Coleman v. Louisiana Power & Light Co.

535 So. 2d 955, 1988 La. App. LEXIS 1881, 1988 WL 97260
CourtLouisiana Court of Appeal
DecidedSeptember 21, 1988
DocketNo. 19929-CA
StatusPublished
Cited by1 cases

This text of 535 So. 2d 955 (Coleman v. Louisiana Power & Light Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coleman v. Louisiana Power & Light Co., 535 So. 2d 955, 1988 La. App. LEXIS 1881, 1988 WL 97260 (La. Ct. App. 1988).

Opinion

LINDSAY, Judge.

The plaintiff, Alvin B. Coleman, appealed from a judgment rejecting his claims against Louisiana Power and Light Company (hereinafter referred to as “LP & L”). The plaintiff sought damages for the injuries he sustained when the crane upon which he was leaning became electrified by contact with the defendant’s electric utility lines. The jury found the defendant free of fault. For the following reasons, we affirm the judgment of the trial court.

FACTS

In May of 1983, a severe storm caused substantial damage in Caldwell Parish and the surrounding area. Of 800 miles of electrical line, about 600 miles were knocked down. At one point, all 11,000 of LP & L’s customers were without electricity. Approximately 700 new poles had to be installed in order to restore electrical service to the community. LP & L had insufficient personnel to repair the enormous [956]*956amount of damage, and about 260 to 270 workers were called in from other areas to assist in the restoration of power in the storm-damaged locality.

An electrical power pole on Louisiana Highway 849 was one of the numerous poles knocked down by the storm. The pole was originally located about forty-one feet from the center line of the highway. Due to standing water and debris, the LP & L workers were unable to place the new pole (hereinafter referred to as the “temporary pole”) in the same spot as the original pole. The temporary pole was placed about twenty-four feet from the center line of the highway, or seventeen feet closer to the road than the original pole. It was located approximately thirteen to fourteen feet from the edge of the two-lane rural road. Its placement put the pole out of line with the other poles running along this stretch of road.

In its new position, the temporary pole was located off of LP & L’s right-of-way and on the state’s highway right-of-way. No permit was obtained to place the temporary pole on the state’s highway right-of-way.

In September, 1983, the Department of Transportation and Development rebuilt a bridge on Louisiana Highway 849 in the vicinity of the temporary pole. The plaintiff, a highway department employee who generally worked with a dirt crew as a heavy equipment operator, was temporarily assigned to the bridge reconstruction crew. His job on this project was to operate a combination backhoe-loader to “dig out headwalls”.

On September 26, 1983, the work on the bridge was completed, and the two-lane road leading to it was scheduled to be reopened that afternoon. The crew was in the process of moving timber which was lying on the road right-of-way. To facilitate this work, the crew utilized a motor crane mounted on a truck. This truck-mounted crane was on the roadway. The crane’s boom was sixty feet long. Forrest Moore, the foreman of the road reconstruction crew, testified that all the debris which was moved was picked up and swung away from the power lines.

The plaintiff’s backhoe had broken down and was awaiting repair. After spending the morning sitting idly in his truck, the plaintiff decided to assist his fellow workers with the clearing of debris. The plaintiff began unhooking the crane cable from the debris and pieces of timber after their removal from a cleared area. At one point, he was relieved by another worker and went back up the incline to get a drink of water. Apparently, while resting, he leaned on the front bumper of the truck upon which the crane was mounted.

At about the same time, the hook of the crane cable became entangled in some vines, creating tension on the cable and boom. When the cable came loose, it swung all the way across the road. It then came into contact with the uninsulated highline of the temporary pole which was on the opposite side of the road. Witnesses reported seeing a small blue “arc” as contact was made. An electrical charge surged through the cable into the boom, the truck and then through the plaintiff’s body. The plaintiff suffered severe burns on his arm and on the soles of both of his feet.

Subsequently, the plaintiff filed suit against LP & L, claiming its negligent placement of the temporary pole created a hazard to routine highway maintenance operations and thus caused his injuries. The defendant answered, claiming comparative negligence on the part of the plaintiff, who put himself in contact with the vehicle while the crane was operational.

A petition of intervention was filed by the plaintiff’s employer to recover the worker’s compensation benefits and medical expenses it had expended as a result of the plaintiff’s injuries.

A jury trial on the merits began on January 29, 1986. At the conclusion of the trial on February 4, 1986, the jury returned a verdict finding the defendant free of negligence. A judgment reflecting the verdict was signed on March 10, 1986.

On March 19, 1986, the plaintiff filed a motion for judgment notwithstanding the [957]*957verdict, or, in the alternative, for a new trial. By written reasons dated January 30, 1987, the trial court denied the motion. A judgment in conformity with the ruling was signed February 19, 1987.

The plaintiff filed a devolutive appeal. The plaintiff argues that the jury verdict was clearly erroneous in finding LP & L free from negligence in connection with the plaintiffs accident and resulting injuries. The plaintiff further argues the extent of his injuries, and the issue of his alleged comparative negligence. Because we find the first issue concerning LP & L’s liability to be dispositive of this case, we do not consider these additional issues.

LIABILITY OF LP & L

The plaintiff argues that the jury was clearly wrong in its determination that LP & L was not negligent. He contends that LP & L was negligent in leaving the temporary pole on the highway right-of-way for several months after the storm. The plaintiff further argues that the placement of the temporary pole constituted a hazard, and that it was foreseeable that someone would have to remove the fallen timber in the area.

The plaintiff presented the testimony of several witnesses to the accident who stated that the hook on the end of the cable, or the cable near the hook, struck the highline near the temporary pole. However, none of these witnesses (Forrest Moore, Cecil Chaudoin, and Huey Little) testified as to the angle of the boom, or the length of the cable at the time of the accident. Additionally, no evidence was presented as to the force with which the cable struck the utility wires.

The plaintiff and LP & L each presented the testimony of an expert in electrical engineering. Both experts agree that the temporary pole greatly exceeded the minimum requirements specified in the National Electric Safety Code (NESC). The NESC required that the pole be installed at least six inches from the pavement and the wires be at least 18 to 20 feet high. The temporary pole was approximately 13 feet away from the edge of the road and its highline was about 31 feet high.

Ricky Louis Nowlin, the plaintiff’s expert, testified that the location of the temporary pole created a hazard and compromised the NESC requirements. He stated that the temporary pole was left too close to the road for too long a period of time following the emergency caused by the storm. However, he agreed that installations should be undertaken in accordance with good, safe engineering practices under the existing local conditions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coleman v. Louisiana Power & Light Co.
536 So. 2d 1202 (Supreme Court of Louisiana, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
535 So. 2d 955, 1988 La. App. LEXIS 1881, 1988 WL 97260, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coleman-v-louisiana-power-light-co-lactapp-1988.