COLO. RIVER ENERGY DISTRIBUTORS ASS'N v. Lewis

516 F. Supp. 926
CourtDistrict Court, District of Columbia
DecidedMarch 20, 1981
DocketCiv. A. No. 81-0163
StatusPublished

This text of 516 F. Supp. 926 (COLO. RIVER ENERGY DISTRIBUTORS ASS'N v. Lewis) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
COLO. RIVER ENERGY DISTRIBUTORS ASS'N v. Lewis, 516 F. Supp. 926 (D.D.C. 1981).

Opinion

516 F.Supp. 926 (1981)

COLORADO RIVER ENERGY DISTRIBUTORS ASSOCIATION, A Non-Profit Colorado Membership Corporation,
and
Provo City, Utah, A Political Subdivision of the State of Utah, Plaintiffs,
v.
William LEWIS, As Acting Secretary of the Department of Energy,
and
Ruth M. Davis, As Assistant Secretary of Energy For Resource Applications, Defendants.

Civ. A. No. 81-0163.

United States District Court, District of Columbia.

March 20, 1981.

*927 Donald R. Allen, Glen L. Ortman, David Yafee, Duncan, Allen & Mitchell, Washington, D. C., for plaintiffs.

Barbara S. Woodall, Dept. of Justice, Washington, D. C., for defendants.

OPINION

BARRINGTON D. PARKER, District Judge.

Plaintiffs, Colorado River Energy Distributors Association (CREDA) and Provo City, Utah (Provo) have brought this action against the Secretary of Energy and the Assistant Secretary for Resource Applications seeking a declaratory judgment that defendants do not have the authority to implement and collect, on an interim basis, proposed rate increases for electric power sold by defendants to plaintiff CREDA's members. This case is presently before the *928 Court on plaintiffs' motion for a preliminary injunction enjoining the Department of Energy (DOE) from placing into effect an interim rate increase for electric power from the hydroelectric generating facilities of the Colorado River Storage Project (CRSP). Plaintiffs argue that no proposed rates may take effect unless and until they have first been approved by the Federal Energy Regulatory Commission (FERC). After considering the parties memoranda and oral argument, the Court concludes that the plaintiffs' motion for a preliminary injunction should be denied. The Court's findings of fact and conclusions of law are set out below.

BACKGROUND

CREDA is a non-profit Colorado membership corporation comprised of seventeen publicly-owned electric utility systems, organizations of publicly-owned electric utility systems and state and federal agencies which provide wholesale electric service. CREDA's members are either electric utilities or associations of electric utilities located in the Colorado River Basin states of Arizona, Colorado, Nevada, New Mexico, Utah and Wyoming. Provo is a political subdivision of the State of Utah and a CREDA member. Under the federal reclamation laws those CREDA members and their customers which are electric utilities qualify for preference in the purchase of electric power produced by CRSP hydroelectric facilities. CREDA's members purchase approximately 90 percent of the power produced by CRSP. Defendant William Lewis was named in his official capacity as Acting Secretary of the Department of Energy. The Secretary is responsible for the operation of the DOE, which includes management of the Western Area Power Administration (WAPA), a distinct organizational entity within DOE. Defendant Ruth M. Davis, named in her official capacity as the Assistant Secretary of Energy for Resource Applications, was delegated the responsibility for the formulation, approval and implementation of rates charged for CRSP power marketed by WAPA.[1]

The Western Area Power Administration was created as an agency within the Department of Energy by the Department of Energy Organization Act of 1977, 42 U.S.C. §§ 7101, 7152(a)(3) (DOE Act). WAPA is responsible for the marketing of electric power generated at 47 federal hydroelectric power plants and one coal-fired plant to over 450 power customers in 15 western states. By statute, revenues from the sale of energy generated at hydroelectric plants in the Colorado River Storage Project must be sufficient to pay the Project's annual operating and maintenance expenses, and, in addition, must provide for a return to the Treasury of the costs of each power unit within the project within fifty years. 43 U.S.C. § 620d(d)(1).

The Twenty-First Annual Report of the Colorado River Storage Project, submitted to Congress as required by 43 U.S.C. § 620e, contained a repayment study which showed that the then-existing (1977) power rates would be sufficient to pay annual operating and maintenance expenses, but would not repay the power investment and irrigation assistance costs within the statutory time frames. WAPA tentatively found that a rate increase of forty-three percent was necessary to provide the required revenue, and publicly proposed such an increase at a customer meeting on March 5, 1978.

Following a series of public meetings with customer representatives and the receipt of written comments, WAPA reduced the rate increase to twenty and one-half percent. This increase was approved on an interim basis by the Assistant Secretary for Resource Applications, in accordance with the Delegation Order, on December 23, 1980. The announcement of the interim rates also advised WAPA customers that the new rates would become effective on January 23, 1981, and restated DOE's intention to refund any overcharges with interest. *929 45 Fed.Reg. 86988 (December 28, 1980).

LEGAL ANALYSIS

Until 1977, the Department of the Interior's Bureau of Reclamation managed the CRSP. Power marketing by the Bureau of Reclamation in the Colorado River Basin was governed by the Reclamation Act of 1902, 43 U.S.C. § 372 et seq., the Reclamation Project Act of 1939, 43 U.S.C. § 485 et seq., and the Colorado River Storage Project Act of 1956, 43 U.S.C. § 620 et seq.

Section 9(c) of the Reclamation Project Act of 1939 gave the following authority to set rates to the Secretary of the Interior:

Any sale of electrical power or lease of power privileges, made by the Secretary in connection with the operation of any project or division of a project, shall be for such periods, not to exceed forty years, and at such rates as in his judgment will produce power revenues at least sufficient to cover an appropriate share of the annual operation and maintenance cost, interest on an appropriate share of the construction investment at not less than 3 per centum per annum, and such other fixed charges as the Secretary deems proper ...." 43 U.S.C. § 485h(c).

In 1977 the Bureau of Reclamation's power marketing functions were transferred to the Secretary of Energy, acting through a new power marketing administration under section 302(a)(1) & (3) of the DOE Act. 42 U.S.C. § 7152(a)(1) & (3). The Act established WAPA as the new power marketing administration. The DOE Act did not change the standards set by the Reclamation Project Act of 1939 relating to the marketing of CRSP power under section 9(c).

The DOE Act also granted the Secretary the power to delegate "any of his functions to such officers and employees of the Department as he may designate." 42 U.S.C. § 7252

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New England Divisions Case
261 U.S. 184 (Supreme Court, 1923)
Ashwander v. Tennessee Valley Authority
297 U.S. 288 (Supreme Court, 1936)
Federal Power Commission v. Hope Natural Gas Co.
320 U.S. 591 (Supreme Court, 1944)
United States v. Thayer-West Point Hotel Co.
329 U.S. 585 (Supreme Court, 1947)
Arizona v. California
373 U.S. 546 (Supreme Court, 1963)
United States v. Florida East Coast Railway Co.
410 U.S. 224 (Supreme Court, 1973)
United States v. Louisiana
446 U.S. 253 (Supreme Court, 1980)
G. L. Christian and Associates v. The United States
312 F.2d 418 (Court of Claims, 1963)
Chris Berg, Inc. v. The United States
426 F.2d 314 (Court of Claims, 1970)
Pacific Power & Light Co. v. Duncan
499 F. Supp. 672 (D. Oregon, 1980)
DeMatteo Construction Co. v. United States
600 F.2d 1384 (Court of Claims, 1979)
Colorado River Energy Distributors Ass'n v. Lewis
516 F. Supp. 926 (District of Columbia, 1981)
City of Santa Clara v. Andrus
572 F.2d 660 (Ninth Circuit, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
516 F. Supp. 926, Counsel Stack Legal Research, https://law.counselstack.com/opinion/colo-river-energy-distributors-assn-v-lewis-dcd-1981.