Columbus Park Corp. v. Department of Housing Preservation & Development

170 A.D.2d 145
CourtAppellate Division of the Supreme Court of the State of New York
DecidedAugust 22, 1991
StatusPublished
Cited by5 cases

This text of 170 A.D.2d 145 (Columbus Park Corp. v. Department of Housing Preservation & Development) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Columbus Park Corp. v. Department of Housing Preservation & Development, 170 A.D.2d 145 (N.Y. Ct. App. 1991).

Opinions

OPINION OF THE COURT

Wallach, J.

This CPLR article 78 proceeding in the nature of mandamus is brought by a Mitchell-Lama limited-profit housing company organized in 1963, and seeks to compel respondent City of New York and its agency in charge of supervising city-sponsored Mitchell-Lama housing, respondent Department of Housing Preservation and Development, to issue a letter of no objection, an administrative permit necessary to clear the way for petitioner’s dissolution as a Mitchell-Lama company and conversion to a private housing cooperative not subject to the Mitchell-Lama Law (Private Housing Finance Law art II). Dismissing the petition, Supreme Court, although critical of respondents’ "laggard approach” and "extreme delay” in their [147]*147assertion of objections to dissolution, sustained the position belatedly adopted by respondents that certain covenants contained in the original deed to petitioner created a contractual duty to maintain its public status as Mitchell-Lama housing for an additional 20-year period (149 Misc 2d 66), thus depriving petitioner of access to the benefits created by the Private Housing Finance Law. We disagree, reverse the order appealed from, and grant the petition.

Petitioner’s case is based on Private Housing Finance Law § 35 (2). Enacted in 1960, this statute entitles a Mitchell-Lama company that obtained its loan after May 1, 1959, such as petitioner, to withdraw from the Mitchell-Lama program after 20 years without the consent of the city, upon payment of the remaining balance of its mortgage. To be compared is the immediately preceding subdivision (§ 35 [1]), applicable to Mitchell-Lama companies that obtained loans prior to May 1, 1959, which allows withdrawal from the program only after 35 years and then only with the consent of the city. Clearly, the purpose of section 35 (2) was to make participation in the program more attractive to private developers by a reduction of the minimum period of participation in the program and an acceleration of the time for relief from municipal constraints (see, 2550 Olinville Ave. v Crotty, 149 Misc 2d 806, 811-812).

Given a statutory provision that explicitly denies the city the authority to prohibit petitioner’s dissolution as a Mitchell-Lama company after 20 years, it is revealing that the city’s brief mentions this decisive legislation only once, and then only in a footnote that does no more than acknowledge its existence. The city’s case is built upon certain stipulations agreed to by petitioner in the parties’ contract, the land disposition agreement (LDA), which were incorporated into the deed as covenants "running with the land”; these covenants, the city argues without reference to section 35 (2), prohibit petitioner’s dissolution as a Mitchell-Lama company for at least 40 years. The city’s argument appears to be that the covenants constituted an implied, but nonetheless legally cognizable waiver by petitioner of its statutory right to withdraw from the program after 20 years. We do not agree that the covenants on which the city relies can be read to establish such a waiver.

The covenants require petitioner and its successors and assigns, for a period of 40 years, to "devote such land to the uses specified in the Urban Renewal and Project Plans”; prohibit such land from "be[ing] used for any use other than [148]*148the uses specified therefor in the Urban Renewal and Project Plans * * * or contrary to any limitations or requirements of said Plans”; and prohibit any "change[s]” in the housing project "as set forth in the Urban Renewal and Project Plans * * * without the consent of the City Planning Commission and the Board of Estimate”. The terms "uses specified in the Urban Renewal Plan” and "land use” are defined to "include the land and all building, housing, and other requirements or restrictions of the Urban Renewal Plan pertaining to such land.”

It is immediately apparent that while the meaning of the covenants must be drawn from the urban renewal and project plans, no references to any specific sections of either Plan are to be found in the covenants. This compels the city to undertake what is, in effect, a word search of the urban renewal and project plans for the term "land use” or the word "uses”. Its scan ends up by isolating a sentence of the urban renewal plan requiring that the land purchased by petitioner, designated as Parcel 16, "be used for tax-abated housing at moderate rentals or carrying charges”, in contradistinction to other residential parcels that were to be "used for public housing” or "used for full tax-paying housing”. In addition, the sentence on which the city focuses refers to Map 3, the "Redevelopment Areas Land Use Map”, depicting all of the parcels in the West Side Urban Renewal Area, and describing them as either "Public Housing”, "Tax-Abated Housing at Moderate Rentals or Carrying Charges”, "Full Tax-Paying Housing”, "Commercial”, "Public” or "Semi-Public”.

Petitioner reads the covenants to mean a 40-year commitment only to maintain the multifamily residential character of the building, and to make no changes in the building’s physical characteristics without the consent of the City Planning Commission or Board of Estimate. Thus, petitioner points out that the urban renewal plan was amended in 1979 to delete the word "used” in the sentence relied on by the city, and to substitute therefor the word "developed”, this to make clear that the land was to be developed as middle-income housing, and "used for multi-family residential purposes”, as the urban renewal plan elsewhere states, in contradistinction to the other "use” categories described in the plan—retail-commercial, general office and banking, public and semipublic. Petitioner’s reading accords with experience. It is quite common for deeds in development tracts to contain covenants prohibiting building alterations and restricting the various [149]*149parcels that comprise the tract to particular, especially residential, uses (see generally, 43 NY Jur 2d, Deeds, §§ 151-223). On the other hand, it is, at best, unconventional to argue, as the city does, that a covenant running with the land was meant to restrict ownership only to persons fitting a particular socioeconomic profile. Indeed, it is doubtful whether a private agreement, as opposed to a statute, imposing such a restriction, would be enforceable (see Shelley v Kraemer, 334 US 1; Barrows v Jackson, 346 US 249). Be that as it may, here a statute does exist restricting ownership to persons of middle-income status, but for a term of only 20 years, not 40 years as urged by the city.

The urban renewal plan was a comprehensive plan of land development and improvement for a 20-block area of the Upper West Side of Manhattan. It was part of this Plan to develop Parcel 16 as a middle-income, multifamily residence, but there is simply no evidence that it was the planners’ overall conception to freeze the socioeconomic make-up of the West Side for 40 years. It is not as if every parcel comprising the renewal area contained similar 40-year covenants. Nor is it as if petitioner received any specific benefit or consideration in exchange for relinquishing its right to withdraw from the program after 20 years.

It is well settled that the policy of the law is to favor the free and unobstructed use of realty, and that covenants restricting the use of property are strictly construed against those seeking to enforce them; furthermore the required level of proof for enforcement is the clear and convincing, as opposed to a mere preponderance, standard (Huggins v Castle Estates,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Silverman v. Silverman
304 A.D.2d 41 (Appellate Division of the Supreme Court of New York, 2003)
40 West 67th Street v. Pullman
296 A.D.2d 120 (Appellate Division of the Supreme Court of New York, 2002)
2550 Olinville Avenue Inc. v. Crotty
185 A.D.2d 200 (Appellate Division of the Supreme Court of New York, 1992)
Columbus Park Corp. v. Department of Housing Preservation & Development
598 N.E.2d 702 (New York Court of Appeals, 1992)
Bronx Park East Housing Co. v. Higgins
177 A.D.2d 457 (Appellate Division of the Supreme Court of New York, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
170 A.D.2d 145, Counsel Stack Legal Research, https://law.counselstack.com/opinion/columbus-park-corp-v-department-of-housing-preservation-development-nyappdiv-1991.