Columbia Gas Transmission Corp. v. Limited Corp.

759 F. Supp. 343, 113 Oil & Gas Rep. 436, 1990 U.S. Dist. LEXIS 18926, 1990 WL 270988
CourtDistrict Court, E.D. Kentucky
DecidedOctober 1, 1990
Docket6:06-misc-00014
StatusPublished
Cited by1 cases

This text of 759 F. Supp. 343 (Columbia Gas Transmission Corp. v. Limited Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Columbia Gas Transmission Corp. v. Limited Corp., 759 F. Supp. 343, 113 Oil & Gas Rep. 436, 1990 U.S. Dist. LEXIS 18926, 1990 WL 270988 (E.D. Ky. 1990).

Opinion

MEMORANDUM OPINION AND ORDER

HOOD, District Judge.

This diversity action is before the Court on cross-motions for summary judgment under Rule 56, Fed.R.Civ.P. [Record Nos. 41 and 55]. Fully briefed and argued, the matter is ripe for decision.

I. INTRODUCTION

This case presents three issues for the Court’s consideration. First, is the plaintiff Columbia Gas Transmission Corporation [TOO] entitled to recover compensatory damages for damage to its natural gas pipelines caused by the defendant Limited Corporation [Limited] and its agents? Second, is Limited responsible for the costs incurred in upgrading and installing road crossings and relocating portions to TCO’s existing pipelines encountered by defendants in the course of their mining operations? Third, is Limited responsible for the *345 cost of relocating existing pipelines that are currently located in areas to be mined by Limited? Based upon the deposition testimony taken in this action, Limited’s responses to requests for admissions, and the affidavits submitted by TCO, there are no genuine issues of material fact which prevent the Court from adjudicating these questions. For the reasons discussed below, TCO is entitled to judgment as a matter of law on these issues.

II. PROCEDURAL HISTORY

TCO instituted this action against defendants Limited and Bruin Trucking Company [Bruin] seeking injunctive relief and compensatory damages arising out of the defendants’ interference with and damage to a number of TCO’s natural gas pipelines located in Pike County, Kentucky. 1 On January 17, 1989, the Court, per Judge Forester, granted TCO’s request for a temporary restraining order enjoining the complained of activities of the defendants. Thereafter, on January 20, 1989, the Court, again per Judge Forester, entered an agreed preliminary injunction which continued the injunctive relief set out in the temporary restraining order.

In conjunction with the agreed preliminary injunction, the parties also entered into an agreement which had the effect of accommodating the rights asserted by the respective parties. [See Record No. 42, Exhibit A]. Pursuant to the terms of this agreement, the defendants paid $69,000 to TCO which represented the anticipated costs and expenses to be incurred in installing road crossings and related construction activities to protect TCO’s pipelines from further damage and to avert the dangerous situation created by the defendants’ mining activities.

On November 1, 1989, Limited moved the Court for leave to assert a counterclaim against TCO. This motion was sustained and Limited’s counterclaim was filed November 28, 1989. By this counterclaim, Limited seeks to recover the $69,000 paid to TCO under the above-referenced agreement. Limited asserts that, pursuant to the terms of an indenture of lease entered into between the parties’ predecessors-in-title, TCO should be required to repay this sum to Limited.

On or about March 1, 1990, Limited moved the Court for leave to amend its counterclaim to assert an additional claim for declaratory relief. On March 28, 1990, the Court sustained this motion and directed that the amended counterclaim be filed.

III. STATEMENT OF FACTS

1. TCO engaged in the production, purchase, underground storage, transportation and sale of natural gas in interstate commerce in Kentucky and other states. As part of the operation of an interstate gas pipeline system, TCO owns and operates several natural gas pipelines and producing natural gas wells which are located near the community of Phelps in Pike County, Kentucky. [Complaint, ¶¶ 1, 8, 9 and 10; Answer, ¶¶ 1, 2].

2. TCO’s rights in the real property which is involved in this action emanate from an indenture of lease dated July 24, 1930 [the Kentland lease or lease] and entered into between Kentland Coal & Coke Company [Kentland] and Howe Oil and Gas Company [Howe]. [See Record No. 42, Exhibit B]. Under the lease, Kentland leased to Howe, TCO’s predecessor, all the oil and gas underlying approximately 65,299 acres of land located in Pike County, Kentucky and Buchanan County, Virginia. [Complaint, n 11; Answer, t! 2].

3. As successors-in-interest to Howe, TCO acquired “the right to lay pipelines ... and such other necessary rights for the efficient operation of the demised property for oil, gas and gasoline_” In connection with these rights, TCO maintains a surface right-of-way above the pipelines *346 and around the wells. [Complaint, 111113, 14].

4. Limited is engaged in the business of mining coal by strip mine and mountain top removal methods. Limited conducts its mining activities through contract miners. [1/19/90 Swiger depo., p. 9]. Limited asserts that, through various assignments, it acquired the coal mining rights in the property covered by the Kentland lease.

5. Limited’s mining operations and the above-referenced pipelines of TCO are located within the area covered by the Kent-land lease. [Complaint, 1111; Answer, U 2], The specific locations of the pipelines in issue are identified on the map attached as Exhibit 2 to the deposition of Herbert Swiger, the General Superintendent of Limited. [1/19/90 Swiger depo., p. 14].

6. The three pipelines involved in this litigation were originally constructed in 1960. These pipelines are designated as p-84, PW-8765 and PW-8887. At the time defendants commenced their mining activities on the subject property, TCO’s pipelines had been in place for approximately 29 years. [3/30/90 Hall Affidavit, ¶2 2 ; 1/19/90 Swiger depo., p. 21].

7. PW-8765 is located both above and below the surface and connects natural gas flow from Well 8765 to Line P-84. [Complaint, U 9], The defendants’ encroachment on TCO’s leasehold rights concerning PW-8765 was first discovered on or about December 9, 1988 by A.T. Hall, an Operations Supervisor for TCO. Prior to this time, TCO was unaware of the defendants’ mining activities on the subject property. [3/30/90 Hall Affidavit, II3].

8. On December 9, Mr. Hall observed that Bruin, Limited’s contract miner, had caused several large boulders to lodge against PW-8765 in an area running parallel to Bruin’s coal haul road. The area involved is more particularly described in Attachment 1 to the 3/30/90 Hall Affidavit. [1/17/89 Hall Affidavit, II2; 1/19/90 Hall depo., pp. 20-21], In addition to dumping debris against this pipeline, Limited also crossed the pipeline in the course of its mining activities. [1/19/90 Swiger depo., p. 34; 3/30/90 Hall Affidavit, Attachment 2].

9. With respect to PW-8765, Limited has admitted that the defendants “caused mining debris to be pushed against portions of ... [PW-8765] located above the surface of the area being mined and parallel to the coal haul road being utilized by Limited Corp. and/or Bruin_” and that “[t]his activity occurred within the area subject to the Kentland lease.” Limited has also admitted that, “[o]n or before December 9, 1988, ... [it] crossed portions of ... [PW-8765 which were] located in an area subject to the Kentland lease.” [Answers to Request for Admissions to the Defendant Limited Corporation, Response No. 11 and 14]-

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
759 F. Supp. 343, 113 Oil & Gas Rep. 436, 1990 U.S. Dist. LEXIS 18926, 1990 WL 270988, Counsel Stack Legal Research, https://law.counselstack.com/opinion/columbia-gas-transmission-corp-v-limited-corp-kyed-1990.