Columbus Const. Co. v. Crane Co.

98 F. 946, 40 C.C.A. 35, 1900 U.S. App. LEXIS 4107
CourtCourt of Appeals for the Seventh Circuit
DecidedJanuary 2, 1900
DocketNo. 548
StatusPublished
Cited by13 cases

This text of 98 F. 946 (Columbus Const. Co. v. Crane Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Columbus Const. Co. v. Crane Co., 98 F. 946, 40 C.C.A. 35, 1900 U.S. App. LEXIS 4107 (7th Cir. 1900).

Opinion

WOODS, Circuit Judge,

after making the foregoing statement, delivered the opinion of the court.

Concerning the letter of February 12, 1891, and its effect as a breach of the contract by the plaintiff, we said in our second opinion (46 U. S. App. 59, 65, 20 C. C. A. 233, 73 Fed. 984):

“On the facts as presented in the briefs, beyond which we have not looked, it does not appear that there was an adequate excuse for the refusal to accept further performance of the contract; * * * and, on that basis, whether other modes of relief were available or not, we think it clear that the defendant [now plaintiff] in error can have no remedy in an action upon the contract. It cannot at one and the same time repudiate an executory contract like this, in respect to a part of the subject-matter, and in respect to other parts insist upon enforcement.”

In this respect it is asserted, and seems to be conceded, that at the last trial "the facts remained precisely the same,” and, that being so, the court might without error have instructed peremptorily against a recovery by the plaintiff in any sum; and it would follow that there was no available error in any instruction touching the obligations, duties, or rights of the parties under their contract in so far as confined to the plaintiff’s right of action, — leaving it material to inquire only whether error was committed in respect to the right of the defendant to recover upon its counterclaim. In apparent recognition of ibis as the true status of the case, the argument in the brief for the plaintiff in error begins by saying that the main question, concretely stated, is “whether defendant can recover full contract price for eight-inch standard line pipe, made according to the specification of the contract, in the best manner known to the art of pipe making, but which for some reason is incapable of meet ing another, and, after all, the most important, requirement of the contract, — that it prove tight when tested in line at a pressure of one thousand pounds to the square inch.” We have not been able to perceive that this question, as stated, arises upon the record. It does [950]*950not seem to be deducible from any exception saved and assigned as error. Touching the test under a pressure of 1,000 pounds, our ruling when the case was here before was that while the plaintiff was entitled to pipe of the character stipulated, and that—

“If at the time of the delivery it remained necessary or desirable, and was practicable, by a reasonable expenditure, to bring the pipe up to the requirements of the contract, it was the privilege of the defendant [now plaintiff] in error to make the expenditure necessary for that purpose, and to exact reimbursement of the Crane Company, instead of resorting to the proof of comparative values; but if * * * the pipe met'the requirements of the modified contracts of the Indiana Company, and by reason of the Indiana statute a pipe capable of bearing a pressure of over three hundred pounds was not needed, then manifestly it was not reasonable to expend time or money on an effort to impart to the pipe a degree of strength which could be of no practical utility. Under such circumstances the ordinary rule should prevail, and the recovery should be on the basis of the difference of value between the article delivered and that which ought to have been delivered, to be determined by the market prices, or, if that should be impracticable, then probably by the difference in cost of production at the mills, — certainly not by the cost of repair or reconstruction on or along the trenches in which the pipe was to be laid, where necessarily the work would be more difficult and expensive than at the mills.” i

There does not seem to have been any attempt at the last trial to show, by market prices or otherwise, the difference in value between the pipe delivered and that contracted for. There has been no reference to evidence on that point, and the inference is fair that there was none. The evidence of the tests made of the pipe in line tended, as stated in our former opinion, “to show the quality and value of the pipe delivered as compared with that contracted for,” but that alone was not enough to afford a basis on which to compute or estimate damages on the theory of comparative values. The trial was not conducted on that theory, but, as before stated, the effort was to show that the pipe delivered was defective,— especially that the threading of the pipe and collars was defective, that the collars were too light, and that the substitution of the Hequembourg collars was necessary in order to make the line tight, even under the reduced pressure permitted by the Indiana statute. To the extent necessary to bring the pipe up to that standard, the plaintiff in error, of course, had the right to incur reasonable expense, and to exact' reimbursement, but could not at the same time claim damages on the other basis of difference of values; and there could have been no error in the refusal of an instruction which proceeded on the latter basis. The contention that, under the notice of a counterclaim which alleged the delivery of pipe in conformity to the contract, proof of strict conformity was essential to a recovery of the contract price, if in itself sound, seems not to have been insisted upon or suggested in the court below, and therefore should not be available here. If suggested, the objection could have been obviated by an amendment to the notice. No exception was saved and no error assigned which hinted at an assertion of variance between the pleading and the proof, if, indeed, such a notice of special matter of defense, accompanying the general issue, was intended to be governed by the strict rule applicable to a declaration, that the allegation and the proof must correspond. There [951]*951should certainly be a liberal practice in allowing amendments of such notices, and on appeal or writ of error any amendment should be regarded as having been made which if allowed could have caused no injustice to the adverse party.

The first specific objection to the charge of the court is that in a number of passages, to which exceptions were saved, the plaintiff was required to sustain the issues of which it had the burden by “satisfactory evidence,” and not simply by a preponderance of the evidencie; but the meaning of the entire charge was clear, as in some instances it was explicitly stated, that the jury should be satisfied by a preponderance of the evidence. The last expression of the court on the point was too plain to be mistalren, when, after stating that the plaintiff was not entitled to recover “unless it has established a cause of’action,” the court added, “It must be established by a preponderance of the evidence.” In view of the nature of the issue;, however, which was whether the pipe was originally defective; in the threading or in the weight of the colliers, or was injured through the negligemee or want of skill of those employed to lay it, — on which latter point the plaintiff, having kept and used the pipe in line, certainly had the burden óf proof, — it is not clear that more than a mere preponderance of evidence might not properly have been required to establish a right of recovery on the declaration.

This objection to the charge; ought not to prevail for the further-reason that it is not pointed out in any exception taken, nor in any specification of error, according to the reeiuirement of our rules 10 and 11 (31 C. C. A. cxlv., 90 Fed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Lesser
66 F.2d 612 (Second Circuit, 1933)
Cincinnati Traction Co. v. Leach
169 F. 549 (Sixth Circuit, 1909)
Ball v. United States
147 F. 32 (Ninth Circuit, 1906)
Chicago City Railway Co. v. Brecher
112 Ill. App. 106 (Appellate Court of Illinois, 1904)
Lafayette Bridge Co. v. Olsen
108 F. 335 (Seventh Circuit, 1901)
Hutchinson Cooperage Co. v. Snider
107 F. 633 (Seventh Circuit, 1901)
Cass County v. Gibson
107 F. 363 (Sixth Circuit, 1901)
Western Union Tel. Co. v. Burgess
108 F. 26 (Sixth Circuit, 1901)
Adams v. Shirk
104 F. 54 (Seventh Circuit, 1900)
McNulta v. West Chicago Park Com'rs
99 F. 900 (Seventh Circuit, 1900)
In re Franks
95 F. 635 (S.D. Alabama, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
98 F. 946, 40 C.C.A. 35, 1900 U.S. App. LEXIS 4107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/columbus-const-co-v-crane-co-ca7-1900.