Cofrancesco Construction Co. v. Superior Components, Inc.

371 S.W.2d 821, 52 Tenn. App. 88, 1963 Tenn. App. LEXIS 92
CourtCourt of Appeals of Tennessee
DecidedMarch 12, 1963
StatusPublished
Cited by7 cases

This text of 371 S.W.2d 821 (Cofrancesco Construction Co. v. Superior Components, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cofrancesco Construction Co. v. Superior Components, Inc., 371 S.W.2d 821, 52 Tenn. App. 88, 1963 Tenn. App. LEXIS 92 (Tenn. Ct. App. 1963).

Opinion

COOPER, J.

This action was originally brought by the Cofrancesco Construction Company, Inc. and the Trustees of Phillips Temple C. M. E. Church in an effort to enjoin Superior Components, Inc. from enforcing a mechanic’s lien for materials used in construction of a church, and to recover actual and punitive damages for the erroneous filing of said lien.

By answer and cross-bill, Superior sought enforcement of the mechanic’s lien in the amount of $4,487.29, which was reduced during the trial to $4,139.63.

The material item in dispute was the cost of 25,000 feet of #1, Douglas Fir 4" x 6" tongue and groove roof decking. The bid of Superior, accepted by Cofrancesco, showed the price to be $1319.00. Superior insists that the correct price was $5,319.00, and that the quoted price was the result of an error in transcribing figures from its worksheet to the typed bid quotation submitted to Cofrancesco; that Cofrancesco knew of the error at the time it accepted the bid, and knowingly took advantage of it. Superior further insists that the error was discovered before the decking was used by Cofrancesco and that Superior sought a rescission of the contract and a return of the material, thus placing the parties in status *90 quo, but that Cofrancesco refused; that Superior sent its trucks to pick up the decking and that Cofrancesco then agreed to pay the corrected price rather than give up the decking.

The Chancellor, after hearing proof hy oral testimony, found that Superior unquestionably made a mistake in submitting its bid, but was “unwilling to ascribe to Mr. Cofrancesco the astuteness of close inspection required” to “have caught the mistake before the acceptance of the bid”; “that the delay between August the 8th (the date the bid was accepted) and October the 13th and 14th, when the mistake was discovered by [Superior], put Mr. Cofrancesco in such a position that his rights were materially affected and, * * * were the offer and acceptance not required to stand firm, it would result in injury or damage to him;” that there was no promise by Cofrancesco to pay the corrected sum and that, if there were, there was no consideration to support the promise.

The Chancellor further found that Superior had furnished materials not provided for in the original contract, and that Cofrancesco was indebted to Superior for $139.63 for these materials.

The Chancellor then dismissed the suit brought by Cofrancesco Construction Company and the Church, denied Superior recovery for the $4,000.00 error, and awarded it a judgment for $139.63. Superior appealed, contending that the Chancellor erred (1) in not holding that Superior was entitled to rescind the contract as to the decking; (2) in not finding that Cofrancesco knew that the error had been made and wilfully concealed his *91 knowledge; and (3) in failing to award Superior a decree against Cofrancesco for the $4,000.00 in question

The record reveals that in May, 1961, the Cofrancesco Construction Company entered into a contract with the Phillips Temple C.M.E. Church to do extensive remodeling and to build an extension, including a sanctuary, at a price of $80,000.00

By August, 1961, the work on the Church had progressed to such a point that Cofrancesco decided to take bids on prefabricated wooden trusses and roof decking for the sanctuary. Cofrancesco contacted Superior and requested that it submit a bid as it was the only fabricators of wood trusses in the immediate area. At the same time, Cofrancesco contacted Graves-Buttram Company of Athens, Tennessee to bid on the roof decking, and the lumber to be used in trusses to be constructed on the job by Cofrancesco. Both suppliers were requested to rush their bids through.

Graves-Buttram Lumber Company submitted an itemized bid for lumber in the total amount of $5,745.35. In the bid was included a price of $4,015.50 for 24,420 board feet of #1 common yellow pine 4" x 6" tongue and groove decking. The decking was standard and could be delivered to the church site within 10 days.

Superior submitted a bid quoting a price of $4,462.01 for the fabricated trusses, and a price of $1310.00 for the 4" x 6" tongue and groove decking (Douglas Fir), and an alternate price of $3,371.21 for 4' x 16' stressed skin panels, calling attention to the fact that the skin panels would reduce onsite labor costs. The board feet of Douglas Fir decking to be furnished was not shown on the typed quotation; however, it is undisputed that it *92 would take in excess of 24,000 board feet to cover the sanctuary roof. This was known to Superior, and must have been known to Cofrancesco, even though it is argued to the contrary in its brief, as Cofrancesco found it necessary to estimate cost of materials and labor in making its original contract with the Church, and it is admitted that the bid for supplying the decking was not sought until after the general contract had been signed for construction of the Church.

On receipt of Superior’s bid, Cofrancesco asked for 2% discount if payment was made within 10 days from billing, which was agreed to, and asked that the bid be rewritten to show the total of the two figures in the original bid and the discount, leaving off the bid for alternate decking.

The retyped bid was submitted to Cofrancesco on August 8th, and Superior was awarded the contract.

Superior proceeded to fabricate the trusses and ordered the necessary 25,000 board feet of “Select KD Doug. Fir” tongue and groove decking from the-son Plywood and Timber Company, Everett, Washington. The decking was shipped on August 28, 1961, and was delivered directly from the freight car to the job site on either October 3rd or 4th, 1961. The actual cost of the decking, as shown by the invoice from the Shipper, was $3793.64.

On October 11th or 12th, Superior discovered that in making its bid to Cofrancesco, it had made a $4,000.00 error in transcribing figures from its worksheet to the typed bid quotation, and contacted its attorney for advice on how to proceed to have the contract rescinded or reformed to show the correct price.

*93 In keeping with the advice of its attorney, Superior wrote Cofraneesco on October 16, 1961 explaining ■ how the error had been made and expressing its intention to pick np the decking if Cofraneesco was not agreeable to paying the corrected price, or if Cofraneesco wished to purchase the material from another supplier. At the time Superior notified Cofraneesco of the error, the decking had not been used, and could not be used for several days as all trusses had not been delivered to the job site. The record is silent on the difficulty, if any, that Cofran-cesco would encounter in securing additional Douglas Fir decking; however, Graves-Buttram testified that it could deliver the #1 yellow pine decking contained in its bid within 10 days.

Cofraneesco refused to accept the increased price and so informed Superior by letter dated October 19, 1961.

On October 23, 1961, Superior sent its trucks and men to pick up the decking from the job site.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Ollie
207 B.R. 586 (W.D. Tennessee, 1997)
Mullins v. Parkey
874 S.W.2d 12 (Court of Appeals of Tennessee, 1992)
Puget Sound National Bank v. Selivanoff
514 P.2d 175 (Court of Appeals of Washington, 1973)
Reed's Photo Mart v. Monarch Marking System Co.
475 S.W.2d 356 (Court of Appeals of Texas, 1971)
Simons v. Federal Bar Building Corporation
275 A.2d 545 (District of Columbia Court of Appeals, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
371 S.W.2d 821, 52 Tenn. App. 88, 1963 Tenn. App. LEXIS 92, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cofrancesco-construction-co-v-superior-components-inc-tennctapp-1963.