received the dividends in the composition to which they were respectively entitled, and are, therefore, barred from any participation in the fund in the hands of the complainant, the owner.

Notwithstanding the financial difficulties, the contractor finally completed the work under the contract, but I find as a fact from the evidence submitted that the work was not completed until December 28th, 1923.

The bill of complaint in this cause was filed on September 19th, 1924, and all of the claimants who filed stop-notices were made parties defendant; but, in addition to the six claimants last above named, only four of the other defendants, namely, Nathan Milstein, Elmer D. Wilson, Newark Glass Company and Decker Building Material Company, are pressing their claims here. These four claimants having accepted the benefits of the composition as indicated above, I hold are not entitled to participate in the distribution of the fund here.

The complainant claims that because of the delay in the completion of the building under this contract, and in view of the provisions of the thirteenth clause of said contract above recited, there is due to the defendant contractor only $5,075, which sum he offers to pay into this court.

Aside from the question as to which of the stop-notice claimants are entitled to participate in the fund here, which I have already disposed of, the only remaining question at issue is the amount which is due to the contractor from the complainant, and that amount is dependent upon the date upon which the building was finally completed, and the construction of the thirteenth clause of the contract.

The defendant contractor, while admitting the work under the contract was not completed within the time specified in *Page 593 the contract, claims that it was fully completed on November 30th, 1923, and that because of strikes affecting the steel work, and because of delay of the owner (the complainant) in the selection of face brick, he was prevented from completing the job sooner, and was, therefore, entitled to an extension of time equal to the delay in completion, and is therefore not liable to any deduction from the contract price under the provisions of section 13.

The last architect's certificate was dated November 30th, 1923; was for $8,000, and, with previous certificates, amounted to the sum of $33,925, which showed a balance of the contract price, plus extras, in the hands of the owner of $11,325. It will be noted that this certificate, and previous certificates, show a sum slightly in excess of seventy-five per cent. of the total contract price. No final certificate was ever issued by the contractor, but under date of January 5th, 1924, the contractor wrote the complainant to the effect that on the day previous "we find that the building at the southwest corner of Court and Broad streets is complete in every respect." The architect testified, however, that this did not indicate that the building was not complete before that time, as inspection might not have been made immediately upon completion.

The defendant Joseph Herman and his son, Samuel Herman, who was in active charge of the job in conjunction with his father, both testified that the job was complete in every detail by December 1st, 1923.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rea Construction Co. v. State Roads Commission
174 A.2d 577 (Court of Appeals of Maryland, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
131 A. 223, 98 N.J. Eq. 589, 13 Stock. 589, 1925 N.J. Ch. LEXIS 23, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commercial-investment-co-v-herman-njch-1925.