Collins v. Metropolitan Casualty Insurance

176 A. 130, 114 N.J.L. 93, 1935 N.J. LEXIS 182
CourtSupreme Court of New Jersey
DecidedJanuary 10, 1935
StatusPublished

This text of 176 A. 130 (Collins v. Metropolitan Casualty Insurance) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Collins v. Metropolitan Casualty Insurance, 176 A. 130, 114 N.J.L. 93, 1935 N.J. LEXIS 182 (N.J. 1935).

Opinion

The opinion of the court was delivered by

Case, J.

This is an appeal by the defendant insurance company from a judgment entered in the Supreme Court for the plaintiffs and against it in the amount of $8,511.88. The judgment was entered upon the finding of Judge Lawrence, sitting, by consent, without a jury.

The action arises on a claim of Allentown Portland Cement Company for materials furnished on a Monmouth county *94 road under a contract between one Harry 0. Wagner, trading as Camden Paving Company, and the board of chosen freeholders of the county of Monmouth, the defendant company having furnished a bond under chapter 75. Pamph. L. 1918, p. 203. The litigated question is whether the required statement was served upon the bonding company within the statutory period of eighty days following acceptance of the road by the Monmouth county freeholders, and this, in turn, depends upon the fixing of the time when acceptance was had. The road contract and the bond were executed on or about August 8th or 9th, 1929. There was a formal and, in its terms, sufficient resolution of acceptance adopted by the board of freeholders on November 23d, 1932. There is no doubt that if that was, as the court below found, the date of acceptance, the necessary statement was served in season thereafter upon the bonding company and the action in due time begun. However, the bonding company contends that acceptance occurred either on April 23d, 1930, or on June 5th, 1931. If this contention is sound, the statement was not served in season.

The time of acceptance of the work under municipal contracts is of vital importance because upon it depends the sufficiency of the several steps necessary to be taken by subcontractors, materialmen or laborers entitled to recover on the contractor’s bond under the statute cited, supra. It is unfortunate if the essentials of acceptance are so loosely defined as to leave the defendant bondsman fairly in doubt, when sued upon the bond, whether to rely upon the events of a given day or of another day more than a year later as constituting the acceptance. For if an obligee, when put to its defense, is thus confused, what of those whom the legislature sought to protect by requiring the bond? They must, at their peril, determine when the facts of the case constitute an acceptance under the statute and govern their several steps in chronological accord therewith. To them an acceptance by the contracting public agency is necessary, and time — the furnishing of a statement within eighty days after acceptance and institution of suit within one year after acceptance *95 but not less than sixty days after the furnishing of the statement — is of the essence. Franklin Lumber Co. v. Globe Indemnity Co., 102 N. J. L. 9; Commonwealth Quarry Co. v. Metropolitan, &c., Co., 108 Id. 518; John P. Callaghan, Inc., v. Continental Casualty Co., 110 Id. 390. An apt illustration of the difficulty sometimes incident to that decision is before us in the present case. Plaintiffs instituted an earlier suit on the same cause on April 20th, 1931, alleging that the acceptance was on April 23d, 1930, to which the defendant answered that the transactions of that day did not constitute an acceptance, whereupon plaintiffs, believing that the defense was well grounded, discontinued that action, caused a resolution of formal acceptance to be passed by the board and brought the instant suit.

The explanation of the appellant’s alternative argument is that it seeks to find the acceptance, not in a formal action of the freeholders resolving to accept, but as a conclusion from other acts that are said to have occurred. The contract provided:

“Upon the completion of the work, the Engineer shall certify to the Board of Chosen Freeholders, in writing, as to the completion of the work and shall further certify as to the entire amount and value of each class of work performed.

“The Board of Chosen Freeholders, upon receipt of such certificate, shall certify the aforesaid certificate and estimate to the County Treasurer for payment of the amount unpaid and due, which amount shall be ninety-five per cent. (95%) of the entire cost of the work less previous payments and any other proper deductions as herein provided.

“At the time of acceptance the whole work must have been finished in a neat and workmanlike manner and must be in that condition at that date. Defects arising from any cause or at any time before acceptance must be made good and the whole work put in the condition as herein specified before acceptance.

“The remainder, or five (5) per cent, will bo retained for a period of one (1) year by the county of Monmouth as further security for the faithful performance of article 37, page 10, and will be paid on certificate of the Engineer.”

*96 Appellant asserts that the incidents thus anticipated, namely, the certification and the payment of ninety-five per centum, actually happened on April 23d, 1930, and that there was consequently, as a fact, an acceptance within the intent of the contract on that day; and that the remainder of the contract price was paid on June 5th, 1931, which, as it says, constitutes an acceptance if there had not been an earlier acceptance.

For the purposes of the argument we may assume that the contract anticipated an acceptance of the work as an incident to the engineer’s written certification of completion and the payment of all of the contract price except the retained five per centum. Whether an -acceptance is to be conclusively presumed from such happenings, without more, we need not determine. It is apparent that if it were proper to draw that conclusion as a matter of law, the facts upon which the conclusion should rest would need to be clearly in proof. Such clarity of proof is not before us and was not before the trial judge.

Defendant placed in evidence an exhibit marked D-l which consisted of an order for additional work in the amount of $446.71, an order for work reduction in the amount of $442.10 an engineer’s final estimate in the amount of $6,664.89, the contractor’s receipt in that figure and a payment voucher dated April 23d, 1930, in like amount. The extra work order, the receipt and the voucher by their terms, and the estimate by inference, were made to relate to the road covered by the contract in question, namely, Farmingdale-Belmar road No. 32, section 2.. Along with and as a development of that proof defendant introduced in evidence the minutes of the board of chosen freeholders for April 23d, 1930. It was then thought that the minutes related to the mentioned road contract. It now appears that they do not. By their content they refer to “Farmingdale-Belmar road No. 36, section 2,” which appellant’s brief now conceives to be a different road section covered by another contract with the same contractor. The minutes, now considered by appellant to be irrelevant, read as folltfws:

*97 “County Engineer Allen also reported the expiration of maintenance on Belmar-Earmingdale Eoad No.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
176 A. 130, 114 N.J.L. 93, 1935 N.J. LEXIS 182, Counsel Stack Legal Research, https://law.counselstack.com/opinion/collins-v-metropolitan-casualty-insurance-nj-1935.