Colonna v. State

224 A.D. 173, 230 N.Y.S. 19, 1928 N.Y. App. Div. LEXIS 9957
Appellate Division of the Supreme Court of the State of New York·Decided June 29, 1928·Published·Cited by 2 cases

Opinion

Hubbs, P. J.

The claimant in this action owned a stone quarry at Albion, N. Y., and the premises upon which it was situated, consisting of five acres of land. On September 2, 1919, he executed a lease of the quarry to a copartnership known as Colonna & Co. The lease commenced on September 2, 1919, and was to run to September 2, 1924, and was stated to be for the purpose of quarrying, producing, breaking and dressing stone. Colonna & Co. agreed to pay as rental eight per cent of the market value of all stone produced, said rental to be due and payable as soon as the stone was produced and measured. The claimant, as lessor, was given the right to determine in what portion of the quarry the operations were to be carried on.

On September 4, 1919, the copartnership began to operate the quarry. At that time the quarry was full of water. Adjoining the land upon which the quarry was located was the Barge canal. The quarry had not been pumped out prior to the formation of the partnership, i. e., the date of the execution of the lease, since early in the preceding year. In the spring of 1919 the level of the Barge canal had been raised. After the partnership began operations and had pumped the water down from seven to nine feet, it was found that water was coming into the quarry from the canal. The partnership continued to pump until most of the [175] water had been removed, but it was found impossible to dry the floor of the quarry sufficiently so that stone could be quarried from the pit or quarry floor. It continued to pump at intervals from then until December sixth, when quarrying operations were discontinued for the season. Upon discovering that the bed of the quarry was wet and could not be worked to advantage, the partnership began stripping the easterly side of the quarry at the surface and confined its quarrying operations to such stone as could be removed from that portion. The Court of Claims found that the leakage from the canal was caused by the negligence of the State.

In the case of Colonna v. State of New York (224 App. Div.-), which action was tried with the present action, this court has determined that the claimant copartnership used reasonable efforts to remove the water from the quarry and that on account of the leakage from the Barge canal it is entitled to recover the difference between what it would have cost to pump out the quarry had it not been for the leakage from the Barge canal and what it expended in attempting to keep the water out of the quarry, that difference being $1,427.13, and that it is entitled to recover also the difference between what it would have received on the sale of paving blocks and curbing from said quarry if there had been no leakage and what it actually received for the same classes of material produced from said quarry during said period, less expenses which would have been paid in producing such additional materials and less the eight per cent royalty due Frank Colonna, making the net loss resulting from their inability to quarry in the pit or bottom of the quarry the sum of $5,109.50.

The claimant here seeks to recover eight per cent upon the difference between what would have been produced had it not been for the leak and what was actually produced, which amount of $488 he claims to be loss of royalties or rental under the lease. The Court of Claims has found that the agreement between the claimant and Colonna & Co. does not give to the claimant any right of action against the State for damages which he suffered by reason of the inability of Colonna & Co. to operate his quarry because of leakage from the canal, and his claim was dismissed upon the merits. The State contends on thi.3 appeal and the Court of Claims has found that claimant cannot recover because his claim is based upon a contract which did not guarantee to claimant any specific sum and, therefore, it does not give to him any right of action against the State by reason of the inability of Colonna & Co. to operate the quarry. The State also contends that as Colonna owned the quarry and the stone therein and the [176] stone was not removed, he cannot recover because he still has the stone left and the value of the stone was not proved.

, This court decided, contrary to the decision of the Court of Claims, that the claimant Colonna & Co. established by a preponderance of the evidence that it could have produced the quantity of stone which it set forth in its claim it could have produced, and that it is entitled to damages based upon loss of profits. It would seem to follow that the claimant here should recover, unless prevented for the reasons urged by the respondent. Even assuming, but not deciding, that the agreement between the claimant and Colonna & Co. was unilateral, still I think the claimant is not prevented from recovering. While the contract did not guarantee to the claimant any specific sum, the parties to the contract or lease conducted their operations under it and, under the facts in this case, a third party is not entitled to take advantage of the fact that the contract was unilateral in nature to escape liability for damage resulting from its negligent act. (13 C. J. 333; Rice v. Manley, 66 N. Y. 82; Laskey Feature Play Co., Inc., v. Fox V. Co., 93 Misc. 364; affd., 174 App. Div. 872.) In the amount of damages awarded to the copartnership of Colonna & Co. against the State, the eight per cent royalty payable to the claimant herein was deducted from the claim as allowed. If the amount of such royalty is not allowed to the claimant herein, the effect will be that the State will escape the payment of the full amount of the damage caused by its negligence.

Free access — add to your briefcase to read the full text and ask questions with AI

Colonna v. State, 224 A.D. 173, 230 N.Y.S. 19, 1928 N.Y. App. Div. LEXIS 9957 (N.Y. Ct. App. 1928).

224 A.D. 173 (Colonna v. State) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Wasik v. Keeler Construction Co.
64 A.D.2d 812 (Appellate Division of the Supreme Court of New York, 1978)
Jones Cut Stone Co. v. State
7 Misc. 2d 1048 (New York State Court of Claims, 1957)