Columbia Casualty Co. v. Barry

149 So. 567, 111 Fla. 517
CourtSupreme Court of Florida
DecidedJuly 13, 1933
StatusPublished
Cited by4 cases

This text of 149 So. 567 (Columbia Casualty Co. v. Barry) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Columbia Casualty Co. v. Barry, 149 So. 567, 111 Fla. 517 (Fla. 1933).

Opinion

Buford, J.

Defendant in error sued plaintiffs in error, the declaration containing six counts.

Plaintiff in error, Louis Fleisher Construction Company, a Florida corporation, was' a contractor agreeing to con *518 .struct a certain building for defendant in error, plaintiff in the court below, and Columbia Casualty Company, a New York corporation, was surety on the contractor’s bond. Before the construction was completed, as it is averred in the declaration, the contractor defaulted and became unable to carry out its contract and thereupon the owner completed the contract. '

. The declaration claims' damages which are here in controversy by reason of the plaintiff in the court below being required to pay two sub-contractors large sums of, money which should have been paid by the contractor, and for which he claimed in his declaration that the surety company was liable.

Many pleas were filed. The amended plea No. 23 was in the following language:

“As to the third count this' defendant says that after the execution by the principal and the said C. J. Balliet of the sub-contract, dated July 25th, 1928, for the furnishing and installation of the heating system in said school building as alleged' in’ said third count, the said C. J. Balliet commenced the performance of said contract and under and by virtue of the statutes of the State of Florida a person not in privity with the owner who is performing or is about .to perform by himself or others labor or is furnishing or is about to furnish’ material may deliver to the owner or his agent a written cautionary notice that he will do certain work or will furnish certain materials or both and that a lien shall exist from the time of the s'ervice of the notice for the amoúnt unpaid on the contract of and by the owner to the contractor, and that such service shall also create a .personal liability against the owner of the property in favor .of the lienor giving such notice for the amount due him, as .aforesaid, but not to a-greater extent than the amount of such original contract; that under and. by virtue of said *519 statutes and pursuant thereto the said C. J. Balliet, on or about September 28th, 1928, delivered to Bishop Barry, the plaintiff herein and the owner, and to his agent, the Reverend Father Michael Fox, a written cautionary notice, notifying the said Bishop Barry that the said C. J. Balliet had contracted and agreed with the principal to furnish and install heating fixtures and appliances in the said school building at and for the amount of $6,581.77, and notifying the said Bishop Barry that the s'aid C. J. Balliet was then engaged in furnishing labor and materials in the installation of said heating fixtures and appliances for the said Saint James Roman Catholic parish school building then under construction and notifying the s'aid owner that should the contractor fail to pay to the said C. J. Balliet the said agreed amount for the furnishing of labor and material in the installation of said heating fixtures and appliances in said school building, then the said C. J. Balliet would call upon and look to the owner of said school building and the land upon which it was' located to make payment to him, the said C. J. Balliet, of the same or any part thereof which the said principal might fail to pay to the said C. J. Balliet when the said sum or any part thereof should become due and payable and on which the said contractor should make default in payment thereof; that the said C. J. Balliet, during the months of September, October and November, 1928, furnished labor and materials in performance of the said contract to the extent and value of $2,673.95, of which payment was' made of $2,276.76, leaving unpaid for said months the amount of $397.69; that upon the service of the said written cautionary notice as aforesaid and the furnishing of said labor and materials by the said C. J. Balliet to the extent of $2,673.95, as aforesaid, it became and was the duty of the •plaintiff to hold.and retain from the contract price payable to Louis Fleisher Construction Company a sufficient amount *520 to pay the sum remaining unpaid to the said C. J. Balliet, yet the said plaintiff, unmindful of his duty in the premises, did not retain from the said contract price, payable to the principal, ^any sum whatever to satisfy the claim of the said C. J. Balliet, but on the contrary did, after the s'ervice of said cautionary notice and after the furnishing of labor and materials to the extent of $2,673.95 as aforesaid, and without the knowledge or consent of this defendant, pay to the principal large sums of money, to-wit: $10,325.45, on or about December 4th, 1928, and $12,164.66 on or about January 5th, 1929. This defendant further avers that the said C. J. Balliet during the month of December, 1928, furnished labor and materials in the performance of the said contract to the extent and value of $2,940.95; that upon the service of said written cautionary notice, as aforesaid, and the furnishing of said labor and materials by the said C. J. Balliet to the extent and value of $2,940.95, as aforesaid, it became and was the duty of the plaintiff to hold and retain from the contract price, payable to the s'aid Louis Fleisher Construction Company, a sufficient amount to pay the amount thus owing to the said C. J. Balliet, yet' the said plaintiff, unmindful of his duty in the premises, did not retain from the contract price payable to the principal herein any sum whatever to satisfy the claim of the said C. J. Balliet, but on the contrary did, after the service of s'aid written cautionary notice and after the furnishing of said labor and materials to the extent and value of $2,940.95, as aforesaid, and without the knowledge or consent of this defendant, pay large sums of money to the principal herein, to-wit, $12,164.66 on or about January 5th, 1929. This defendant further avers that in the suit filed by s'aid C. J. Balliet in the Circuit Court of Orange County, Florida, as alleged in said Third Count, the said C. J. Balliet sought to recover for the value of said labor and materials furnished during *521 the month of December, 1928, as heretofore alleged, and the balance unpaid of the value of said labor and materials furnished during the months' <pf September, October and November, 1928, as heretofore alleged, and that the final decree rendered in favor of the said C. J. Balliet, as alleged in said Third Count, was solely for the value of said labor and materials furnished during the month of December, 1928, as heretofore alleged, and the balance unpaid of the value of said labor and materials furnished during the months of September, October and November, 1928, as heretofore alleged.”

Amended plea No. 26 was like plea No. 23 except that it applied to the payments made to Zane •& Webber, co- ' partners, whereas the 23rd plea applied to payments made to C. J. Balliet.

Demurrers were sustained to these pleas'. We are not advised as to what the other pleas were.

A trial resulted in a judgment in favor of the plaintiff.

Plaintiffs in error contend that the sustaining of demurrers to the pleas above referred to constituted error which would warrant reversal under the authority of the opinion and judgment of this Court in the case of Gato v. Warrenton, 37 Fla. 542, 19 Sou.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Phoenix Indemnity Co. v. Board of Public Instruction
114 So. 2d 478 (District Court of Appeal of Florida, 1959)
Pan American Surety Co. v. Board of Public Instruction
76 So. 2d 868 (Supreme Court of Florida, 1955)
Standard Accident Insurance v. Bear
184 So. 97 (Supreme Court of Florida, 1938)
State Ex Rel. Gillespie v. Walsma
152 So. 196 (Supreme Court of Florida, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
149 So. 567, 111 Fla. 517, Counsel Stack Legal Research, https://law.counselstack.com/opinion/columbia-casualty-co-v-barry-fla-1933.