Coastal Industries, LLC v. Arkel Constructors, LLC; Smith LaRock Architecture P.C. and the Leffler Group Consulting Structural Engineers, Inc.
Opinion
STATE OF LOUISIANA
COURT OF APPEAL
FIRST CIRCUIT
2019 CA 1586
COASTAL INDUSTRIES, LLC
VERSUS
ll' ARKEL CONSTRUCTORS, LLC, SMITH LAROCK ARCHITECTURE P. C.
AND THE LEFFLER GROUP CONSULTING STRUCTURAL ENGINEERS, INC.
SEP 212020
Judgment Rendered:
On Appeal from the
Nineteenth Judicial District Court In and for the Parish of East Baton Rouge State of Louisiana
Trial Court No. 649, 069
The Honorable Wilson Fields, Judge Presiding
Russel W. Wray Attorneys for Plaintiff/Appellant, Jacob A. Altmyer Coastal Industries, LLC St. Francisville, Louisiana
John C. Funderburk Attorneys for Defendant/ Appellee, Thomas D. Bourgeois, Jr. Arkel Constructors, LLC Baton Rouge, Louisiana
B FCS HI GINBOTHAM, PENZATO, AND LANIER, JJ.
PENZATO, J.
Appellant, Coastal Industries, LLC, ( Coastal) appeals a trial court judgment
granting a motion to lift stay and confirming an arbitration award in favor of appellee, Arkel Constructors, LLC (Arkel) and denying Coastal' s motion to vacate, correct and/ or modify the award of the arbitrator and ex parte motion to stay proceedings to enforce the award. For the reasons that follow, we dismiss the
appeal.
FACTS AND PROCEDURAL HISTORY
Coastal originally filed a petition for damages against Arkel, Smith LaRock Architecture P. C. ( Smith LaRock), and The Leffler Group Consulting Engineers, Inc., d/ b/ a The Leffler Group ( Leffler) on June 13, 2016. Coastal sought damages
from the three defendants arising from the construction of a building at the Marathon Petroleum Company LP ( Marathon) plant in Garyville, Louisiana ( the Project). Arkel, the general contractor, subcontracted with Coastal to perform
certain work ( the subcontract) at the site. Coastal alleged that Smith LaRock, the
architect, was engaged by Marathon to design the Project and that Smith LaRock contracted with Leffler to perform the structural engineering work. Coastal
claimed that Arkel breached the subcontract resulting in damages. Coastal also
asserted that Smith LaRock and Leffler breached the standard of care owed to
Coastal by providing untimely and incorrect plans, specifications, and
modifications that interfered in Coastal' s work causing damages.
On July 20, 2016, Arkel filed a dilatory exception of prematurity and alternative motion to stay and compel arbitration, claiming that Coastal' s claims fell within the scope of an arbitration clause contained in the subcontract. Arkel
requested that Coastal' s claims be dismissed pursuant to the exception of
prematurity.' Leffler and Smith LaRock both answered Coastal' s suit and filed a
joint memorandum in support of Arkel' s exception of prematurity.
On May 9, 2017, the trial court held a hearing on Arkel' s exception of
prematurity, and all three defendants argued that Arkel should be dismissed on the
2
exception of prematurity. At the conclusion of the hearing, the trial court heard
arguments concerning whether Arkel should be dismissed pursuant to the
3
exception of prematurity and took the matter under advisement. On May 16,
2017, the trial court held another hearing to issue its ruling wherein it granted the exception of prematurity, ordered the arbitration, and issued a stay of the proceedings. The trial court clarified in open court that it was issuing a stay rather than dismissing Coastal' s claims. The trial court signed an order on June 13, 2017, reflecting its oral ruling, granting the exception of prematurity and staying all claims of Coastal against Arkel and the remaining defendants pending arbitration between Arkel and Coastal.' No claim or party was dismissed by the June 13, 2017 order.
Following the trial court' s order, Arkel and Coastal submitted to arbitration with the American Arbitration Association, wherein Arkel answered the arbitration
demand and asserted a counterclaim against Coastal. The arbitrator issued an
Coastal had previously filed its own " Motion to Stay Proceedings Pending Arbitration," but later filed an ex parte motion to withdraw that motion, which the trial court granted on January 24, 2017.
2 The trial court originally held a hearing on Arkel' s exception of prematurity on March 20, 2017. After determining that Coastal would be allowed to offer expert testimony, the trial court rescheduled the hearing.
3 On July 20, 2016, a notice of removal was filed with the United States District Court for the Middle District of Louisiana ( Middle District) ( which is not contained in this record but is referred to in other pleadings).
Counsel for Coastal argued at the May 9, 2017 hearing that the entire case had been remanded from the Middle District and that the defendants were attempting to have Arkel dismissed, so that the remaining two defendants could return the case to the Middle District.
4 We note, however, that La. C. C.P. art. 933( A) provides, in pertinent part, " If the dilatory exception pleading prematurity is sustained, the premature action, claim, demand, issue or theory shall be dismissed." ( Emphasis added).
interim award on December 11, 2018, that contained certain findings. In
connection with the claims made by Coastal, the arbitrator found Coastal' s " Total Cost Claim" to be unreasonable and denied Coastal' s claim of $972, 278. 72 for
Termination Costs." The arbitrator also found that Arkel did not unreasonably withhold or delay payment to Coastal or breach the contract regarding payment to Coastal. Therefore, the arbitrator denied the claims made by Coastal for payment of penalties, interest and/ or attorneys' fees. On February 12, 2019, in his final arbitration award, which incorporated the interim award, the arbitrator awarded
Arkel a total of $530, 574. 02 against Coastal ( final arbitration award). No award
was made to Coastal. The final arbitration award included the following language: This Award is in full settlement of all claims and counterclaims submitted in this
Arbitration. All claims not expressly granted herein are hereby denied." Following the final arbitration award, on February 15, 2019, Arkel filed a motion to lift stay and confirm arbitration award ( motion to lift stay/ confirm award) pursuant to La. R.S. 9: 42095. Coastal filed its own motion on March 14, 2019, to
vacate, correct, and/ or modify award of arbitrator and ex parte motion to stay proceedings to enforce the award ( motion to vacate/ stay enforcement of award) pursuant to La. R.S. 9: 4210 and La. R.S. 9: 4211. Both Coastal and Arkel opposed
the other party' s motion.
On May 6, 2019, a hearing was held on both Arkel' s motion to lift stay/ confirm award and Coastal' s motion to vacate/ stay enforcement of award. After arguments, the trial court took the matter under advisement. On May 20,
2019, the trial court ruled on both motions in open court and specifically ordered 5 Louisiana Revised Statute 9: 4209 provides:
At any time within one year after the award is made any party to the arbitration may apply to the court in and for the parish within which the award was made for an order confirming the award and thereupon the court shall grant such an order unless the award is vacated, modified, or corrected as prescribed in R. S. 9: 4210 and 9: 4211. Notice in writing of the application shall be served upon the adverse party or his attorney five days before the hearing thereof.
M
that the stay be lifted and the final arbitration award be confirmed.' On August 19,
2019, the trial court signed a judgment that lifted the stay, denied Coastal' s motion to vacate/ stay enforcement of award, and granted Arkel' s motion to lift
stay/ confirm award. The August 19, 2019 judgment ( judgment) further entered
judgment in favor of Arkel and against Coastal for specific amounts as follows:
Free access — add to your briefcase to read the full text and ask questions with AI
Coastal Industries, LLC v. Arkel Constructors, LLC; Smith LaRock Architecture P.C. and the Leffler Group Consulting Structural Engineers, Inc. (Coastal Industries, LLC v. Arkel Constructors, LLC; Smith LaRock Architecture P.C. and the Leffler Group Consulting Structural Engineers, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.