Davis, J.,

delivered the opinion of the court:

The contract in issue in this case provided for the delivery to the Government, at plaintiff’s quarry, of riprap, intended for [351]*351use in the improvement of the Lower Mississippi. An abstract of the contract may thus be stated:

Plaintiff was to furnish the riprap as called for, and was to furnish all the stone prior to July 1. He was to take care of the Government barges which called at his quarry for the stone and was to load them. Having complied with these conditions, he became entitled to his pay of 55 cents per cubic yard.

The principal duty imposed by the contract upon defendants, aside from that of payment, was to furnish the barges. This they did not do; and upon July 1 plaintiff, through no fault of his, but entirely from the failure on defendants’ part to produce barges at his quarries, had delivered only about one-half' the stone.

At the end of the contract period (July 1, 1883) plaintiff refused to deliver more stone, claiming that his contract had ended; but the engineer officer in charge, in the exercise of that careful protection of the Government’s interests which traditionally has characterized his corps, asked him to proceed under a certain personal assurance of protection.

The Engineer Bureau inWashington differed from the plaint-. iff, and held the contract to be a continuing one. They refused any compensation to plaintiff for delay, and refused any arrangement for the future other than that before in force. Plaintiff protested against this decision, but did furnish, still v under protest, the remainder of the stone, and was paid therefor the contract rate. The last delivery of riprap was in December, 1883, one year after the contract was signed.

Was the delivery of stone to continue over an indefinite period, as in substance contended by the Engineer Bureau, or was plaintiff to deliver 70,000 cubic yards of stone in such quantities as might from time to time be called for, but all to be called for before July 1, as contended by him ? It may be noted here that no point is made as to the regularity or irregularity of call under the clause fixing the monthly allotments.

The specifications annexed to the contract state—

“ That barges will be supplied and towed to and from the points where the stone is loaded by the United States; the quantity to be supplied will be about 12,000 cubic yards per month, beginning about January 2, 1883, navigation permitting. The total quantity required will be about 70,000 cubic yards, with the privilege of taking up to 100,000 cubic yards at the same rates. All to be taken up by June 30, 1883.”

[352]*352Although annexed to the contract as “ specifications ” or “instructions,” this document appears, from its context, to have been prepared before the contract for the information of bidders. The contract states that it was made in conformity with these “ specifications.” Its first clause, after the recital, provides that plaintiff shall deliver—

“Upon barges supplied by defendant, riprap rock, as follows : 5,000 cubic yards in January, 1S83; and 13,000 cubic yards in each of the months of February, March, April, May, and June, 1883, providing navigation will permit the barges to reach the quarry; othenvise, lesser quantities will be furnished monthly. Total quantity to be delivered between January 1 and June 30,1883, is 70,000 cubic yards.”

Further on we find defendants agreeing to supply—

“ Good, serviceable barges as fast as they can be unloaded, but does not guaranty to keep the [plaintiff] supplied with barges at all times, nor does he [Captain Sears] guaranty to take 7,000 cubic yai’ds a month; but he does agree to use his best efforts to supply barges to take stone as fast as possible, and to take the whole 70,000 cubic yards by June 30, 1883, navigation permitting, and, if not, as soon thereafter as possible.”

Again:

“ The said [plaintiff] shall commence the delivery of the rip-rap rock, as specified, on or before the 10th day of January, 1883, and shall complete the said delivery on or before the 30th day of June, 1883, providing the party of the first part can supply barges sufficient to remove it.”

Such are the clauses of this instrument which immediately affect the issue before us. A careful reading of the whole contract shows it to have been prepared in the interest of the Government; the plaintiff receives his pay and is to be furnished barges; otherwise the principal burden very properly is upon him. The barges were furnished in such absolutely insufficient number, that by July 1 less than one-half of the stone had been removed.

We do not agree with the construction put upon this contract by the Engineer Bureau. They laid stress upon certain phrases of the instrument which, disconnected from the context, might support the result they reach. Taking the instrument as a whole,- however, it will be seen that the defendants specifically bound themselves to take all the stone by July 1. There was allowed to them certain elasticity as to the various takings, but everywhere we find the one fact fixed, that prior to July 1 [353]*353all the stone was to be taken. Defendants distinctly pledged themselves to.two things: to take all the stone within the contract period and to pay for it at the contract rate. “ Navigation permitting ” is the only limiting clause upon this part of the agreement; this means “navigation” permitting at the point of loading, and “ navigation ” there did not impede the fulfillment of the contract.

Plaintiff did not agree to hold himself ready for an unlimited period to furnish stone in any amount the Government might ask with the one limit of 70,000 cubic yards. It is not reasonable te suppose that his entire plant, his'men, and boats were to indefinitely await the pleasure and convenience of defendant’s officers. Nearly six months elapsed after the contract period before that amount was called for; a delay not explainable upon any theory of “ days of grace ^ or elasticity in time.

The engineer office relied largely upon the single clause in the contract that barges should be supplied as fast as they could be unloaded, and holding that the barges could not be unloaded faster than they were, then reached the result that plaintiff must be ready to deliver at once, until the United States ceased to care to take it, provided that, at some period,the 70,000 yards were taken. Such an interpretation proceeds upon the assumption that some definite number of barges was to be used in carrying away this stone; no number of barges is named in the contract, and, to push this argument to its logical result, defendants might have used two barges, the lowest number which fulfils the contract demand of the plural, and have held the plaintiff at their command until these barges could have loaded and unloaded all the stone. The reasonable and fair interpretation of the contract is, that defendants were to furnish sufficient barges to take away all’ the stone by about July 1, and that the single phrase “ as fast as they can be unloaded ” refers simply to the regularity of call for the stone. It will be noted, in support of this position, that the same paragraph in which this phrase occurs closes with the provision that all the stone shall be taken by June 30, 1883.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Steiner v. United States
36 F. Supp. 496 (District of Columbia, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
23 Ct. Cl. 341, 1888 U.S. Ct. Cl. LEXIS 29, 1800 WL 1511, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cole-v-united-states-cc-1888.