Colonna's Shipyard, Inc. v. United States

United States Court of Federal Claims·Decided January 24, 2020·No. 19-1376·Published

Opinion

In the United States Court of Federal Claims No. 19-1376C

(E-Filed: January 24, 2020)1

) COLONNA’S SHIPYARD, INC., ) ) Plaintiff, ) Motion to Transfer; 41 U.S.C. § 7107(d) ) (2012). v. ) ) THE UNITED STATES, ) ) Defendant. ) )

Travis Pittman, Washington, DC, for plaintiff.

John M. McAdams III, Trial Attorney, with whom were Joseph H. Hunt, Assistant Attorney General, Robert E. Kirschman, Jr., Director, Steven J. Gillingham, Assistant Director, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, for defendant. David D. Bach, United States Navy, of counsel.

OPINION

CAMPBELL-SMITH, Judge.

On November 7, 2019, defendant filed a motion to “transfer this case to the Armed Services Board of Contract Appeals (ASBCA or Board) for consolidation with Colonna’s

1 This opinion was issued under seal on January 9, 2020. The parties were invited to identify source selection, proprietary, or confidential material subject to deletion on the basis that the material was protected/privileged. No redactions were proposed by the parties. Thus, the sealed and public versions of this opinion are identical, except for the publication date and this footnote. case number 61635, currently pending before the Board.”2 ECF No. 12 at 4. Plaintiff filed a response in opposition to the motion to transfer, ECF No. 19; and defendant filed a reply in support of the motion, ECF No. 27. For the following reasons, defendant’s motion is GRANTED in part, as to the request for transfer, and DENIED in part, as to the request for consolidation, as the court is without authority to direct proceedings before the ASBCA.

I. Background

On July 19, 2017, the United States Navy awarded plaintiff contract number N50054-17-C-007 for maintenance, inspection, and repair work on the United States Naval Ship (USNS) Narragansett. See ECF No. 12 at 5 (citing ECF No. 1-5 at 1). The contract was firm fixed-price for the amount of $7,620,005, and work was initially scheduled to be completed by January 26, 2018.3 See ECF No. 12 at 5. Performance extended beyond the anticipated time, however, and on April 27, 2018, while still performing under the contract, plaintiff made a request for equitable adjustment (REA) from the Navy in an amount of more than $6 million. See id. The Navy did not make plaintiff’s requested adjustment, and plaintiff filed a notice of appeal with the ASBCA on May 29, 2018, see id. at 18, and the appeal complaint was filed on July 31, 2018, see id. at 81. That appeal was docketed as ASBCA case number 61635.4 See id. In the appeal, plaintiff alleged breach of contract and changes to the contract, and summarized plaintiff’s request for relief in a chart itemizing the cost of each alleged breach or change. See id. at 80, 120-22.

2 Defendant embedded in its motion to transfer a request to stay this case pending a decision on the motion to transfer. See ECF No. 12 at 5, 15. Defendant is advised that for purposes of proper case management and docket clarity compound motions are generally not permitted. In this instance, however, any request to stay proceedings is rendered moot by the issuance of this opinion. 3 The January 26, 2018 date cited here is taken from defendant’s motion for transfer, but the court notes that the complaint plaintiff filed before the ASBCA states that the contract work was initially due to be completed by December 15, 2017. See ECF No. 12 at 19. The court does not have sufficient documentation to determine which date is correct, but making such a determination is not relevant to the present analysis. 4 On August 5, 2019, plaintiff filed a second certified claim related to this contract with the contracting officer, see ECF No. 12 at 90-123, and later appealed the contracting officer’s “deemed denial” to the ASBCA, see id. at 88-89. That appeal, which was docketed as ASBCA case number 62212, has been consolidated with plaintiff’s appeal of the denial of its initial REA, under case number 61635. See id. at 124 (ASBCA consolidation order). 2 Following completion of the contract work on August 3, 2018, the Navy issued a negative Contractor’s Performance Assessment Report (CPAR) evaluation on February 14, 2019, see ECF No. 1-3, which was reviewed and affirmed on March 14, 2019, see ECF No. 1-5. Plaintiff filed a certified claim, pursuant to the Contract Disputes Act of 1978, 41 U.S.C. § 7101 (2012) (CDA), with the contracting officer seeking correction of the negative CPAR on April 5, 2019. See ECF No. 1 at 2. On August 22, 2019, the contracting officer issued a final decision affirming the findings in the CPAR. See ECF No. 1-6 at 1. Shortly thereafter, on September 10, 2019, plaintiff filed its complaint with this court challenging the “highly negative” evaluation. See ECF No. 1 at 1-2.

II. Legal Standards

Pursuant to the CDA, the court has the authority to direct consolidation or transfer of a case under the following circumstances:

If 2 or more actions arising from one contract are filed in the United States Court of Federal Claims and one or more agency boards, for the convenience of parties or witnesses or in the interest of justice, the United States Court of Federal Claims may order the consolidation of the actions in that court or transfer any actions to or among the agency boards involved.

41 U.S.C. § 7107(d) (2012). The decision to consolidate or transfer a case “is a discretionary action that embraces a variety of factors, and is an ad hoc determination.” Multi-Roof Sys. Co. v. United States, 5 Cl. Ct. 245, 247 (1984). See also Joseph Morton Co. v. United States, 757 F.2d 1273, 1280 (Fed. Cir. 1985) (noting the court’s “broad discretion in exercising its power to consolidate” matters pursuant to the CDA). In assessing whether consolidation or transfer is appropriate under this statute, the court considers several factors, including:

(1) whether the same contract is involved; (2) whether the cases present the same or overlapping issues; (3) whether the Plaintiff chose to proceed initially in the board or at the court; (4) whether substantial efforts have been expended in one forum, but not the other; and (5) whether transfer will eliminate duplication of efforts.

Precision Pine & Timber, Inc. v. United States, 45 Fed. Cl. 134, 135-36 (1999).5 See also In re Morse Diesel Int’l, 163 F. App’x 878, 879 (Fed. Cir. 2006) (upholding a decision by

5 In listing the factors considered by the court to determine whether transfer is appropriate, plaintiff cites Northrop Grumman Corp. v. United States, 70 Fed. Cl. 230, 231 (2006). See ECF No. 19 at 2. In Northrop, the court lists six factors, rather than five. See Northrop, 70 Fed. Cl. at 231 (including a separate factor addressing “whether concurrent resolution would result in an 3 this court based on this framework for determining whether consolidation or transfer is appropriate).

III. Analysis

In its motion to transfer, defendant argues that the factors enumerated above militate in favor of transferring this case to the ASBCA for consolidation with ASBCA case number 61635. See ECF No. 12 at 10-15. Plaintiff opposes the motion, and claims that “the standard factors weighing in favor of consolidation are not present in this case,” ECF No. 19 at 1, and separately argues that the court should deny transfer in the interest of justice, see id. at 7.

Free access — add to your briefcase to read the full text and ask questions with AI

Colonna's Shipyard, Inc. v. United States, (uscfc 2020).

Colonna's Shipyard, Inc. v. United States (Colonna's Shipyard, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Precision Pine & Timber, Inc. v. United States
45 Fed. Cl. 134 (Federal Claims, 1999)
Northrop Grumman Corp. v. United States
70 Fed. Cl. 230 (Federal Claims, 2006)
Multi-Roof Systems Co. v. United States
32 Cont. Cas. Fed. 72,530 (Court of Claims, 1984)
In re Morse Diesel International, Inc.
163 Fed. Appx. 878 (Federal Circuit, 2006)