Coleman v. North Kansas City Electric Company

298 S.W.2d 362, 1957 Mo. LEXIS 581
CourtSupreme Court of Missouri
DecidedJanuary 14, 1957
Docket44673
StatusPublished
Cited by13 cases

This text of 298 S.W.2d 362 (Coleman v. North Kansas City Electric Company) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coleman v. North Kansas City Electric Company, 298 S.W.2d 362, 1957 Mo. LEXIS 581 (Mo. 1957).

Opinion

LEEDY, Judge.

Action for damages for personal injuries arising out of a casualty which occurred while the plaintiff, Grant Coleman, was in the employ of defendant corporation, North Kansas City Electric Company, which injuries were allegedly sustained as the result of the negligence of the employer. Coleman had rejected the Workmen’s Compensation Act, Chapter 287, RSMo and V.A.M.S. Upon a trial in the Clay Circuit Court of this, his common law action, verdict and judgment went in his favor in the sum of $65,000, and defendant-employer appealed.

Plaintiff is an electrician, and at the time he was injured was 35 years of age. Defendant is a corporation engaged in the business of electrical repair and installation work. It is owned in large part and operated by members of plaintiff’s wife’s family, her father and brother having been in the active management of the company at the time of the accident. One of its principal customers or retainers is the Staley Milling Company, a large concern located in North Kansas City. Plaintiff was injured while doing electrical work in and upon a substation at one of the Staley mills. He submitted his case under instructions which *363 hypothesized negligence on the part of defendant in failing to warn him of the danger of the electricity, and in failing to cut off the electricity, or have the same cut off while plaintiff was working. Defendant contends that the evidence fails to show any actionable negligence on its part, but, if it does, then under the evidence plaintiff was guilty of contributory negligence as a matter of law, and further that he assumed the risk of injury from the electricity as a matter of law, as alleged in its answer.

The outdoor substation in which plaintiff was working at the time in question is a fenced enclosure approximately 25x30 feet with the long way north and south. Within this enclosure is a tall superstructure or steel frame (exact dimensions not shown) which supports the 13,200 volt primary lines or conductors overhead and appurtenances connected with such an installation. Beneath the steel frame were two concrete platforms (both running east and west), and on one of these were three hooked-up or alive and functioning transformers (hereinafter referred to as the old transformers); on the other platform were three new transformers which had not yet been energized or connected. The old transformers were about 8 feet from the north end of the enclosure, and the platform on which they rested was 15-18 inches above the level of the ground. The east transformer on this platform was 4-5 feet from the east fence, and the west transformer was 1½-2 feet from the fence on the west. The height of these old transformers, including platform, was 6-7 feet. They were hooked up on both their primary and secondary sides, the primary or high voltage line in each instance being connected to the south side, and the secondaries connected on the north side of the old transformers.

The new transformers, resting on the second concrete platform, were —4 feet south of,' and parallel to, the bank of the three old transformers above mentioned. Their height was 6½-7 feet from the floor of the platform, which was itself 4-6 inches above ground level. The diameter of the new transformers was 2-2½ feet at the top, and they were 12-15 inches higher than the old ones, and about 6 inches greater in diameter. Each of the old transformers had a primary line of 13,200 volts coming into it. A primary line was connected to the east old transformer on its south side, the line going out of the top of the transformer, and ran somewhat to the south under the south edge of a catwalk on top of the old transformers at about a 45 degree angle, then fastened to a knife switch which was mounted on a cross member at a 45 degree angle, and from the knife switch, which was on an insulator, fed straight up to the top of the station, or straight toward the top of the station. The knife switch was about 4 feet above the level of the new transformers, at their north edge, and somewhere near the middle of the distance between the east and middle transformers. The primary line ran almost straight up, as stated. It was about 1-1 ½ feet north of the north edge of the new east transformer, and approximately on a line with the west edge of said transformer.

Before going to the job on which he was injured, plaintiff and another electrician, John Lingo, had been working together on an electrical construction job for defendant at the Jones and Laughlin plant in Kansas City, Kansas, which had shut down because of a strike by some other craft. On the day before the accident they had reported back to defendant’s shop for assignment to other work, and were directed to go to the Staley mill, where they reported to Jake Flanary, an employee and general foreman of defendant who was in charge of all electrical work at the two Staley mills. Flanary was also the steward for the Local Union to which plaintiff belonged, and he and plaintiff carried precisely the same Union classification card. They arrived at the plant about 10 o’clock A.M., and Flanary got the key to the substation, took the two workmen inside and outlined *364 to them the work to be done. Flanary remained about 10 or 15 minutes. Among other work thus directed was that of making up and installing copper bus bars on the secondary side of the new transformers and connecting them to each other, but not with the current, and also the stringing of a delta bar or cable between the two sides of the substation. He did not tell them what to use or how to use it, but left it strictly up to them to select and procure the equipment needed. The necessary materials were not at the substation but were at the shop of the nearby No. 2 Staley mill, to which place Lingo and plaintiff went and obtained the materials, as well as two ladders. They worked in and about the substation (in making up and installing the copper bus bars for the new transformers) 'during the remainder of the first day and until the afternoon of the next, without incident.

At the time of the casualty plaintiff and Lingo were engaged in installing the delta bar or cable which was to be attached to the frame of the substation at the east and west sides thereof, 12 or 14 feet above the surface of the ground, and 7-7½ feet south of the nearest primary line. Holes were bored in the steel frame on both the east and west sides, the cable cut and insulators put on both ends. Fastening was to be accomplished by means of putting eye bolts through the holes with nut fasteners on the other side. They fastened the cable to the east part of the frame first, and then the west, when it was discovered that the eye bolts did not have sufficient threads to permit the slack in the cable to be taken out by tightening the bolts. Flanary had directed that the delta bar or cable be tight and neat looking. The two workmen then decided to remove the slack by the use of a block and tackle, which they obtained at the shop at the No. 2 mill. Returning to the substation with the block and tackle, they fastened one end to one side of the steel framework and the other to the free end of the delta bar. In an effort to tighten the delta bar they pulled on the rope in the block and taclde from the ground, standing in the open area south of the new transformers under the delta bar or cable and somewhat to the east of the west insulator on the delta bar. From this position the rope was not long enough to permit pulling from a point on the ground much farther to the east.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tellis v. Union Electric Co.
536 S.W.2d 742 (Missouri Court of Appeals, 1976)
Redman v. Earle M. Jorgenson Co.
491 S.W.2d 304 (Supreme Court of Missouri, 1973)
Lynch v. Hill
443 S.W.2d 812 (Supreme Court of Missouri, 1969)
Helming v. Dulle
441 S.W.2d 350 (Supreme Court of Missouri, 1969)
Bridges Ex Rel. Bridges v. Arkansas-Missouri Power Co.
410 S.W.2d 106 (Missouri Court of Appeals, 1966)
Taylor v. Hitt
342 S.W.2d 489 (Missouri Court of Appeals, 1961)
Marks v. Bettendorf's, Inc.
337 S.W.2d 585 (Missouri Court of Appeals, 1960)
Arkansas-Missouri Power Company v. Ray B. Carl
280 F.2d 7 (Eighth Circuit, 1960)
Potter Ex Rel. Potter v. Sac-Osage Electric Cooperative, Inc.
335 S.W.2d 192 (Supreme Court of Missouri, 1960)
Losh v. Ozark Border Electric Cooperative
330 S.W.2d 847 (Supreme Court of Missouri, 1960)
Giambelluca v. Missouri Pacific Railroad Company
320 S.W.2d 457 (Supreme Court of Missouri, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
298 S.W.2d 362, 1957 Mo. LEXIS 581, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coleman-v-north-kansas-city-electric-company-mo-1957.