Coherent Logix, Inc.

CourtArmed Services Board of Contract Appeals
DecidedApril 2, 2015
DocketASBCA No. 59725
StatusPublished

This text of Coherent Logix, Inc. (Coherent Logix, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coherent Logix, Inc., (asbca 2015).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of-- ) ) Coherent Logix, Inc. ) ASBCA No. 59725 ) Under Contract Nos. FA8650-05-C-l 825 ) W911QX-06-C-0002 ) N00039-08-C-0092 ) FA8750-05-C-0005 ) FA9453-05-C-0029 ) Wl 5QKN-04-C-l l 59 ) Wl SQKN-06-C-0219 ) Wl 5P7T-07-C-L610 )

APPEARANCE FOR THE APPELLANT: Daniel C. Minutillo, Esq. Minutillo, A Professional Law Corporation San Jose, CA

APPEARANCES FOR THE GOVERNMENT: E. Michael Chiaparas, Esq. DCMA Chief Trial Attorney Joseph D. Keller, Esq. Trial Attorney Defense Contract Management Agency Chantilly, VA

OPINION BY ADMINISTRATIVE JUDGE O'SULLIVAN

In this appeal, Coherent Logix, Inc. (CLX) appeals from the contracting officer's decision not to waive the penalty assessed on unallowable costs included in appellant's 2007 incurred cost submission. CLX has elected to proceed under Board Rule 12.2, 1 Expedited Procedures, and both parties have elected to waive a hearing and submit their cases on the written record pursuant to Board Rule 11.

1 The Contract Disputes Act, implemented by Board Rule 12.2, provides that this decision shall have no value as precedent, and in the absence of fraud shall be final and conclusive and may not be appealed or set aside. FINDINGS OF FACT

CLX is a small business concern based in Austin, Texas. Its principal business focus is creating technology for high performance data processing using a scalable embedded processor platform. (Compl. ~ 1) CLX, during the period relevant hereto was performing a number of flexibly priced contracts for the Air Force (Air Force Research Laboratory), Army (RDECOM, Picatinny, and CECOM), and Navy (SPA WAR) (R4, tab 5 at G-63). Of the eight contracts being performed by CLX, six exceeded the statutory dollar value threshold and were treated as "covered contracts" under FAR 42.709 (app. br. at 7; R4, tab 5 at G-63).

On 13 August 2008, CLX submitted its final indirect cost rate proposal for its fiscal year ending 31December2007 (comp!.~ 11). On 19 June 2013, CLX submitted a revised final indirect rate cost proposal for 2007 (R4, tab 5 at G-32). The Defense Contract Audit Agency (DCAA) questioned certain overhead and general and administrative ("G&A") costs and found $82,396 of such costs to be expressly unallowable and subject to penalty (id. at G-64 ). A Level One penalty was recommended to be assessed (id.). 2

The questioned expressly unallowable costs consisted primarily of patent legal fees in the amount of$68,894 (R4, tab 5 at G-64). The remainder of the questioned expressly unallowable costs included costs of exhibition at trade shows (advertising costs), travel costs exceeding per diem, undocumented first class airfare, and costs of meals determined to be entertainment (id. at G-40).

On 21November2014, the Defense Contract Management Agency (DCMA) administrative contracting officer (ACO) issued his final decision finding that CLX had included expressly unallowable costs in its 2007 submission, consisting of the $68,894 in patent legal fees and $13,204 in other expressly unallowable costs (R4, tab 6 at G-110-11). The ACO assessed a Level One penalty of $73,912 on the portion of these costs allocable to covered contracts, and added interest of$17,239, for a total of $91,151. He also stated that while he had carefully considered CLX's request for waiver of the penalty under FAR 42.709-S(c), he had determined that CLX's request did not meet the FAR criteria for waiver of the penalty. (Id. at G-113-14) In particular, the ACO stated that the unallowable costs were not inadvertently incorporated into the proposal, but were included because CLX believed them to be allowable (id.)

2 FAR 42. 709-1 prescribes a penalty of 100 percent of the amount of expressly unallowable costs allocated to covered contracts (Level One); and a penalty of twice the amount of unallowable costs allocated to covered contracts if the cost had been determined to be unallowable prior to proposal submission (Level Two).

2 CLX timely appealed to this Board, alleging (1) the ACO's final decision was untimely under the Contract Disputes Act's six-year statute of limitations, 41 U.S.C. § 7103(a)(4); and (2) the ACO erred in declining to waive the penalty. CLX does not contest the underlying issues of the unallowability of the costs or the government's imposition of a penalty, only the ACO's decision not to waive the penalty. (Compl. ~~ 16-34) Further, appellant has chosen to submit argument and evidence limited to the patent legal costs.

DECISION

Is the Government's Claim Barred?

Whether or not a party's claim has been asserted within the Contract Disputes Act's six-year statute of limitations is no longer ajurisdictional issue. Sikorsky Aircraft Corp. v. United States, 773 F.3d 1315, 1320-22 (Fed. Cir. 2014). We treat CLX's assertion that the government's final decision on its claim for penalties was issued after the six-year period passed as an affirmative defense, on which CLX has the burden of proof.

CLX submitted its original final indirect cost rate proposal on 13 August 2008. The ACO issued his final decision on 21November2014. The question is whether the government's claim accrued at the time the original proposal was submitted. If so, the government's claim for penalty is untimely. 41 U.S.C. § 7103(a)(4).

The parties have briefed this issue, focusing only on the patent legal costs. CLX argues that the government's claim accrued no later than 13 August 2008, because the government had conducted audits of prior years' final indirect rate cost proposals during which it had access to detailed cost records involving the legal fees at issue. (App. br. at 5) In support of this contention, CLX submitted for the record the affidavit of Donald Gorsuch, its Vice President for Finance and Administration. Mr. Gorsuch stated as follows:

Included in the 2005 ICE Schedules A, Band Care Legal costs totaling $21,500 (not related to patents) and Amortization costs totaling $237,543 (all related to patents amortization IP). Our General Ledger accounting records for 2005 shows [sic] the $21,500 and the $23 7 ,543 total accumulated Amortization, all of which tie to the amounts in the 2005 ICE Schedules Band C. On the left side of the General Ledger pages are the transactions and accounts, which clearly show legal fees, Meyertons (our patent attorneys), and amortization IP. The General Ledger was readily available to the Government Auditors to verify the

3 detailed amounts in the 2005 ICE and the Amortization amount for patents was reviewed by Trista Franklin, the DCAA Auditor and all but $41,028 of the claimed amount of $237,543 was accepted and paid by the Government.

... [CLX's 2006 final indirect cost rate proposal included] legal costs totaling $25,998 and Amortization IP (all related to patents) costs totaling $2,733 and $24,599 .... Our General Ledger accounting pages for 2006 show the [$25,998] and the $27,331.94 (the sum of $2,733 and $24,599) all of which tie to the amounts in the 2006 Revised ICE. On the left side of the General Ledger pages are the transactions and accounts which clearly show legal fees, Meyertons (our patent attorneys), patents and amortization IP.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sikorsky Aircraft Corporation v. United States
773 F.3d 1315 (Federal Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Coherent Logix, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/coherent-logix-inc-asbca-2015.