Commercial Casualty Ins. Co. v. Town of Breckenridge

1927 OK 488, 262 P. 208, 128 Okla. 215, 1927 Okla. LEXIS 422
CourtSupreme Court of Oklahoma
DecidedDecember 20, 1927
Docket17396
StatusPublished
Cited by4 cases

This text of 1927 OK 488 (Commercial Casualty Ins. Co. v. Town of Breckenridge) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commercial Casualty Ins. Co. v. Town of Breckenridge, 1927 OK 488, 262 P. 208, 128 Okla. 215, 1927 Okla. LEXIS 422 (Okla. 1927).

Opinion

LEACH, C.

This action was commenced in the district court of Garfield county by the town of Breckenridge, a municipality, as plaintiff, against Commercial Casualty Insurance Company, a ’ corporation, as defendant, wherein plaintiff sought to recover the sum of $1,030.04 upon a surety bond executed by the defendant to plaintiff. The plaintiff also sought to recover other sums alleged to be due under the contract and bond, but such sums were denied by the court, and no appeal was taken from the action and ruling of the court thereon.

It was alleged that the plaintiff employed an engineer, who prepared plans, specifications, and estimates for the construction of a lighting system for the town; that one McCargar submitted a proposal to construct such system for $5,932, which proposal was accepted by the town, and the bidder executed a bond on which the defendant here was surety, conditioned for the faithful performance and discharge of the conditions of the contract to construct the lighting system ; that upon the execution and delivery of such bond, the town delivered to the contractor its bonds in the sum of $6,000; that the principal, McCiarg'ar, never took any action towards carrying out his contract, and one John D. Bonford, who had drawn the plans and specifications, undertook the performance of the work and construction of the lighting system; that the town notified the bonding company that the said Bonford was attempting to carry out the contract, and the bonding company agreed that Bonfo-'d should be considered as the principal in the bond. The said Bonford failed to complete the system, and after notice to him and the bonding company, with request that they complete the system, the town employed another party to complete the lighting system ; that the cost of material and laoor in completing the system under the contract, and the amount paid out by the town, was the sum of $1,030.04, and prayed judgment for recovery of that amount.

The defendant, the Commercial Casualty Insurance Company, filed its demurrer to plaintiff’s petition, which was overruled, and it thereupon filed its answer consisting of a general denial.

Upon a trial of the cause, and after plaintiff had introduced its evidence, the defendant demurred to such evidence, which demurrer was overruled by the court, and the defendant electing to stand on its demurrer, the court directed and the jury returned a verdict in favor of plaintiff for the sum of $1,030. 04, and defendant brings the cause here for review.

The parties are referred to as they appeared in the trial court.

Plaintiff in error sets up nine specifications of error, which are presented in its brief and disposed of under three propositions or assignments.

The first assignment of error is that the court erred in overruling the demurrer of defendant to the petition of the plaintiff, and in support of such assignment, says the petition discloses that the contract upon which the bond is given and upon which the action is predicated, is void as being contrary to law, and will not therefore support an action or recovery under it, and calls attention to that part of the proposal and contract under which the contractor proposed to construct the lighting system, which part reads as follows:

“We understand that at your option we are to receive as payment for this work, bonds' in the sum of $6,000, which are legally issued by the town of Breckenridge, and that said bonds are to be turned over to us as soon as our bond, guaranteeing the faithful performance of the work, is accepted, and we will pay the town of Breckenridge in cash the difference between our bid and $6,000, or $98. Should you desire to pay us in bonds as above mentioned, we understand *217 that we are to pay you par and accrued interest for said bonds,”

—and asserts that on account of such provision, the bond is unenforceable, because the contract upon which it was given is contrary to law and in violation of statute, under the holding of this court in the case of Town of Buffalo v. Walker, 126 Okla. 6, 257 Pac. 766, and other decisions.

The facts in the ease at bar, the nature of the action, and relief sought here, are different from those in Town of Buffalo v. Walker, supra, and warrant a different holding and disposal than that urged by plaintiff in error.

Section 5014, C. O. S. 1921, is as follows:

“The object of a contract is the thing which it is agreed, on the part of the party receiving the consideration, to do or not to do.”

Let us see what the object of the contract or bond sought to be enforced in this case was. After the preparation of the plans and specifications for the proposed lighting system, the town invited bids or proposals for the construction of such lighting system, and, under the instructions to bidders, it is provided :

“A surety bond assuring the faithful performance of the contract will be required in the sum equal to 100 per cent of the contract. This bond shall be filed with the town clerk.”

Also:

“These bonds shall be in accordance with the laws of the state of Oklahoma covering bonds for the protection of towns in the construction of public improvements.”

The invitation for bids, and the instruction to bidders, referred to the plans and specifications, and it will be observed from an examination of the plans and specifications, that no reference therein is made in any manner to the exchange of or payment of the work in bonds. The bid or proposal of the principal, offering to construct and complete the system according to the plans and specifications’ contained the following paragraph relating to the furnishing of the bond sued upon:

“Accompanying this proposal is a certified check in the amount of ten per cent. (10%) of the bid which shall become the property of the town of Breckenridge if this proposal be accepted by you, and we shall fail and refuse to execute bonds within twenty (20) days from date hereof each in a sum equal to one hundred per cent. (100%) of the herein specified total contract price, said bonds to be in accordance with the laws of the state of Oklahoma, governing bonds for the protection of public improvements, as outlined in the specifications attached and shall guarantee the payment in full of all bills and accounts for contract; and the faithful compliance with the specifications hereto attached.”

The acceptance of the bid or proposal of the contractor by the town is as follows:

“Acceptance.
§ State of Oklahoma, County of Garfield, Town of Breckenridge — ss.
“The foregoing proposal is hereby accepted by the undersigned, for the town of Breckenridge, Okla., this 23 day of 'April, 1923, for the total lump sum of five thousand nine hundred thirty-two dollars ($5,932). Witness our hands and seals of said town. [Signed] H. E. Walker-, Chairman of Board of Trustees. Attest: W. G. Shaw, Town Clerk."

The bond sued upon contains the following:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chisholm v. House
183 F.2d 698 (Tenth Circuit, 1950)
Wright v. Fidelity Deposit Co. of Maryland
1935 OK 1215 (Supreme Court of Oklahoma, 1935)
Aetna Casualty & Surety Co. v. Tucker
1935 OK 726 (Supreme Court of Oklahoma, 1935)
Leininger v. Ward-Beekman & Brooks, Inc.
1929 OK 494 (Supreme Court of Oklahoma, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
1927 OK 488, 262 P. 208, 128 Okla. 215, 1927 Okla. LEXIS 422, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commercial-casualty-ins-co-v-town-of-breckenridge-okla-1927.