Coleman Capital Corporation v. Travelers Indemnity Company

443 F.2d 47, 1971 U.S. App. LEXIS 10025
CourtCourt of Appeals for the Second Circuit
DecidedMay 25, 1971
Docket629, Docket 35822
StatusPublished
Cited by4 cases

This text of 443 F.2d 47 (Coleman Capital Corporation v. Travelers Indemnity Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coleman Capital Corporation v. Travelers Indemnity Company, 443 F.2d 47, 1971 U.S. App. LEXIS 10025 (2d Cir. 1971).

Opinion

HAYS, Circuit Judge:

This action arose out of the construction of an office building in Garden City, Long Island. The defendant, Travelers Indemnity Company, is the surety on a labor and materials payment bond executed by the general contractor to secure the payment of all subcontractors, materialmen and laborers. In order to complete certain specified concrete work required in the construction of the building, the general contractor engaged Presgold Construction Corporation as a subcontractor. Presgold lacked sufficient funds to finance its performance of the subcontract and arranged financing with the plaintiff, a small business investment company licensed by the Small Business Administration.

In the contract between Presgold and the plaintiff, Presgold assigned to the plaintiff all sums of money due or to become due to Presgold on the subcontract work for the building as security for plaintiff’s extending a line of credit of $25,000 to Presgold for this and several other projects. Presgold covenanted that it would receive and hold any and all monies advanced under the lending agreement as trust funds pursuant to N.Y. Lien Law § 13(6) (McKinney’s Consol.Laws, c. 33, 1966) to be applied to the payment of claims of subcontractors, architects, engineers, materialmen and laborers.

*49 Under the lending agreement, plaintiff advanced to Presgold a total of $126,420.79 to be used to conduct work on the Garden City building and for several other construction jobs which Pres-gold had under contract at the same time. Total payments of $90,055.21 were received under the assignment, leaving a net advance of $36,365.58 which has not been repaid. Ledger sheets of the plaintiff show that a separate account was not kept of the receipts and disbursements on each construction job, but only a total for all the advances and receipts for all Presgold’s construction work wherever done.

The plaintiff would have been completely repaid had Presgold completed the subcontract as planned and had the main contractor paid Presgold according to the original plan. Disputes, however, arose in 1965 between the general contractor and Presgold over its concrete work, resulting in the general contractor’s holding up payments to Presgold. Presgold in turn failed to pay various suppliers and laborers whose claims are the basis of this suit.

Plaintiff at this juncture found itself in a difficult position. It was doubtful that the balance due on the subcontract would be paid. If, as a result, Presgold did not pay the claims of the material-men and laborers then Presgold would be out of business and plaintiff would lose the advances it had made on this and other projects. In order to protect itself plaintiff decided to “purchase” claims totalling $15,709.14 from Pres-gold’s materialmen and laborers. It took assignments from the payees. These payments were found by the district court to have been entered as advances to Presgold’s loan account on the plaintiff’s ledger sheets. Had the work progressed after February 19, 1965 as planned, more assigned funds would have come into existence, but Presgold did its last work on the building about March 22, 1965, and was not entitled to any further payments because, as the district court found, it “had not * * * substantially performed its work either in extent or in quality * * * when it left the job * *

Upon later discovering that the general contractor had executed a labor and materials payment bond with the defendant as surety, plaintiff brought suit against the defendant upon the assignment of the claims of the suppliers and laborers of Presgold. In the first cause of action, plaintiff sought recovery of $4,016 which Presgold failed to pay to a supplier of ready mixed concrete. In the second, plaintiff sought $165 due to a lumber supplier. In the third cause of action, recovery was sought for $11,528.-14 of unpaid wages owed by Presgold to its employees. The fourth, fifth and sixth causes of action were for funds to become due to Presgold under the subcontract; but the court below ruled that nothing more was due on the subcontract, and plaintiff has not appealed from that determination. The court granted summary judgment to the defendant on the first two causes of action on the ground that plaintiff had not given timely notice to defendant on those claims. Partial summary judgment was at first granted to plaintiff on the third cause of action for those claims asserted within the required time, but later this order was reversed and summary judgment was also granted to defendant on the entire third cause of action. Plaintiff appeals the determination of the district court granting summary judgment on these first three causes of action. We affirm the dismissal of all three causes of action.

The district court properly dismissed plaintiff’s first and second causes of action, since plaintiff clearly failed to assert his claim within the time required by the language of the payment and performance bond upon which recovery would be based. The bond provides as follows:

“3. No suit of action shall be commenced hereunder by any claimant,

(a) unless claimant * * * shall have given written notice to any two of the following: the Principal, the Owner, or the Surety above named, *50 within ninety (90) days after such claimant did or performed the last of the work or labor or furnished the last of the materials for which claim is made * * * Such notice shall be served by mailing the same by registered mail or certified mail * * *

to the Principal, Owner or Surety.” The findings of the district court show that the last of the ready mix concrete, upon which the first cause of action is based, was delivered on March 5, 1965 and that notice of the claim was first given to the general contractor and defendant on June 7, 1965, i. e. ninety-four days after the last delivery. The lumber, forming the basis of the second cause of action, was last delivered on February 23, 1965 and notice was not given until June 7, 1965, well over ninety days after the last delivery. However, of the $11,528.14 claimed in the third cause of action, only $192.78 related to laborers who did not perform their last work within ninety days before June 7, 1965.

Plaintiff argues that it should be excused from its failure to give timely notice, because plaintiff did not know of the existence of a payment bond in addition to the customary performance bond, that the bond’s existence was only disclosed inadvertently to plaintiff by the attorney of the general contractor, and that once plaintiff learned of the bond, notice was given within thirty days. As support for its position, plaintiff cites a large body of New York law excusing a beneficiary of a life or fire insurance policy for delay in giving notice if notice is given within a reasonable time after discovery of the existence of the policy. See, e. g., Solomon v. Continental Fire Ins. Co., 160 N.Y. 595, 55 N.E. 279 (1899); Greaves v. Public Service Mutual Ins. Co., 4 A.D.2d 609, 168 N.Y.S.2d 107, 111-112 (1st Dept. 1957), aff’d 5 N.Y.2d 120, 181 N.Y.S.2d 489, 155 N.E.2d 390 (1959); and see 31 N.Y. Jurisprudence, Insurance § 1280 (1963).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
443 F.2d 47, 1971 U.S. App. LEXIS 10025, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coleman-capital-corporation-v-travelers-indemnity-company-ca2-1971.