Coloritype Co. v. Williams

78 F. 450, 24 C.C.A. 163, 1897 U.S. App. LEXIS 1686
CourtCourt of Appeals for the Second Circuit
DecidedJanuary 7, 1897
StatusPublished

This text of 78 F. 450 (Coloritype Co. v. Williams) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coloritype Co. v. Williams, 78 F. 450, 24 C.C.A. 163, 1897 U.S. App. LEXIS 1686 (2d Cir. 1897).

Opinion

LACOMBE, Circuit Judge.

It will be seen from the above statement of facts that a part only of the questions which were litigated in the circuit court are presented here for review. The several objections to the judgment which have been submitted on the argument will be separately considered.

The court charged the jury, that “by the terms of the contract between the parties at all- times after February 1st the plaintiff was either bound to pay the stipulated penalty or was entitled to receive the stipulated rent; and the date when the penalty ceased and the rent began was the same.” Such objections as have been urged to this part of the charge as not correctly construing the contract between the parties will be considered hereafter. It is quoted here as introductory to the first point of plaintiff in error, in which it is contended that the verdict cannot be sustained even if it is held that the contract was properly construed by the trial justice. Plaintiff conceded that under such construction the building was not completed ready for occupancy on February 1st, the date when rent was to begin, provided plaintiff had fulfilled his covenants, but contended that it was so completed on February 6th. Defendant contended that it was not so completed as to terminate the penalty clause, and make defendant liable for rent, until April 2d. It is urged here that the court should have instructed the jury to decide this contention in favor of the defendant. The record, however, shows that there was a conflict of testimony as to the day when the building was completed within the terms of the contract as the court construed them. It was not error, therefore, to leave that question to the jury; on the contrary, it would have been error to take it from them. The defendant, however, seeks to show by.an analysis of the verdict that it is to be assumed that the jury fixed upon some day other than February 6th, or April 2d, which supposed date the evidence does not sustain. That question is not before this court. If the verdict is supposed to be against the weight of evidence, that point should be raised by motion for a new trial; and the decision of the trial judge on that point is not reviewable by writ of error in the federal courts. Upon conflicting evidence the question was submitted to [453]*453the jury — properly so submitted, since it is apparent that the evidence was conflicting — with instructions to bring in a general verdict; and their general verdict upon such conflicting evidence, not having been set aside by the court, must stand here as a finding of fact that at some date subsequent to February 6th the building was completed, the running of the penalty clause stopped, and liability for rent incurred. If defendant wished to have the jury fix that date specifically, it should have asked for a special verdict upon a question properly framed. This court cannot set aside the general verdict upon a guess as to what was the mental process by which the jury reached the conclusion which they have expressed therein. Moreover, we find no assignment of error which covers this point.

The main question In the case is whether the trial judge correctly construed the contract between the parties, and properly instructed the jury thereon. The lease was executed August 30,1893. It demised to defendant the four upper lofts of the building known as “No. 32 Lafayette Place” !’or* the term of five years from February i, 1894; the lessee covenanting to pay $15,000 a year, in equal monthly payments on the 1st day of each month. Subsequently, on September 7,1893, the parties entered into a further written agreement, in substance as follows: It recites that defendant has executed the lease, and obligated itself, under the covenants thereof, upon the express condition that all the agreements hereinafter in the agreement contained shall be fully performed by plaintiff. Williams covenants and agrees that the building now in course of erection shall be practically completed in compliance with the plans, * ⅞ which ⅛ * * provide for the erection of a substantial eight story and basement fireproof building, * ⅝ * and on the top loft a suitable skylight or skylights, providing the saíne are acceptable to * 'f ⅞ the building department, * * * and not objectionable to the board of fire underwriters. Also that the building is to be furnished with freight and passenger elevators, etc. Williams further stipulated that:

“He will have the premises ready for occupancy hy defendant on or before February 1, 1894, excepting, however, such minor details as gas fitting, steam fittings, painting, and the various nonessential and minor details of the said buildings as cannot be completed on or before February 1, .1894.
“That he agrees to give the [defendant] possession oj the premises teased to them at as early a date before the first day of February, 1894, as he can have the loits in suitable condition ready for occupancy, or for them to place their machinery in; but the rent, to commence on February 1,189-4, or as soon thereafter as the building is completed.
“That in case the building is not ready for occupancy on the first day of February, 1894, the measure of damages shall be a forfeiture of fifty dollars ($80.00) per day during the month of February, and one hundred dollars ($100.00) per day during the month of March and thereafter.
“But it is covenanted that, in the event of the said John T. Williams being prevented from completing the said building on the first day of February, 1894, or later, by "reason of the occurrence of a strike which shall prevent the completion of the said premises on or after that date, he shall be exonerated and held blameless of and from any or all liability by reason of the delay in the completion of said building caused by said strike.”

[454]*454.The defendant has argued at great length that this agreement so modified the original lease that, although the premises leased might be ready for occupancy as that phrase is defined in the agreement, on February 1st, or some subsequent day, there would be no liability .for rent, and defendant would be entitled to exact the overtime penalty until the whole building was entirely completed. There is no force in this contention. The italicized paragraph above quoted provides for the single case where the defendant is put into possession before the beginning of the .lease. It is a parenthetical clause in no wise affecting the principal part of the agreement, which provides in plain language-.that plaintiff will have the premises ready for occupancy, excepting the minor details, on February 1st; that, if not ready for occupancy then, the specified-daily penalty shall be paid, unless the failure was due to the occurrence of a strike. The trial judge thus construed the contract between the parties as made out by the lease and agreement, and charged the jury accordingly. In this there was-, no error. Moreover, the contract is so plain and unambiguous-upon its face that he correctly refused to admit evid'enee of oral conversations and negotiations prior to the making of the contract, which were offered upon the theory that they would elucidate alleged obscurities in the contract which, so far as we can see, dp not exist. This disposes of most -of the 46 assignments of error. They are too numerous to review in detail.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
78 F. 450, 24 C.C.A. 163, 1897 U.S. App. LEXIS 1686, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coloritype-co-v-williams-ca2-1897.