Columbia Concrete Pipe Co. v. Knowles

219 P.2d 557, 36 Wash. 2d 602, 1950 Wash. LEXIS 332
CourtWashington Supreme Court
DecidedJune 20, 1950
Docket31149
StatusPublished
Cited by4 cases

This text of 219 P.2d 557 (Columbia Concrete Pipe Co. v. Knowles) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Columbia Concrete Pipe Co. v. Knowles, 219 P.2d 557, 36 Wash. 2d 602, 1950 Wash. LEXIS 332 (Wash. 1950).

Opinion

Beals, J.

The plaintiff in this action, Columbia Concrete Pipe Company, a corporation, filed its complaint October 2, 1947, alleging its corporate existence; that, during the month of August, 1945, the defendants, Clayton C. and Jane Doe *603 Knowles, husband and wife, became indebted to plaintiff in the sum of $1,414.87 for goods delivered to them by plaintiff, and that no payment had been made upon the account, plaintiff praying for judgment against defendants for the amount above stated, with interest and costs.

The defendants answered the complaint, denying plaintiff’s corporate existence, admitting that merchandise was delivered to them by plaintiff, but denying all indebtedness to the plaintiff.

By way of an affirmative defense and counterclaim (also referred to in the answer as a cross-complaint), the defendants alleged that, during the summer of 1945, plaintiff delivered merchandise, consisting principally of concrete pipe, and installed the same on defendants’ land to convey pumped water for irrigation purposes; that plaintiff had guaranteed the pipe to be fit for the use above referred to and for which plaintiff installed the pipe; that the pipe was improperly installed; that it was not usable for carrying pumped water for irrigation, and that, by reason of defects in the pipe line and the negligent installation thereof, as pleaded in their answer, defendants had suffered and were continuing to suffer damage to the land and crops thereon, their damages amounting to ten thousand dollars (which amount was, apparently, later raised to the sum of $14,630). Defendants prayed that plaintiff’s action be dismissed, and that they be awarded judgment for the damages demanded.

Plaintiff replied, denying the allegations of the affirmative defense set forth in the answer.

The action was tried to the court and resulted in the entry of findings of fact and conclusions of law in plaintiff’s favor, followed by a judgment in favor of plaintiff for the sum demanded in its complaint.

From the judgment rendered against them, the defendants have appealed. They have also appealed from the court’s refusal to award defendants judgment against the plaintiff, as demanded in their “counterclaim and cross-complaint.” In their brief, appellants make the following assignment of errors:

*604 “(1) The trial court erred in making Finding of Fact No. 4 in finding that during the year 1945 there were only ‘minor leaks’ occurring in said pipe line, and in finding that said leaks were repaired ‘pursuant to the agreement between the parties hereto.’
“(2) The court erred-in Finding of Fact No. 5 that the reasonable' and agreed price for said labor and materials was the sum of $1,414.87.
“(3) The court erred in its Finding of Fact No. 6 that Respondent has not breached any warranty as to fitness of use and purpose for which the pipe line was intended and that Appellants have failed in proof of damage resulting therefrom.
“ (4) The trial court erred in granting judgment against the Appellants in any sum whatsoever and in failing to grant a judgment in favor of the Appellants and against Respondent for the sum of $14,630.00, which represents damages sustained by Appellants as a direct and natural result of Respondent’s breach of an express and implied warranty and gross negligence.
“(5) The court erred in finding that Respondent Company was a corporation at the commencement of this action, and entitled to maintain suit.”

We shall refer to Clayton C. Knowles as though he were the sole appellant.

From the evidence, it appears that, during the year 1944, appellant purchased sixty-three acres of farm land located in the Methow valley in Okanogan county, the land being then irrigated by water taken from a canal on the west side of the property and carried, by gravity flow, through galvanized pipe. Appellant’s father, Charles Knowles, moved to the farm in the spring of 1944 and was in charge of the farming operations thereafter. Appellant resided on the farm from about June 1, 1945, until the middle of August following, when he moved to Morton, Washington, where he lived until January, 1947, at which time he removed to California.

While appellant was on the farm in 1945, the season being extremely dry, he decided to procure additional water for irrigation purposes by pumping from the Methow river on the east side of the property, and consulted George Wagenman, who then represented respondent as its “field man.” *605 Appellant stated that he wanted a pipe line that would carry fifteen hundred gallons of water per minute, under pressure, from the river to the edge of that portion of the farm growing alfalfa, and, from that point, one thousand gallons per minute to the end of the line, to be there turned into an open ditch for irrigating another portion of the farm. The proposed pipe line was to run across appellant’s property from east to west, and to be so installed that water (when available) could also be taken by gravity flow from the canal on the west side of the farm, replacing the existing irrigation system.

Wagenman examined the land, and recommended the use of ten-inch concrete pipe, informing appellant that respondent would not guarantee the pipe line unless it installed the same. Appellant agreed, and ordered the pipe installed, stressing the need for haste as the crops required water. After further discussion, it was agreed that appellant would dig the ditch for the installation of the pipe and accomplish the backfilling after the pipe had been laid. This portion of the agreement was later modified, and respondent accomplished the backfilling after laying the pipe.

Appellant procured a machine referred to as a “road patrol” and used it in digging the ditch. Appellant and his father both testified that Wagenman did not tell them how deep the trench should be dug, and that he did not inspect it after it was prepared. It appears that respondent’s foreman, who was in charge of the installation of the pipe line, told Wagenman that the ditch was not deep enough for proper installation, but it does not appear that this criticism was mentioned either to appellant or to his father. Concerning this matter, Wagenman testified, on direct examination, as follows:

“Q. Did you ever give Mr. Knowles instructions as to the way it should be dug? A. I told him that we would like fifteen inches of cover over the pipe when a job is complete. Q. Was it necessary for you to do any work in connection with the digging of the ditch? A. Well, this road patrol leaves a V-shaped ditch in the bottom and we went along and squared that up. . . . Q. Going back to the ditch that was dug by Mr. Knowles. What was the depth of the *606 ditch dug by him? A. Oh, I imagine in certain places, only twelve inches deep. Q. What is ordinarily required for depth in laying a ten-inch pipe? A. Oh, twenty-seven to thirty inches. Q. And did Mr. Knowles do the backfill of the pipe? A. No. Q. Mr. Wagenman, did you call Mr. Knowles’ attention to the depth of the ditch at the time that it was dug? A. Well, I don’t remember but we usually do in cases like that.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fossum v. Timber Structures, Inc.
341 P.2d 157 (Washington Supreme Court, 1959)
Frisken v. Art Strand Floor Coverings, Inc.
288 P.2d 1087 (Washington Supreme Court, 1955)
Eliason v. Walker
256 P.2d 298 (Washington Supreme Court, 1953)
Mills v. Meyer
243 P.2d 491 (Washington Supreme Court, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
219 P.2d 557, 36 Wash. 2d 602, 1950 Wash. LEXIS 332, Counsel Stack Legal Research, https://law.counselstack.com/opinion/columbia-concrete-pipe-co-v-knowles-wash-1950.