Colorado Iron Works v. Taylor

12 Colo. App. 451
CourtColorado Court of Appeals
DecidedJanuary 15, 1899
DocketNo. 1515
StatusPublished

This text of 12 Colo. App. 451 (Colorado Iron Works v. Taylor) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Colorado Iron Works v. Taylor, 12 Colo. App. 451 (Colo. Ct. App. 1899).

Opinion

Wilson, J.

This is an action in which the appellant seeks to enforce a mechanic’s lien for work and labor done upon and materials furnished for the erection of certain mill improvements upon certain mining claims and a mill site owned by the appellees. In order to a proper understanding of the issues, a somewhat lengthy statement of the facts is required. About August 21, 1894, appellees entered into a contract in writing with one W. A. Clark for the sale of the property in controversy for the sum of $65,000, to be paid at certain specified periods. The contract was in the first instance in the nature of a grant of an option to purchase but by its terms became operative, when the first payment should be made, as an absolute contract of sale. One provision of this contract was that at the time of the second payrnent on the purchase price, “ ten thousand dollars additional shall be paid or secured to be paid to the purchasing company, which ten thousand dollars shall be expended in the erection of ten additional stamps to the mill, and the construction of a tramway from the river to the mill, and the balance of said ten thousand dollars shall be set apart as a working capital to be used in the development and operation of the property.” It was also provided in this contract that after Clark or his assigns had paid the sum of $20,000 on the purchase money, and after the further sum of $10,000 had been paid or secured to be paid as provided above, a lease in addition to the contract of sale was to be executed and delivered to the said Clark or his assigns. It was also further agreed that Mr. Robert Billings, or such other person as might be mutually agreed upon between the parties, should act as reponsible manager of the mines and mill. Clark assigned a one-half interest in this contract to Billings, and failing to comply with his contract, Billings elected to proceed thereunder alone. In pursuance of this, on October 2, 1894, a second contract was entered into be[453]*453tween the appellees and Billings, which was declared, however, by its terms to he only supplemental to and in explanation of the first contract. This last contract provides for the sale of the property to Billings for the same sum as was specified in the Clark contract, to be paid in specified amounts at certain periods, and further provided that moneys expended by said Billings “ in the erection of ten stamps or other improvements upon the mill prior to the expiration of sixty days from this date, shall he computed as part of the ten thousand dollars to he paid or secured within that time for the purposes aforesaid, hut in lieu of the ten stamps, equivalent machinery for reduction may he erected.” On the same day, appellees executed a deed conveying all of the property to said Billings, which was placed in escrow under an escrow agreement which provided among other things that “the said Billings shall within said time (sixty days) pay or cause to be secured to the person or company purchasing said property, the further sum of ten thousand dollars, to be applied to the erection of ten additional stamps, or their equivalent, in said mill. * * * Provided, however, that moneys expended within said sixty days in such additional machinery to said mill, shall he taken and computed .to he a part of said sum of ten thousand dollars.” The escrow agreement also provided that “in case of failure to pay or deposit the sum of fifteen thousand dollars within sixty days from this date, or to pay or secure the further sum of ten thousand dollars hi manner aforesaid within said time, the said deed shall on demand be surrendered to said Taylor and Leonard.” Under these, contracts, Billings paid appellees within the proper time $5,000. Afterwards, he assigned the contracts to the Allegheny Gold Mining and Milling Company, which paid appellees the further sum of $15,000, making the completed $20,000 payment, and on or about November 15, 1894, appellees in pursuance of their agreements delivered the possession of the premises to the said Allegheny company, assignee of said Billings. On this same date, being within sixty days from the date of the last agreement with Billings [454]*454above mentioned, the Allegheny company entered into a contract with appellant to erect the additional stamps and make the additional improvements upon the mill, in pursuance, as it was claimed, of the contracts above mentioned. The contract was completed by appellant, and within the statutory time it filed a statement of claim of lien. The notice of intention to claim the lien as required by subdivision 4 of section 8 of the mechanic’s lien act, Laws of 1893, was entitled as follows : “ Notice of Intention to file statement of Mechanics Lien claim. The Allegheny Mining and Milling Company, et al. owner. Colorado Iron Works, claimant.

“ To The Allegheny Gold Mining and Milling Company, W. A. Taylor, and John Leonard, and Robert Billings, owners of the following described lots or parcels of land situate in the county of San Miguel.” Here followed a description of the property which it was sought to charge with the lien, and then concluded: “You are hereby notified of our intention to file a statement of mechanic’s lien upon the above described property, on account of work done, and mill machinery and other material furnished at the request of The Allegheny Gold Mining and Milling Company, of the value of 14,472.10 ( dollars of which has been paid,) for the construction of the structure, building and improvement now situate upon said premises.” This was signed by appellant. More than twenty-four hours before the filing of the lien statement, this notice was personally served upon H. A. McIntyre, secretary and treasurer of the Allegheny Gold Mining and Milling Company, and upon Robert Billings. It was not served upon appellees, or either of them. Upon trial, the court fpund that the contracts considered as a whole constituted a contract or agreement of sale; that by their terms the appellees authorized and required the erection of the improvements which were made upon the property, and that the interest of the appellees would be bound, provided that the provisions of the lien act had been complied with. It further found, however, that this notice of intention to claim a lien was [455]*455defective and insufficient, and that by reason of this, together with the failure to serve notice upon appellees, their interest in the property could not be charged with the lien. A decree was entered accordingly, and from this an appeal is had to this court.

Appellees have assigned no cross-error, and having made no objection, nor taken exception to any of the findings of the court, it will be seen that the sole question before us for determination is the finding of the court that a lien could not attach to the interest of the appellees because of some material defect in or want of service upon them of the notice of intention to claim a lien. In this view of the case, it is unnecessary for us to discuss or advert to the other findings of the court, except so far as they bear upon the determination of the precise question at issue. We simply content ourselves with stating that such other findings of fact by the court and its conclusions of law thereupon, were correct. Although the legal title to the property still remained in appellees, the improvements and work and labor for which the lien was sought were done and made under a contract of sale of the property, by the terms of which the improvements were expressly authorized and required. The findings of the court, and conclusion of law thereon, to the effect that the interest of appellees in the property was subject to a lien for the improvements in question were correct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moore v. Jackson
49 Cal. 109 (California Supreme Court, 1874)
Davis v. Humphrey
112 Mass. 309 (Massachusetts Supreme Judicial Court, 1873)
Shapleigh v. Hull
21 Colo. 419 (Supreme Court of Colorado, 1895)
G. B. Shaw & Co. v. Bryan
39 Mo. App. 523 (Missouri Court of Appeals, 1890)
O'Leary v. Roe
45 Mo. App. 567 (Missouri Court of Appeals, 1891)
Bohn Manufacturing Co. v. Kountze
12 L.R.A. 33 (Nebraska Supreme Court, 1890)
Henderson v. Connelly
123 Ill. 98 (Illinois Supreme Court, 1887)
Paulsen v. Manske
18 N.E. 275 (Illinois Supreme Court, 1888)
Hill v. Gill
42 N.W. 294 (Supreme Court of Minnesota, 1889)

Cite This Page — Counsel Stack

Bluebook (online)
12 Colo. App. 451, Counsel Stack Legal Research, https://law.counselstack.com/opinion/colorado-iron-works-v-taylor-coloctapp-1899.