Colorado School v. Rocky Mountain

Colorado Court of Appeals·Decided June 11, 2026·No. 25CA0679·Unpublished

Opinion

25CA0679 Colorado School v Rocky Mountain COLORADO COURT OF APPEALS

Court of Appeals No. 25CA0679 Arapahoe County District Court No. 23CV30301 Honorable Michelle Amico, Judge Honorable Elizabeth Beebe Volz, Judge

Colorado School District Self Insurance Pool and Widefield School District No. 3,

Plaintiffs-Appellees, v. Rocky Mountain Construction Company, Defendant-Appellant.

JUDGMENT AFFIRMED

Division V

Opinion by JUDGE YUN

Lipinsky and Schutz, JJ., concur

NOT PUBLISHED PURSUANT TO C.A.R. 35(e)

Announced June 11, 2026

Hall & Evans, LLC, Ryan L. Winter, Matthew J. Ninneman, Ethan E. Zweig, Denver, Colorado, for Plaintiffs-Appellees

Lorber, Greenfield & Olsen, LLP, Thomas F. Olsen, Konrad R. Schreier, Greenwood Village, Colorado, for Defendant-Appellant

¶1 Defendant, Rocky Mountain Construction Company (RMCC), appeals the district court’s denial of its motion for directed verdict and subsequent denial of its motion for post-trial relief after a jury returned a verdict in favor of plaintiffs, the Colorado School District Self Insurance Pool (SIP) and Widefield School District No. 3 (the school district), on their breach of contract claim. We affirm the judgment.

I. Background

¶2 After two summer hailstorms damaged Mesa Ridge High School, the school district and SIP contacted RMCC to perform mitigation and repair work. With the SIP’s approval, RMCC began mitigation efforts at the school in September 2018. RMCC then submitted three estimates, covering three phases of work at the school, totaling $3,929,710.12, to be paid through a series of progress payments.

¶3 Each estimate specified work to be performed in more than 150 areas of the school, including classrooms, offices, hallways, and common spaces. Extensive repairs were required in any room or hallway with a drop ceiling. The school district agreed to work with RMCC, and the SIP issued progress payments as RMCC

completed certain percentages of the work set forth in the estimates.

¶4 During the second phase of work, the SIP’s claims adjuster requested that RMCC’s chief executive officer (the CEO) provide documentation substantiating RMCC’s incurred costs because this phase involved the acquisition and installation of materials. By that point, the school district and SIP had already paid RMCC $3,278,643.12, but the claims adjuster needed to verify costs before issuing further payments. The CEO initially agreed to supply the documentation but later insisted that the original estimates were sufficient. Because RMCC did not provide the documentation, the SIP paused all payments to RMCC in January 2020.

¶5 The school district and SIP retained an independent building consultant to audit the costs before resuming payments. In an April 2020 report, the consultant found that RMCC had billed $846,318.88 for work it had never performed. Most of this overbilling resulted from RMCC overcounting rooms with drop ceilings — listing many rooms with drywall ceilings, where no work was needed, as rooms with drop ceilings, where substantial work

was required. The school district and SIP notified RMCC of this overbilling, but RMCC again declined to verify its costs.

¶6 In February 2023, the school district and SIP filed a complaint alleging, among other claims, breach of contract. RMCC moved for summary judgment, arguing that the statute of limitations barred the breach of contract claim. RMCC contended that such a claim is subject to a three-year statute of limitations that begins when the breach should have been discovered by the exercise of reasonable diligence. See §§ 13-80-101(1)(a), -108(6), C.R.S. 2025. RMCC asserted that the February 2023 complaint was “not timely” because the school district and SIP should have discovered the breach before they received the consultant’s April 2020 report. Since all three estimates were available by December 2019 and drop ceilings are easily identifiable, RMCC argued that the statute of limitations began running when “the estimates were provided to [the school district and SIP].”

¶7 The district court denied RMCC’s motion for summary judgment, finding “that determining when [the school district and SIP] knew, or should have known, of any alleged breach is a

disputed question of fact precluding summary judgment on this issue.”

¶8 During trial, after the school district and SIP presented their case-in-chief, RMCC moved for a directed verdict on the breach of contract claim under C.R.C.P. 50. RMCC reiterated its statute of limitations argument, asserting that the school district and SIP — specifically, the school district’s operations manager and the SIP’s claims adjuster — should have discovered the breach by comparing the estimates to the work performed onsite. Additionally, RMCC argued that the SIP “[does not] have any witness who will testify . . . that they have a contract with [RMCC].”

¶9 The district court denied RMCC’s motion for directed verdict, rejecting its arguments regarding the statute of limitations and the existence of a contract. As for the existence of the contract, the court observed the following:

The very first question the jury asked in the beginning of this case was: Was this a fixed price contract or was it a time and material[?]

And no witness so far has been able to answer that question. I don’t know what contract you had. But I also find that it’s so up in the air there could be unjust enrichment. There could be waiver.

. . . I do think it is for the jury to decide when whoever was paying — I mean, obviously, [the SIP] was paying for the claim. The [school district] was getting the services. It’s difficult for me to understand why, if you’re going to pay over a million dollars you don’t have any idea of whether or not the work you paid for was the work you wanted. . . . I’m looking at both sides here.

The court decided to “leave [these issues] up to the jury” because “there’s so much information here and so many ways that a claim could potentially be made.”

¶ 10 After a five-day trial, the jury returned a verdict for the school district and SIP. Specifically, the jury answered the following questions in the special verdict form:

QUESTION NO. 1: Do you find that a contract was formed between plaintiffs [the SIP] or [the school district] and defendant [RMCC]? (yes or no)

ANSWER NO. 1: Yes

....

QUESTION No. 4: Did [RMCC] breach the contract? (yes or no)

ANSWER NO. 4: Yes

....

QUESTION NO. 6: If you determined that [RMCC] breached the contract, did [RMCC]

prove by a preponderance of the evidence its affirmative defense based on the statute of limitations? (yes or no)

ANSWER NO. 6: No.

In accordance with the jury verdict, the court awarded the school district and SIP $846,318.88 in damages.

¶ 11 RMCC then moved for post-trial relief under C.R.C.P. 59, requesting either “an amended verdict on the statute of limitations because the jury’s [verdict] is irreconcilable with . . . the law, testimony, and the evidence admitted at trial” or a “new trial on the [s]tatute of [l]imitations issues.” The district court observed that RMCC’s motion was, in essence, a request for judgment notwithstanding the verdict (JNOV) or, in the alternative, for a new trial. The court denied both requests, reiterating that the statute of limitations was a factual question properly resolved by the jury.

¶ 12 RMCC now appeals.

II. Analysis

¶ 13 RMCC contends that the district court erred by denying its directed verdict motion because the SIP and school district failed to prove the existence of a contract during their case-in-chief. RMCC

also maintains that the court erred by denying its motions for directed verdict and JNOV on the grounds that the statute of limitations barred the lawsuit as a matter of law.1 We begin by providing the applicable standard of review and relevant law, then address each contention in turn.

A. Standard of Review and Applicable Law

Free access — add to your briefcase to read the full text and ask questions with AI

Colorado School v. Rocky Mountain, (Colo. Ct. App. 2026).

Colorado School v. Rocky Mountain (Colorado School v. Rocky Mountain) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

I.M.A., Inc. v. Rocky Mountain Airways, Inc.
713 P.2d 882 (Supreme Court of Colorado, 1986)
Mastro v. Brodie
682 P.2d 1162 (Supreme Court of Colorado, 1984)
Crosby v. American Family Mutual Insurance Co.
251 P.3d 1279 (Colorado Court of Appeals, 2010)
Salazar v. American Sterilizer Co.
5 P.3d 357 (Colorado Court of Appeals, 2000)
Salstrom v. Starke
670 P.2d 809 (Colorado Court of Appeals, 1983)
Marquardt v. Perry
200 P.3d 1126 (Colorado Court of Appeals, 2008)
ge Condominium Association, Inc. v. Lo Viento Blanco, LLC
2020 COA 34 (Colorado Court of Appeals, 2020)
Sterenbuch v. Goss
266 P.3d 428 (Colorado Court of Appeals, 2011)