Coleman & Kraus v. Board of Education

77 Misc. 504, 136 N.Y.S. 1054
CourtNew York Supreme Court
DecidedAugust 15, 1912
StatusPublished

This text of 77 Misc. 504 (Coleman & Kraus v. Board of Education) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coleman & Kraus v. Board of Education, 77 Misc. 504, 136 N.Y.S. 1054 (N.Y. Super. Ct. 1912).

Opinion

Page, J.

The -principal legal question involved in this case arises in relation to the liens of the defendants Alfred [505]*505and Julius James. This action was commenced by the plaintiff and a Us pendens filed, and the defendants James filed their answer prior to the expiration of three months from the date of the filing of their liens but they did not file a Us pendens in their own behalf.

The Appellate Division in this department has recently held (Bradley & Sons v. Huber Co., 146 App. Div. 630), where defendants failed to file a Us pendens within three months of the filing of the notice of lien, the lien was lost, and that the lien was not kept alive by the fact that the lienors are made parties defendant in a suit of foreclosure brought by another lienor who files a notice of pendency. The complaint of the plaintiff was dismissed by reason of the fact that their notice of lien was defective and the court held that under that condition the defendants, not having filed a Us pendens, could not litigate their claims further. This case is based upon the authority of Danziger v. Simonson, 116 N. Y. 329, but as is pointed out in Newman Lumber Co. v. Wemple, 56 Misc. Rep. 168, 173, the language of the Consolidation Act, under which that case was decided, was entirely different from that of the present Lien Law, and Justice Clark in a well reasoned opinion held that under the present Lien Law the filing of a Us pendens by the plaintiff satisfied the requirements of the statute as to public as well as private mechanics’ liens and that the defendants do not also have to file Us pendens. This construction is in harmony with the opinion in Brace v. City of Gloversville, 167 N. Y. 452, and the Court of Appeals, in a very recent decision, held in the case of a municipal lien, without discussing the reasons for their holding, that “ the plaintiff having commenced an action which it has sustained, and having duly filed a Us pendens and the defendants * * * having each interposed an answer in the action setting up its lien as provided by the Lien Law, before its lien had expired, it was not necessary for either to commence a further and independent action to foreclose its lien. ,The statute provides that the court may adjust and determine the equities of all the parties to the action, and the order of priority of the different liens (Lien Law, § 45).” [506]*506Berger Mfg. Co. v. City of New York, 206 N. Y. 24, 32. By section 18 of the Lien Law it is provided “ If the lien is for labor done or materials furnished for a public improvement, it shall not continue for a longer period than three months from the time of filing the notice of such lien, unless an action is commenced to foreclose such lien within that time, and a notice of the pendency of such action is filed * * There is now no requirement of the statute for the filing of a lis pendens except as a concomitant of the bringing of an action, and when the Court of Appeals holds that, when the lienors are parties defendant in an action to foreclose a similar lien when the plaintiff has filed a lis pendens, it is unnecessary for the defendant to bring an independent action, it necessarily follows that it is not necessary for the defendants to file a lis pendens. I, therefore, feel that I should follow the decision of the Court of Appeals rather than that of the Appellate Division and hold that the defendants James did not lose their lien by failure to file a lis pendens.

I find in this case that the plaintiffs performed their contract and have a valid first lien for the balance due on their contract in the sum of $849, and for extra work the sum of $478.62, making a total of $1,327.62', with interest thereon from Movember 15, 1911, and are entitled to judgment as prayed in the complaint, with costs. That the defendant Alfred James has a valid lien in the sum of $263.41, with interest from December 7, 1911, together with costs. That the defendant Julius James has a valid lien in the sum of $74.21, with interest from December 7, 1911, together with costs.

I find that there was nothing due the subcontractor Foley from the defendant J. F. Walsh Construction Company, and that the Phoenix Soapstone Company has no lien and that their case should, therefore, be dismissed.

Ordered accordingly.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Danziger v. . Simonson
22 N.E. 570 (New York Court of Appeals, 1889)
Berger Manufacturing Co. v. City of New York
99 N.E. 153 (New York Court of Appeals, 1912)
Brace v. . City of Gloversville
60 N.E. 779 (New York Court of Appeals, 1901)
Bradley v. Henry Huber Co.
146 A.D. 630 (Appellate Division of the Supreme Court of New York, 1911)
J. J. Newman Lumber Co. v. Wemple
56 Misc. 168 (New York Supreme Court, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
77 Misc. 504, 136 N.Y.S. 1054, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coleman-kraus-v-board-of-education-nysupct-1912.