Combs v. McLynn

419 S.E.2d 903, 187 W. Va. 490, 1992 W. Va. LEXIS 154
CourtWest Virginia Supreme Court
DecidedJuly 16, 1992
Docket20729
StatusPublished
Cited by4 cases

This text of 419 S.E.2d 903 (Combs v. McLynn) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Combs v. McLynn, 419 S.E.2d 903, 187 W. Va. 490, 1992 W. Va. LEXIS 154 (W. Va. 1992).

Opinion

PER CURIAM:

This is an appeal by Shirley H. McLynn and Alyce C. Estrada-Palma from an August 28, 1991, final order of the Circuit Court of Hardy County awarding the appel-lee, Arnold Combs, d/b/a Combs Enterprises, $7,341 from appellant Estrada-Palma and $5,705 from appellant McLynn. The appellants contend that the appellee is not entitled to any amount over and above the contract prices agreed to by the appellee and the individual appellants in their two separate contracts. We reverse the decision of the Circuit Court of Hardy County and remand the matter with directions that the appellants be required to pay the $4000 remaining on their contracts less the offset previously determined by the lower court, as explained at the conclusion of this opinion.

I.

Appellants Estrada-Palma and McLynn are both retired secretaries who had previously worked in Washington, D.C., for the federal government. In September 1989, the appellants contracted with the appellee, in Mathias, West Virginia, to construct homes for two individual lots which the appellants had purchased near Lost River in Hardy County, West Virginia. 1 The contract between appellant McLynn and Combs was executed on September 1,1989, and the contract between Estrada-Palma and Combs was executed on September 18, 1989. Both contracts provided for the pur *492 chase of modular homes to be placed on lots for the total cost of $106,000 for appellant McLynn and $130,000 for appellant Estrada-Palma. The terms of payment were one-third down, with the balance, except $4,000, to be paid upon delivery of the homes to the job site. The final payment of $4,000 was to be paid upon final completion of the homes. 2

The contracts were prepared by Combs and his father-in-law, and neither appellant had any input into the terms or conditions of the contract. Both contracts provided that the seller, as noted above, would complete a turn-key job and further provided that upon encountering any unusual circumstances or conditions, the seller would stop work and contact the buyers to determine what they “want to do and the amount of additional costs.”

Upon completion of the two homes, Combs demanded final payment of $4,000 from each of the appellants. The appellants refused to pay that balance until certain corrections were made for work which was allegedly improperly completed by Combs. 3 Thereafter, on February 10,1990, Combs billed appellant Estrada-Palma for $7,049.75 and appellant McLynn for $5,932.75 for additional expenses incurred in excavation, dynamite, blasting, equipment, and rock removal.

Mr. Combs testified that he had walked the lots prior to signing the contracts and had recognized that some blasting of existing rock would be necessary. The appellants, however, testified that they had no knowledge of required blasting until appellant Estrada-Palma actually witnessed the blasting activity. Furthermore, the appellants denied knowledge of any possible obligation to pay any additional sums over and above the contract prices for blasting or other excavation activity. Mr. Combs, however, presented testimony indicating that although he had originally recognized the excavation problems and had included some expenditure for excavation within the contract price, he subsequently discovered that additional equipment was necessary and that unforeseen circumstances existed. Mr. Combs testified that, pursuant to the contractual requirement regarding unusual circumstances, he stopped work and notified appellant Estrada-Palma of the problem. Mr. Combs testified that his conversation with appellant Estrada-Palma occurred in the presence of Charles Moton, a machine operator employed by Mr. Combs. Mr. Moton testified that he did overhear a conversation between Mr. Combs and appellant Estrada-Palma in which Mr. Combs explained the excavation problems and appellant Estrada-Palma agreed to additional compensation.

With regard to appellant McLynn’s knowledge of the necessity for additional compensation for excavation, Mr. Combs introduced a telephone record indicating *493 that a twenty-three minute telephone conversation had taken place between Mr. Combs and appellant McLynn on September 14, 1989. Although Mr. Combs testified that he told appellant McLynn during that conversation that additional work and compensation would be required, both appellants deny any conversation between them and Mr. Combs regarding extra money for additional excavation work.

The appellee filed two separate civil actions on April 12, 1990, against the appellants seeking the final payment of $4,000 from each appellant and additional charges for excavation of $5,932.75 from appellant McLynn and $7,049.75 from appellant Estrada-Palma. The appellants filed answers with no counterclaims, the two actions were consolidated, and the parties waived their right to a jury trial. The matter was tried before the Circuit Court of Hardy County, and the court rendered judgment in favor of Mr. Combs on May 10, 1991.

The lower court further ordered the parties to attempt to agree upon a monetary amount to settle the claim. Upon the parties’ failure to do so, the lower court issued its finding on July 11, 1991. The court found that appellant Estrada-Palma was entitled to an off-set of $3,709 for the unsatisfactory work which was alleged and that appellant McLynn was entitled to such off-set in the amount of $4,228. Recognizing the $4,000 still owned on the contract by each party and the additional excavation costs incurred by Mr. Combs, the lower court calculated the damages as follows:

Appellant Estrada-Palma
$4.000.00 still owed on contract
+7,050.00 additional excavation
—3,709.00 for unsatisfactory work
$7,341.00 still owed
Appellant McLynn
$4,000.00 still owed on contract
+5,933.00 additional excavation
—4,228.00 for unsatisfactory work
$5,705.00 still owed

II.

The appellants claim that the circuit court erred in granting Mr. Combs any damages in excess of the contract prices. In support of that contention, they argue that the complete and valid contracts entered into between the parties provided for a turn-key delivery of the homes. The turn-key job, they contend, required Mr. Combs to complete the construction tasks and bear the risk of rising costs, delays, or other problems. Further, the appellants contend that because Mr. Combs had knowledge, prior to entering into the contracts, that some amount of excavation or blasting would be necessary, the unusual circumstances clause should not be applied. Any ambiguity within the contracts, they maintain, should be resolved against the seller, Mr. Combs.

We agree with the lower court’s determination that the unusual circumstances clause was somewhat ambiguous.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Consol Energy, Inc. v. Hummel
792 S.E.2d 613 (West Virginia Supreme Court, 2016)
Jochum v. Waste Management of West Virginia, Inc.
680 S.E.2d 59 (West Virginia Supreme Court, 2009)
Cohen v. Un-Ltd. Holdings, Inc. (In Re Nelco, Ltd.)
264 B.R. 790 (E.D. Virginia, 1999)
A.D. Powers v. Miller
1999 NMCA 080 (New Mexico Court of Appeals, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
419 S.E.2d 903, 187 W. Va. 490, 1992 W. Va. LEXIS 154, Counsel Stack Legal Research, https://law.counselstack.com/opinion/combs-v-mclynn-wva-1992.