Commercial Contractors Equip. v. Lower Platte North NRD

CourtNebraska Court of Appeals
DecidedMay 26, 2015
DocketA-14-260
StatusUnpublished

This text of Commercial Contractors Equip. v. Lower Platte North NRD (Commercial Contractors Equip. v. Lower Platte North NRD) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commercial Contractors Equip. v. Lower Platte North NRD, (Neb. Ct. App. 2015).

Opinion

IN THE NEBRASKA COURT OF APPEALS

MEMORANDUM OPINION AND JUDGMENT ON APPEAL (Memorandum Web Opinion)

COMMERCIAL CONTRACTORS EQUIP. V. LOWER PLATTE NORTH NRD

NOTICE: THIS OPINION IS NOT DESIGNATED FOR PERMANENT PUBLICATION AND MAY NOT BE CITED EXCEPT AS PROVIDED BY NEB. CT. R. APP. P. § 2-102(E).

COMMERCIAL CONTRACTORS EQUIPMENT, INC., A NEBRASKA CORPORATION, APPELLEE, V.

LOWER PLATTE NORTH NATURAL RESOURCES DISTRICT, A POLITICAL SUBDIVISION OF THE STATE OF NEBRASKA, APPELLANT.

Filed May 26, 2015. No. A-14-260.

Appeal from the District Court for Saunders County: MARY C. GILBRIDE, Judge. Affirmed. Jovan W. Lausterer, of Bromm, Lindahl, Freeman-Caddy & Lausterer, for appellant. David Geier for appellee.

IRWIN, RIEDMANN, and BISHOP, Judges. IRWIN, Judge. I. INTRODUCTION Lower Platte North Natural Resources District (NRD), a political subdivision of the State of Nebraska, appeals an order of the district court for Saunders County, Nebraska, in this contract action concerning a contract between NRD and Commercial Contractors Equipment, Inc. (Commercial), a Nebraska Corporation. On appeal, NRD challenges the district court’s determination that NRD was required to comply with a claims procedure set forth in its contract with Commercial, the court’s determination that it did not comply with the claims procedure, and the court’s determination that Commercial was entitled to payment under the contract. We find no merit to NRD’s assertions regarding the claims and liquidated damages provisions in the contract, and we decline to address NRD’s assertions regarding Commercial’s completion of the work because NRD failed to argue that assertion in its brief. We affirm.

-1- II. BACKGROUND This case arises out of a contract entered into between Commercial and NRD for the construction of a dam in Saunders County, Nebraska. Commercial was to construct the dam for NRD. The contract provided that Commercial would receive in excess of $12,500,000 for completion of the project. The contract provided for substantial completion in July 2010 and final completion in August 2010. Testimony adduced at trial indicated that an inspection in June 2010 resulted in a list of items that needed to be completed to satisfy substantial completion, and Commercial’s President testified that those items were all completed by the end of August 2010. Other testimony indicated that the work of construction of the dam was completed in December 2010. There was testimony adduced throughout trial about documents and paperwork that may or may not have been completed in support of Commercial’s application for final payment under the contract. The contract between Commercial and NRD included a liquidated damages provision, under which NRD had a right to liquidated damages in the amount of $1,000 per day. In December 2011, Commercial filed a complaint seeking payment of $300,000 that NRD had not yet paid under the contract. Commercial alleged that it had completed the contracted work, that NRD had taken possession and control of the dam, and that NRD had refused to pay the $300,000 balance due under the contract. NRD filed an answer and a counterclaim, alleging its right to liquidated damages. After a trial, the district court concluded that Commercial had completed all work required under the contract and was entitled to the $300,000 unpaid balance. The court concluded that NRD’s claim for liquidated damages was subject to a contract provision requiring notice of claims under the contract to be filed with a project engineer (Engineer) and that NRD had failed to timely comply with the notice provision in the contract. As such, the court concluded that NRD was not entitled to enforcement of its right to liquidated damages. This appeal followed. III. ASSIGNMENTS OF ERROR On appeal, NRD has assigned four errors, which we consolidate for discussion to three. First, NRD asserts that the district court erred in finding that the claims procedure set forth in the contract applied to NRD’s claim for liquidated damages. Second, NRD asserts that the court erred in finding that NRD failed to comply with the claims procedure. Third, NRD asserts that the court erred in finding that Commercial had completed required services under the contract and is entitled to payment. IV. ANALYSIS The issues presented for resolution in this case concern the interpretation and application of various provisions in the contract between the parties. While that contract is more than 350 pages in length, the issues on appeal primarily concern the meaning and application of a handful of provisions that the parties have agreed are the crux of the case. Those provisions are set forth as necessary below. The meaning of a contract is a question of law, in connection with which an appellate court has an obligation to reach its conclusions independently of the determinations made by the court

-2- below. Kercher v. Bd. Of Regents of University of Nebraska, 290 Neb. 428, 860 N.W.2d 398 (2015). In interpreting a contract, a court must first determine, as a matter of law, whether the contract is ambiguous. Gibbons Ranches, L.L.C. v. Bailey, 289 Neb. 949, 857 N.W.2d 808 (2015). A contract is ambiguous when a word, phrase, or provision in the contract has, or is susceptible of, at least two reasonable but conflicting interpretations or meanings. Gibbons Ranches, L.L.C. v. Bailey, 289 Neb. 949, 857 N.W.2d 808 (2015). When the terms of a contract are clear, a court may not resort to rules of construction, and the terms are to be accorded their plain and ordinary meaning as an ordinary or reasonable person would understand them. Kercher v. Bd. Of Regents of University of Nebraska, 290 Neb. 428, 860 N.W.2d 398 (2015); Gibbons Ranches, L.L.C. v. Bailey, 289 Neb. 949, 857 N.W.2d 808 (2015). A contract must receive a reasonable construction and must be construed as a whole, and if possible, effect must be given to every part of the contract. Kercher v. Bd. Of Regents of University of Nebraska, 290 Neb. 428, 860 N.W.2d 398 (2015). 1. APPLICATION OF CLAIMS PROCEDURE First, NRD asserts that the district court erred in finding that the claims procedure set forth in its contract with Commercial applied to NRD’s claim for liquidated damages. NRD argues that the plain language of the contract indicates that a claim for liquidated damages was not subject to the claims procedure set forth in the contract. We disagree. In Harmon Cable Communications of Nebraska Ltd. Partnership v. Scope Cable Television, Inc., 237 Neb. 871, 468 N.W.2d 350 (1991), the Nebraska Supreme Court discussed contractual conditions, their significance, and the difference between a condition and a promise. In that case, the Court noted that a contractual condition has been defined as an operative fact on which some particular legal relation depends and as an event, not certain to occur, which must occur, unless its non-occurrence is excused, before performance under a contract becomes due. Id. As a general rule, a condition must be exactly fulfilled before liability can arise on the contract. Id. Performance of a duty subject to a condition cannot become due unless the condition occurs or its non-occurrence is excused and unless it has been excused, the non-occurrence of a condition discharges the duty. Id. See, also, Restatement (Second) of Contracts § 225 at 165 (1981). In Harmon Cable Communications of Nebraska Ltd. Partnership v. Scope Cable Television, Inc., supra, the Court was called upon to determine whether a purchaser was entitled to recover damages or whether the right to damages was foreclosed by the purchaser’s failure to comply with notification provisions in an indemnification provision in a contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First National Bank v. Acceptance Insurance Companies
675 N.W.2d 689 (Nebraska Court of Appeals, 2004)
Gibbons Ranches v. Bailey
289 Neb. 949 (Nebraska Supreme Court, 2015)
State v. Cook
290 Neb. 381 (Nebraska Supreme Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Commercial Contractors Equip. v. Lower Platte North NRD, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commercial-contractors-equip-v-lower-platte-north--nebctapp-2015.