Cole v. Sears, Roebuck & Co.

389 So. 2d 762, 1980 La. App. LEXIS 4547
CourtLouisiana Court of Appeal
DecidedOctober 8, 1980
DocketNo. 7819
StatusPublished
Cited by2 cases

This text of 389 So. 2d 762 (Cole v. Sears, Roebuck & Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cole v. Sears, Roebuck & Co., 389 So. 2d 762, 1980 La. App. LEXIS 4547 (La. Ct. App. 1980).

Opinion

GUIDRY, Judge.

In this proceeding the plaintiff seeks judgment against his former employer, Sears, Roebuck and Co., pursuant to the provisions of La.R.S. 23:1333,1 accelerating all compensation payments due him and yet unpaid under a judgment dated February 23, 1976.

There is no dispute with regard to the attendant facts which we will briefly summarize.

By judgment of the 10th Judicial District Court for the Parish of Natchitoches dated February 23, 1976, plaintiff was declared totally disabled as a result of a work connected accident and thus entitled to compensation benefits from his employer, Sears, at the rate of $65.00 per week beginning July 23, 1975, not to exceed the statutory maximum of five hundred (500) weeks.2 On appeal this court amended the judgment, so as to delete therefrom the award of penalties and attorney’s fees, but in all other respects the judgment was affirmed. Cole v. Sears, Roebuck & Co., 337 So.2d 900 (La.App.1976).

Upon finality of our judgment Sears began to make the compensation payments due plaintiff under the judgment, which by agreement of the parties were to be made every four (4) weeks. See La.R.S. 23:1201. Presumably, prior to June of 1977 the compensation payments were made and received promptly on or before the end of each four week period. However, beginning in June of 1977 Sears developed a pattern of being late with plaintiff’s compensation payments, the consistency of which circumstance prompted the filing of this suit on September 24,1979. The record reflects that during the period beginning June 26, 1977 and ending September 24, 1979, Sears allowed intervals of five weeks between compensation payments to occur on eight different occasions. Further, during this same time period, on five separate occasions, compensation payments were delayed six weeks; and, at three different times, during this time span, compensation payments were delayed as long as eight weeks. Sears consistent tardiness in the payment of the compensation due plaintiff prompted repeated requests by his counsel requesting that the compensation checks due him be mailed promptly each month as agreed. As stated by the trial court:

“The record reflects repeated letters by counsel to employer and its counsel requesting payment that was delayed by employer.
These letters are as follows:
1. Counsel’s letter to Employer dated August 10, 1977;
2. Counsel’s letter to Employer’s counsel, dated May 17, 1978;
3. Counsel’s letter to Employer’s counsel, dated July 26, 1978;
4. Counsel’s letter to Employer’s counsel, dated October 4, 1978;
5. Counsel’s letter to Employer’s counsel, dated November 30, 1978;
6. Counsel’s letter to Employer’s counsel, dated July 27, 1979.”

[764]*764Finally, this suit was filed, as aforestated, on September 24, 1979, at which time the weekly compensation payments were in arrears since August 5, 1979, a period in excess of seven weeks. Following institution of suit and on October 2,1979, Sears mailed a check to plaintiff covering the compensation payments due for the period from August 6, 1979 through September 30, 1979, being the amount due for a total of eight weeks. In his suit plaintiff prayed for judgment accelerating all compensation not yet payable under the judgment of February 23, 1976, pursuant to the provisions of Section 1333, and attorney’s fees and penalties under the provisions of Section 1201.2. In its answer Sears admitted rendition of the judgment of February 1976 but denied that plaintiff was entitled to a judgment under Section 1333. In addition Sears, in its answer, made the following allegation:

“SECOND DEFENSE”
“As mover, respondent shows that the judgment herein was rendered on February 23,1976; that under the provisions of La.R.S. 23:1123 and La.R.S. 23:1331, a rule should issue herein ordering plaintiff, SAM COLE, JR., through his attorney, to appear and show cause why petitioner should not be required to submit to a medical practitioner appointed by this Honorable Court.”

The order to show cause annexed to defendant’s answer was originally fixed for hearing on October 24, 1979, however, on said date the trial court, on its own motion, rescinded such order reserving to Sears the right to re-submit same for consideration if the trial court determined that Sears had a valid and reasonable defense to plaintiff’s demand for acceleration of the payments not yet made under the original judgment.

The trial court rendered judgment in favor of plaintiff, making due and exigible, all sums not yet payable under the February 1976 judgment, but rejected his demand for penalties and attorney’s fees. Sears has appealed from this judgment. Plaintiff-appellee has answered the appeal requesting amendment of the trial court judgment insofar as it denied his request for penalties and attorney’s fees.

The issues on appeal are: (1) Did the trial court err in rendering judgment accelerating all remaining weekly indemnity due plaintiff under the February 1976 judgment? (2) Did the trial court err in refusing to permit Sears to have plaintiff examined pursuant to the provisions of La. R.S. 23:1331? (3) Did the trial court err in granting plaintiff a judgment pursuant to La.R.S. 23:1333, without statutory discount? (4) Did the trial court err in refusing to award plaintiff-appellee penalties and attorney’s fees?

IS PLAINTIFF ENTITLED TO A JUDGMENT UNDER THE PROVISIONS OF R.S. 23:1333?

We believe the recent decision of our Supreme Court in Lytell v. Strickland Transportation Company, Inc., 373 So.2d 138 (La.1979) to be dispositive of this issue. In Lytell, supra, the court held that after a judgment awarding compensation the penalty provisions of R.S. 23:1333 may be invoked against the employer who fails to pay compensation pursuant to such judgment for six successive weeks, “whether or not the award is based on disability (subject to reopening) or upon a non-disabling specific injury (with a scheduled fixed-number of weeks)”. In the course of its opinion in Lytell, the court stated:

“The circumstance that the judgment might be subject to modification under Section 1331 (i. e., if the disability lessens) is not, under the statutory scheme, relevant to the availability of the penalty provided by the succeeding Section 1333. The latter section complements the statutory scheme of the judicial administration and enforcements of judgments awarding weekly compensation to an injured employee; it provides a penalty against the recalcitrant employer for non-payment of the executory judgment against him awarding weekly compensation to an employee — the employer who, despite definitive judicial determination of his liability, nevertheless still fails to pay weekly com[765]*765pensation due the work-injured employee.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Continental Ins. Cos.
410 So. 2d 1058 (Supreme Court of Louisiana, 1982)
Cole v. Sears
395 So. 2d 811 (Supreme Court of Louisiana, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
389 So. 2d 762, 1980 La. App. LEXIS 4547, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cole-v-sears-roebuck-co-lactapp-1980.