Cohen v. MAYFLOWER COPR.

86 S.E.2d 860, 196 Va. 1153, 1955 Va. LEXIS 185
CourtSupreme Court of Virginia
DecidedApril 25, 1955
DocketRecord 4352
StatusPublished
Cited by31 cases

This text of 86 S.E.2d 860 (Cohen v. MAYFLOWER COPR.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cohen v. MAYFLOWER COPR., 86 S.E.2d 860, 196 Va. 1153, 1955 Va. LEXIS 185 (Va. 1955).

Opinion

Eggleston, J.,

delivered the opinion of the court.

Mayflower Corporation, hereinafter referred to as the plaintiff, filed a motion for judgment against Donald Cohen, trading as Deecee Associates, and United States Casualty Company to recover damages for the alleged breach of two written contracts whereby Cohen had agreed, for the sum of $20,895, to furnish the necessary labor, materials and equipment and perform certain work on buildings owned by the plaintiff. Cohen, as principal, and United States Casualty Company, as surety, executed a bond in the penalty of $21,000 guaranteeing the performance of the “contract” (sic). There was a trial before a jury which resulted in a verdict and judgment of $21,000 in favor of the plaintiff against both defendants, and to review that judgment the present writ of error was allowed.

Mayflower Corporation owns a large 16-story brick apartment building with an adjacent one-story brick shopping *1155 center located near the ocean front at Virginia Beach. Shortly after the completion of the buildings serious leaks developed in both of them, and to correct this condition the plaintiff asked for bids for waterproofing the buildings. The written bids of Cohen to do the work, and the acceptances thereof by the plaintiff, are printed in the margin. 1

The performance bond, which is in the usual form, was executed on May 1, 1952.

*1156 Cohen started work on the contracts in May, 1952, and on June 26 wrote the plaintiff that the work had been completed and that the balance was due. In this letter Cohen stated in part:

“This work has been completed as of this date and we *1157 will appreciate a check * * * which covers the following contracts:

“1. Waterproofing of the Mayflower Apartments $20,000.

“2. Waterproofing of the shopping center $895.

.V. J/, Jf. Jt Jf, Jf,

'fr -7,' ■Jp . ■?? 7i* •Tv' W

“As you understand, while we believe this job is one hundred per cent waterproofed right now, there is always the possibility of some small leaks appearing. Please do not hesitate to call us if this should occur.”

On or about July 31, 1952, the plaintiff paid Cohen the amount due under the contracts. Shortly thereafter it was found that the buildings were still leaking badly in the locations which Cohen had attempted to remedy. Cohen was notified and on several occasions from the fall of 1952 through the early summer of 1953 he returned and attempted to correct the situation, but was unable to do so. Finally, by letter dated August 28, 1953, the plaintiff notified Cohen that in view of his failure to perform the contracts the plaintiff would have the work done by someone else and *1158 would look to Cohen and the surety for reimbursement for the cost thereof. A copy of this letter was sent to the surety company. In reply, both Cohen and the surety- company took the position that there had been no breach of the "contracts and denied liability. Thereupon the plaintiff engaged another contractor, Harry E. Paul, to waterproof the buildings at a cost of $23,500.

The evidence on behalf of the plaintiff showed that the work done by Cohen had not corrected the leaks, that numerous window frames had not been properly caulked, and that many open mortar joints in the brick walls of the apartment building had not been properly filled.

There is further evidence that Paul, the second contractor, was successful in correcting these conditions and stopping the leaks.

At the trial in the lower court the defendant admitted that the leaks had not been corrected and the buildings had not been waterproofed by Cohen’s work. But they contended that under the terms of the contracts Cohen was not obligated to waterproof the buildings;, that his undertaking was merely to perform certain specified work, namely, to apply mortar where required, caulk the window frames, caulk the copings, and apply waterproof paint to the outside surface of the bricks, and that this was done. It was further contended that the provision in the contract that “The above work is covered by our standard two-year guarantee against the penetration of water through the surfaces treated by üs,” bound Cohen to “service” for a period of two years the work done by him; that is, during the specified period Cohen would, at his own expense, attempt to correct any leaks which might develop.

These contentions are entirely devoid of merit. Cohen admitted that before he submitted his bids he examined the buildings, knew of the conditions which caused the leaks, and knew that the plaintiff wanted these corrected. It is absurd to say that in this situation the parties contemplated that Cohen was bound merely to furnish and apply the *1159 specified materials and do the specified work, regardless o£ whether the desired results were accomplished. Moreover,, when Cohen wrote the plaintiff on June 26 that the work had been completed he demanded payment for “Waterproofing of the Mayflower Apartments $20,000,” and “Waterproofing of the shopping center $895.” In the same letter he said, “while we believe this job is one hundred per cent waterproofed right now, there is always the possibility of some small leaks appearing. Please do not hesitate to call us if this should occur.” This letter clearly shows that the defendant, Cohen, interpreted the contracts as placing upon him the obligation to stop the leaks and waterproof the buildings.

Accordingly, the trial court correctly instructed the jury that under the provisions of the contracts the defendant, Cohen, undertook to waterproof the walls, window frames, etc., “so as to prevent the penetration of water through these areas for a period of two years.”

The main question in the case and that which prompted the granting of this writ of error is, What effect did the failure of the defendant, Cohen, to register as a contractor and obtain the license required by the provisions of Chapter 7, Title 54, of the Code of Virginia (§§ 54-113 to 54-145, 2 inclusive), have upon the right of the plaintiff, Mayflower Corporation, to maintain this action?

The defendants argue that since “the aggregate amount of the contracts * * * was for more than $20,000,” and since Cohen had not registered and had not obtained the license required by the provisions of the chapter, the contracts were “illegal and void” under our holding in Bowen Electric Co. v. Foley, 194 Va. 92, 100, 72 S. E. (2d) 388, 393, and that consequently an action for-damages for breach of the contracts and the performance bond cannot be maintained.

The statute applies “when the cost of the undertaking * * * is twenty thousand dollars or more.” Code, § 54-113.

*1160

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fleming Steel Co. v. W.M. Schlosser Co.
345 F. App'x 752 (Third Circuit, 2009)
Shuttleworth, Ruloff & Giordano, P.C. v. Nutter
493 S.E.2d 364 (Supreme Court of Virginia, 1997)
Turja v. Turja
Fourth Circuit, 1997
Shatarsky v. Long & Foster Real Estate, Inc.
31 Va. Cir. 328 (Loudoun County Circuit Court, 1993)
P. M. Palumbo, Jr., M.D., Inc. v. Bennett
409 S.E.2d 152 (Supreme Court of Virginia, 1991)
Malpractice Research, Inc. v. Norman
24 Va. Cir. 118 (Fairfax County Circuit Court, 1991)
Old Dominion Lodge No. 1 v. Smoky Mountain Secrets, Inc.
36 Va. Cir. 582 (Roanoke County Circuit Court, 1991)
Erwin v. T. E. M., Inc.
17 Va. Cir. 376 (Virginia Beach County Circuit Court, 1989)
J. W. Woolard Mechanical & Plumbing, Inc. v. Jones Development Corp.
367 S.E.2d 501 (Supreme Court of Virginia, 1988)
Blick v. Marks, Stokes and Harrison
360 S.E.2d 345 (Supreme Court of Virginia, 1987)
Bowles v. Davenport
2 Va. Cir. 259 (Richmond County Circuit Court, 1985)
Board of Supervisors v. Safeco Insurance Co. of America
310 S.E.2d 445 (Supreme Court of Virginia, 1983)
BD. OF SUP'RS OF STAFFORD CTY. v. Safeco Ins.
310 S.E.2d 445 (Supreme Court of Virginia, 1983)
Lee v. Lake
5 Va. Cir. 45 (Arlington County Circuit Court, 1982)
Kennedy v. Annandale Boys Club, Inc.
272 S.E.2d 38 (Supreme Court of Virginia, 1980)
First Charter Land Corp. v. Middle Atlantic Dredging, Inc.
237 S.E.2d 145 (Supreme Court of Virginia, 1977)
State Ex Rel. Mayle v. Aetna Casualty & Surety Co.
166 S.E.2d 133 (West Virginia Supreme Court, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
86 S.E.2d 860, 196 Va. 1153, 1955 Va. LEXIS 185, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cohen-v-mayflower-copr-va-1955.