Coleman v. Korrect Plumbing, Inc., Unpublished Decision (3-24-2006)

2006 Ohio 1579
CourtOhio Court of Appeals
DecidedMarch 24, 2006
DocketC.A. No. 21355.
StatusUnpublished
Cited by2 cases

This text of 2006 Ohio 1579 (Coleman v. Korrect Plumbing, Inc., Unpublished Decision (3-24-2006)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coleman v. Korrect Plumbing, Inc., Unpublished Decision (3-24-2006), 2006 Ohio 1579 (Ohio Ct. App. 2006).

Opinion

OPINION
{¶ 1} Plaintiff-appellant Myron B. Coleman appeals from a summary judgment rendered in favor of defendant-appellee Korrect Plumbing, Inc., on Coleman's cause of action for negligence. Coleman contends that summary judgment was improperly rendered in this case because there are genuine issues of material fact, namely whether Korrect Plumbing had knowledge of the hazard it had created and whether Korrect Plumbing breached its duty to the public using the roadway where the hazard lay. We conclude that even when the evidence is viewed in a light most favorable to Coleman, a reasonable mind could only conclude that Korrect Plumbing lacked knowledge of the hazard in the roadway and therefore did not breach a duty to the public. Accordingly, we conclude that the trial court did not err when it rendered summary judgment.

I
{¶ 2} In October, 2002, Korrect Plumbing began a sewer tie-in project for a local residence. In completing this project, Korrect Plumbing, through its employee Dan Puderbaugh, and an independent contractor, Tom Spatz, cut a hole in the roadway approximately three feet by seven feet. Before leaving the work site at 5:00 p.m., Puderbaugh and Spatz filled the hole with a stabilized backfill until the hole was approximately eight inches deep, and then covered the hole with two 3/4 inch steel plates. Puderbaugh also indicated that each steel plate was four feet by ten feet and required a backhoe to be placed over the hole. The hole was completely covered when Puderbaugh and Spatz left the site.

{¶ 3} Later that evening, at about 10:30 p.m., Coleman was traveling eastbound on Little Richmond Road in Dayton, in the right-hand, curb lane. Coleman alleged that he drove over the hole Korrect Plumbing made earlier that day. Coleman indicated that the hole was not covered by the metal plates and that he drove his vehicle over the hole inadvertently. As a result, Coleman was physically injured, and his vehicle suffered severe damage.

{¶ 4} When Puderbaugh arrived at the work site the following day, the plates completely covered the hole. At approximately 8:30 a.m., Coleman approached Puderbaugh at the work site and indicated that he had driven into the hole the previous evening and that the plates were not covering the hole at that time. This was the first time anyone had reported to a representative of Korrect Plumbing that the plates had shifted during the night.

{¶ 5} Coleman filed a complaint against Korrect Plumbing, alleging that Korrect Plumbing acted negligently by creating a hazard in the public roadway. Coleman argues that the hazard Korrect Plumbing created was the hole that it failed to adequately cover. Alternatively, Coleman argues that if the metal plates were the hazard, then Korrect Plumbing had constructive knowledge that the plates would shift due to swiftly moving traffic on the road. Coleman argues that Korrect Plumbing was negligent by failing to put the public on notice of the hazard by failing to erect signs, signals, barriers, or in some other fashion denote the hole's presence.

{¶ 6} Korrect Plumbing moved for summary judgment, arguing that Korrect Plumbing did not negligently create a hazard by creating the hole in the roadway. Korrect Plumbing argued that the plates could more accurately be construed as the hazard in the road. However, Korrect Plumbing also argued that it did not act negligently by placing the plates in the roadway, because in the company's and in the workers' experience, similar metal plates had never previously shifted in a way that would create a risk to drivers.

{¶ 7} Korrect Plumbing asserted that it had no actual or constructive knowledge of the potential for the plates to move, and that using metal plates to cover a hole in a roadway is a common and well-accepted industry practice. Korrect Plumbing's Vice President, Dave Puderbaugh, testified at his deposition that in his 35 years with Korrect Plumbing, he had never encountered a problem using the steel plates to cover similar holes. Dave Puderbaugh further testified that there is no feasible way to secure the plates to the road, and that Korrect Plumbing never considered attempting to fasten the plates to the road, because the plates are so heavy that they must be moved by heavy machinery, and that it is unlikely that they could be moved by general traffic. Dave Puderbaugh did admit that there was a possibility that the steel plates were shifted by speeding traffic, but he testified that this possibility seemed doubtful. Likewise, Dan Puderbaugh indicated in his affidavit that in his 15 years experience as a plumber, he had used steel plates approximately 25-50 times without incident.

{¶ 8} Coleman filed his own motion for summary judgment, asserting that there existed no issue of material fact from which it could be argued that Korrect Plumbing was not negligent. Coleman argued that Korrect Plumbing's failure to "properly place" the steel plates, by failing to secure the plates to the roadway or anticipate that the movement of traffic might dislodge them, breached its duty of care to the users of the roadway.

{¶ 9} The trial court rendered summary judgment in favor of Korrect Plumbing, finding that Korrect Plumbing neither knew, nor had reason to know, that the plates might shift under the weight of traffic, thereby causing a potential risk of injury to motorists. From the summary judgment rendered against him, Coleman appeals.

II
{¶ 10} Coleman's sole assignment of error is as follows:

{¶ 11} "THE TRIAL COURT ERRED BY GRANTING SUMMARY JUDGMENT IN FAVOR OF DEFENDANT-APPELLEE KORRECT PLUMBING, INC."

{¶ 12} An appellate court reviews summary judgment de novo.Cramer v. McCray (Oct. 14, 2005), Mont. App. No. 20791,2005-Ohio-5507, at ¶ 7. Summary judgment is appropriately granted when, looking at the evidence as a whole: (1) there exist no genuine issues as to any material facts; (2) reasonable minds can come to but one conclusion, and that conclusion is adverse to the non-moving party: and (3) the facts demonstrate that the moving party is entitled to judgment as a matter of law. Horton v.Harwick Chemical Corp. (1995), 73 Ohio St.3d 679, 686-687, 1995-Ohio-286, 653 N.E.2d 1196. The moving party bears the initial burden of demonstrating that no genuine issues of material fact exist for a trier of fact to determine. Harless v.Willis Day Warehousing Co. (1978), 54 Ohio St.2d 64, 66,375 N.E.2d 46. The moving party may successfully meet its burden by showing that the non-moving party's case lacks sufficient evidence to support its claims. Dresher v. Burt (1996),75 Ohio St.3d 280, 289-290, 1996-Ohio-107, 662 N.E.2d 264.

{¶ 13} If the moving party meets its initial burden, the burden then shifts to the non-moving party, under Civ. R. 56(E), to demonstrate the existence of a genuine issue of material fact for trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Batteiger v. Deutsch, Ca021933 (3-28-2008)
2008 Ohio 1582 (Ohio Court of Appeals, 2008)
Diesz v. Ampco Sys. Parking, Unpublished Decision (2-14-2007)
2007 Ohio 621 (Ohio Court of Appeals, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
2006 Ohio 1579, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coleman-v-korrect-plumbing-inc-unpublished-decision-3-24-2006-ohioctapp-2006.