Combustion v. Miller Hydro

CourtCourt of Appeals for the First Circuit
DecidedJanuary 5, 1994
Docket93-1266
StatusPublished

This text of Combustion v. Miller Hydro (Combustion v. Miller Hydro) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Combustion v. Miller Hydro, (1st Cir. 1994).

Opinion

USCA1 Opinion


January 3, 1994 UNITED STATES COURT OF APPEALS
FOR THE FIRST CIRCUIT
___________________

No. 93-1266

COMBUSTION ENGINEERING, INC.

Plaintiff, Appellant,

v.

MILLER HYDRO GROUP, ET AL.,

Defendants, Appellees.

____________________

No. 93-1267

COMBUSTION ENGINEERING, INC.,

Plaintiff, Appellee,

v.

MILLER HYDRO GROUP, ET AL,

Defendants, Appellants.

____________________

ERRATA SHEET

The opinion of this Court issued on December 30, 1993, is
amended as follows:

On page 25, 1st full paragraph, line 5, "When a directed
verdict was served," should be "after a directed verdict was
ordered,".

UNITED STATES COURT OF APPEALS
FOR THE FIRST CIRCUIT
____________________

No. 93-1266

COMBUSTION ENGINEERING, INC.,

Plaintiff, Appellant,

v.

MILLER HYDRO GROUP, ET AL.,

Defendants, Appellees.
____________________

No. 93-1267

COMBUSTION ENGINEERING, INC.,

Plaintiff, Appellee,

v.

MILLER HYDRO GROUP, ET AL.,

Defendants, Appellants.
____________________

APPEALS FROM THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF MAINE

[Hon. Gene Carter, U.S. District Judge]
___________________
____________________

Before

Boudin and Stahl, Circuit Judges,
______________

and Fuste,* District Judge.
______________

____________________

____________________

*Of the District of Puerto Rico, sitting by designation.

John H. Montgomery with whom Gordon F. Grimes, David A. Soley,
___________________ ________________ _______________
Diane S. Lukac, Faith K. Bruins and Bernstein, Shur, Sawyer & Nelson
______________ ________________ _________________________________
were on briefs for plaintiff.
George S. Isaacson with whom David W. Bertoni and Brann &
____________________ __________________ ________
Isaacson were on briefs for defendant Miller Hydro Group.
________
Roy S. McCandless with whom Robert S. Frank, Mark K. Googins and
__________________ _______________ _______________
Verrill & Dana were on brief for party-in-interest appellee Kansallis-
______________
Osake-Pankki.

____________________
December 30, 1993
_________________

BOUDIN, Circuit Judge. This appeal arises out of a
_____________

complex commercial dispute, with overtones of deception,

relating to the construction of a hydroelectric facility in

Maine. In the ensuing litigation, neither the builder,

Combustion Engineering, Inc., nor the owner, Miller Hydro

Group, succeeded in recovering against the other. Both

appeal. We affirm the district court.

I. BACKGROUND

In the early 1980's, Miller Hydro set about creating a

hydroelectric facility on the Androscoggin River near Lisbon

Falls, Maine, to generate electricity. It first negotiated a

contract with Central Maine Power Company by which the latter

agreed to purchase a set amount of power from the planned

facility. Miller Hydro also obtained financing from a

Finnish bank, Kansallis-Osake-Pankki, and a license to build

the project from the Federal Energy Regulatory Commission

("FERC").

In May 1986, Miller Hydro entered into a contract--the

central document at issue in this case--with Combustion

Engineering for the latter to build the facility on a

"turnkey" basis. The turnkey contract, by cross-reference,

provided for a facility including turbines with a capacity of

7800 cubic feet of water per second.1 Under its contract

____________________

1The 7800 cfs figure, which is important to this case,
appears in technical specifications annexed to the turnkey
contract. A shorter and more general "project description,"

-3-
-3-

with Maine Central Power, Miller Hydro was expected to

provide power capacity of 14 megawatts, and the Miller Hydro

contract with Combustion Engineering also referred to this

requirement by cross-reference.

Subject to these and other specifications, it was

entirely up to Combustion Engineering to design and build the

new facility. The turnkey contract contained incentive and

penalty provisions, one of which lies at the heart of this

case. The price set for construction was fixed at just under

$24 million, but the contract provided that Combustion

Engineering would earn a sliding-scale bonus for efficiency

to the extent that the facility produced power in excess of

77,500 megawatt hours per year; a corresponding penalty

provision reduced Combustion Engineering's fixed price to the

extent that the facility was less efficient than a specified

minimum output of 73,500 megawatt hours per year.

The turnkey contract provided that the bonus or penalty

would be determined by certain tests that would be performed

by an independent tester at the completion of construction.

A protocol specified how the test would be conducted,

including a requirement that the facility be tested at a

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Richard M. Moody v. Town of Weymouth
805 F.2d 30 (First Circuit, 1986)
Loyal Erectors, Inc. v. Hamilton & Son, Inc.
312 A.2d 748 (Supreme Judicial Court of Maine, 1973)
Levine v. Reynolds
54 A.2d 514 (Supreme Judicial Court of Maine, 1947)
Wilcox v. First Interstate Bank of Oregon, N.A.
815 F.2d 522 (Ninth Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
Combustion v. Miller Hydro, Counsel Stack Legal Research, https://law.counselstack.com/opinion/combustion-v-miller-hydro-ca1-1994.