STATE OF LOUISIANA
COURT OF APPEAL
FIRST CIRCUIT
2019 CA 1586
COASTAL INDUSTRIES, LLC
VERSUS
ll' ARKEL CONSTRUCTORS, LLC, SMITH LAROCK ARCHITECTURE P. C. AND THE LEFFLER GROUP CONSULTING STRUCTURAL ENGINEERS, INC.
SEP 212020 Judgment Rendered:
On Appeal from the Nineteenth Judicial District Court In and for the Parish of East Baton Rouge State of Louisiana Trial Court No. 649, 069
The Honorable Wilson Fields, Judge Presiding
Russel W. Wray Attorneys for Plaintiff/Appellant, Jacob A. Altmyer Coastal Industries, LLC St. Francisville, Louisiana
John C. Funderburk Attorneys for Defendant/ Appellee, Thomas D. Bourgeois, Jr. Arkel Constructors, LLC Baton Rouge, Louisiana
B FCS HI GINBOTHAM, PENZATO, AND LANIER, JJ. PENZATO, J.
Appellant, Coastal Industries, LLC, ( Coastal) appeals a trial court judgment
granting a motion to lift stay and confirming an arbitration award in favor of
appellee, Arkel Constructors, LLC (Arkel) and denying Coastal' s motion to vacate,
correct and/ or modify the award of the arbitrator and ex parte motion to stay
proceedings to enforce the award. For the reasons that follow, we dismiss the
appeal.
FACTS AND PROCEDURAL HISTORY
Coastal originally filed a petition for damages against Arkel, Smith LaRock
Architecture P. C. ( Smith LaRock), and The Leffler Group Consulting Engineers,
Inc., d/ b/ a The Leffler Group ( Leffler) on June 13, 2016. Coastal sought damages
from the three defendants arising from the construction of a building at the
Marathon Petroleum Company LP ( Marathon) plant in Garyville, Louisiana ( the
Project). Arkel, the general contractor, subcontracted with Coastal to perform
certain work ( the subcontract) at the site. Coastal alleged that Smith LaRock, the
architect, was engaged by Marathon to design the Project and that Smith LaRock
contracted with Leffler to perform the structural engineering work. Coastal
claimed that Arkel breached the subcontract resulting in damages. Coastal also
asserted that Smith LaRock and Leffler breached the standard of care owed to
Coastal by providing untimely and incorrect plans, specifications, and
modifications that interfered in Coastal' s work causing damages.
On July 20, 2016, Arkel filed a dilatory exception of prematurity and
alternative motion to stay and compel arbitration, claiming that Coastal' s claims
fell within the scope of an arbitration clause contained in the subcontract. Arkel
requested that Coastal' s claims be dismissed pursuant to the exception of
2 prematurity.' Leffler and Smith LaRock both answered Coastal' s suit and filed a
joint memorandum in support of Arkel' s exception of prematurity.
On May 9, 2017, the trial court held a hearing on Arkel' s exception of
prematurity, and all three defendants argued that Arkel should be dismissed on the 2 exception of prematurity. At the conclusion of the hearing, the trial court heard
arguments concerning whether Arkel should be dismissed pursuant to the
3 exception of prematurity and took the matter under advisement. On May 16,
2017, the trial court held another hearing to issue its ruling wherein it granted the
exception of prematurity, ordered the arbitration, and issued a stay of the
proceedings. The trial court clarified in open court that it was issuing a stay rather
than dismissing Coastal' s claims. The trial court signed an order on June 13, 2017,
reflecting its oral ruling, granting the exception of prematurity and staying all
claims of Coastal against Arkel and the remaining defendants pending arbitration
between Arkel and Coastal.' No claim or party was dismissed by the June 13,
2017 order.
Following the trial court' s order, Arkel and Coastal submitted to arbitration
with the American Arbitration Association, wherein Arkel answered the arbitration
demand and asserted a counterclaim against Coastal. The arbitrator issued an
Coastal had previously filed its own " Motion to Stay Proceedings Pending Arbitration," but later filed an ex parte motion to withdraw that motion, which the trial court granted on January 24, 2017.
2 The trial court originally held a hearing on Arkel' s exception of prematurity on March 20, 2017. After determining that Coastal would be allowed to offer expert testimony, the trial court rescheduled the hearing.
3 On July 20, 2016, a notice of removal was filed with the United States District Court for the Middle District of Louisiana ( Middle District) ( which is not contained in this record but is referred to in other pleadings). Counsel for Coastal argued at the May 9, 2017 hearing that the entire case had been remanded from the Middle District and that the defendants were attempting to have Arkel dismissed, so that the remaining two defendants could return the case to the Middle District.
4 We note, however, that La. C. C.P. art. 933( A) provides, in pertinent part, " If the dilatory exception pleading prematurity is sustained, the premature action, claim, demand, issue or theory shall be dismissed." ( Emphasis added).
3 interim award on December 11, 2018, that contained certain findings. In
connection with the claims made by Coastal, the arbitrator found Coastal' s " Total
Cost Claim" to be unreasonable and denied Coastal' s claim of $972, 278. 72 for
Termination Costs." The arbitrator also found that Arkel did not unreasonably
withhold or delay payment to Coastal or breach the contract regarding payment to
Coastal. Therefore, the arbitrator denied the claims made by Coastal for payment
of penalties, interest and/ or attorneys' fees. On February 12, 2019, in his final
arbitration award, which incorporated the interim award, the arbitrator awarded
Arkel a total of $530, 574. 02 against Coastal ( final arbitration award). No award
was made to Coastal. The final arbitration award included the following language:
This Award is in full settlement of all claims and counterclaims submitted in this
Arbitration. All claims not expressly granted herein are hereby denied."
Following the final arbitration award, on February 15, 2019, Arkel filed a motion
to lift stay and confirm arbitration award ( motion to lift stay/ confirm award)
pursuant to La. R.S. 9: 42095. Coastal filed its own motion on March 14, 2019, to
vacate, correct, and/ or modify award of arbitrator and ex parte motion to stay
proceedings to enforce the award ( motion to vacate/ stay enforcement of award)
pursuant to La. R.S. 9: 4210 and La. R.S. 9: 4211. Both Coastal and Arkel opposed
the other party' s motion.
On May 6, 2019, a hearing was held on both Arkel' s motion to lift
stay/ confirm award and Coastal' s motion to vacate/ stay enforcement of award.
After arguments, the trial court took the matter under advisement. On May 20,
2019, the trial court ruled on both motions in open court and specifically ordered 5 Louisiana Revised Statute 9: 4209 provides:
At any time within one year after the award is made any party to the arbitration may apply to the court in and for the parish within which the award was made for an order confirming the award and thereupon the court shall grant such an order unless the award is vacated, modified, or corrected as prescribed in R. S. 9: 4210 and 9: 4211. Notice in writing of the application shall be served upon the adverse party or his attorney five days before the hearing thereof.
Free access — add to your briefcase to read the full text and ask questions with AI
STATE OF LOUISIANA
COURT OF APPEAL
FIRST CIRCUIT
2019 CA 1586
COASTAL INDUSTRIES, LLC
VERSUS
ll' ARKEL CONSTRUCTORS, LLC, SMITH LAROCK ARCHITECTURE P. C. AND THE LEFFLER GROUP CONSULTING STRUCTURAL ENGINEERS, INC.
SEP 212020 Judgment Rendered:
On Appeal from the Nineteenth Judicial District Court In and for the Parish of East Baton Rouge State of Louisiana Trial Court No. 649, 069
The Honorable Wilson Fields, Judge Presiding
Russel W. Wray Attorneys for Plaintiff/Appellant, Jacob A. Altmyer Coastal Industries, LLC St. Francisville, Louisiana
John C. Funderburk Attorneys for Defendant/ Appellee, Thomas D. Bourgeois, Jr. Arkel Constructors, LLC Baton Rouge, Louisiana
B FCS HI GINBOTHAM, PENZATO, AND LANIER, JJ. PENZATO, J.
Appellant, Coastal Industries, LLC, ( Coastal) appeals a trial court judgment
granting a motion to lift stay and confirming an arbitration award in favor of
appellee, Arkel Constructors, LLC (Arkel) and denying Coastal' s motion to vacate,
correct and/ or modify the award of the arbitrator and ex parte motion to stay
proceedings to enforce the award. For the reasons that follow, we dismiss the
appeal.
FACTS AND PROCEDURAL HISTORY
Coastal originally filed a petition for damages against Arkel, Smith LaRock
Architecture P. C. ( Smith LaRock), and The Leffler Group Consulting Engineers,
Inc., d/ b/ a The Leffler Group ( Leffler) on June 13, 2016. Coastal sought damages
from the three defendants arising from the construction of a building at the
Marathon Petroleum Company LP ( Marathon) plant in Garyville, Louisiana ( the
Project). Arkel, the general contractor, subcontracted with Coastal to perform
certain work ( the subcontract) at the site. Coastal alleged that Smith LaRock, the
architect, was engaged by Marathon to design the Project and that Smith LaRock
contracted with Leffler to perform the structural engineering work. Coastal
claimed that Arkel breached the subcontract resulting in damages. Coastal also
asserted that Smith LaRock and Leffler breached the standard of care owed to
Coastal by providing untimely and incorrect plans, specifications, and
modifications that interfered in Coastal' s work causing damages.
On July 20, 2016, Arkel filed a dilatory exception of prematurity and
alternative motion to stay and compel arbitration, claiming that Coastal' s claims
fell within the scope of an arbitration clause contained in the subcontract. Arkel
requested that Coastal' s claims be dismissed pursuant to the exception of
2 prematurity.' Leffler and Smith LaRock both answered Coastal' s suit and filed a
joint memorandum in support of Arkel' s exception of prematurity.
On May 9, 2017, the trial court held a hearing on Arkel' s exception of
prematurity, and all three defendants argued that Arkel should be dismissed on the 2 exception of prematurity. At the conclusion of the hearing, the trial court heard
arguments concerning whether Arkel should be dismissed pursuant to the
3 exception of prematurity and took the matter under advisement. On May 16,
2017, the trial court held another hearing to issue its ruling wherein it granted the
exception of prematurity, ordered the arbitration, and issued a stay of the
proceedings. The trial court clarified in open court that it was issuing a stay rather
than dismissing Coastal' s claims. The trial court signed an order on June 13, 2017,
reflecting its oral ruling, granting the exception of prematurity and staying all
claims of Coastal against Arkel and the remaining defendants pending arbitration
between Arkel and Coastal.' No claim or party was dismissed by the June 13,
2017 order.
Following the trial court' s order, Arkel and Coastal submitted to arbitration
with the American Arbitration Association, wherein Arkel answered the arbitration
demand and asserted a counterclaim against Coastal. The arbitrator issued an
Coastal had previously filed its own " Motion to Stay Proceedings Pending Arbitration," but later filed an ex parte motion to withdraw that motion, which the trial court granted on January 24, 2017.
2 The trial court originally held a hearing on Arkel' s exception of prematurity on March 20, 2017. After determining that Coastal would be allowed to offer expert testimony, the trial court rescheduled the hearing.
3 On July 20, 2016, a notice of removal was filed with the United States District Court for the Middle District of Louisiana ( Middle District) ( which is not contained in this record but is referred to in other pleadings). Counsel for Coastal argued at the May 9, 2017 hearing that the entire case had been remanded from the Middle District and that the defendants were attempting to have Arkel dismissed, so that the remaining two defendants could return the case to the Middle District.
4 We note, however, that La. C. C.P. art. 933( A) provides, in pertinent part, " If the dilatory exception pleading prematurity is sustained, the premature action, claim, demand, issue or theory shall be dismissed." ( Emphasis added).
3 interim award on December 11, 2018, that contained certain findings. In
connection with the claims made by Coastal, the arbitrator found Coastal' s " Total
Cost Claim" to be unreasonable and denied Coastal' s claim of $972, 278. 72 for
Termination Costs." The arbitrator also found that Arkel did not unreasonably
withhold or delay payment to Coastal or breach the contract regarding payment to
Coastal. Therefore, the arbitrator denied the claims made by Coastal for payment
of penalties, interest and/ or attorneys' fees. On February 12, 2019, in his final
arbitration award, which incorporated the interim award, the arbitrator awarded
Arkel a total of $530, 574. 02 against Coastal ( final arbitration award). No award
was made to Coastal. The final arbitration award included the following language:
This Award is in full settlement of all claims and counterclaims submitted in this
Arbitration. All claims not expressly granted herein are hereby denied."
Following the final arbitration award, on February 15, 2019, Arkel filed a motion
to lift stay and confirm arbitration award ( motion to lift stay/ confirm award)
pursuant to La. R.S. 9: 42095. Coastal filed its own motion on March 14, 2019, to
vacate, correct, and/ or modify award of arbitrator and ex parte motion to stay
proceedings to enforce the award ( motion to vacate/ stay enforcement of award)
pursuant to La. R.S. 9: 4210 and La. R.S. 9: 4211. Both Coastal and Arkel opposed
the other party' s motion.
On May 6, 2019, a hearing was held on both Arkel' s motion to lift
stay/ confirm award and Coastal' s motion to vacate/ stay enforcement of award.
After arguments, the trial court took the matter under advisement. On May 20,
2019, the trial court ruled on both motions in open court and specifically ordered 5 Louisiana Revised Statute 9: 4209 provides:
At any time within one year after the award is made any party to the arbitration may apply to the court in and for the parish within which the award was made for an order confirming the award and thereupon the court shall grant such an order unless the award is vacated, modified, or corrected as prescribed in R. S. 9: 4210 and 9: 4211. Notice in writing of the application shall be served upon the adverse party or his attorney five days before the hearing thereof.
M that the stay be lifted and the final arbitration award be confirmed.' On August 19,
2019, the trial court signed a judgment that lifted the stay, denied Coastal' s motion
to vacate/ stay enforcement of award, and granted Arkel' s motion to lift
stay/ confirm award. The August 19, 2019 judgment ( judgment) further entered
judgment in favor of Arkel and against Coastal for specific amounts as follows:
IT IS FURTHER ORDERED, ADJUDGED AND DECREED that the Motion to Lift Stay and Confirm Award is GRANTED, the Award is confirmed in all respects, and that judgment be entered in favor of Defendant, Arkel Constructors, LLC, and against Plaintiff, Coastal Industries, LLC in the amount of. $ 530, 574. 02 ( FIVE HUNDRED THIRTY THOUSAND FIVE HUNDRED SEVENTY-FOUR AND 02/ 100 DOLLARS) for the sum due in the Award; $ 14, 191. 40 FOURTEEN THOUSAND ONE HUNDRED [ NINETY] -ONE AND 40/ 100 DOLLARS) for additional attorney' s fees incurred by Arkel] to confirm the Award; $ 5, 785. 42 ( FIVE THOUSAND SEVEN HUNDRED EIGHTY-FIVE AND 42/ 100) for interest on 525, 292. 92 ( the total amount due in the Award excluding interest - awarded therein) from March 16, 2019 through May 21, 2019; and judicial interest on $ 525, 292. 92 ( the total amount due in the Award excluding interest therein) from May 22, 2019 until paid.
It is from this judgment that Coastal appeals.
LAW AND DISCUSSION
Appellate courts have a duty to examine subject matter jurisdiction sua
sponte, even when the parties do not raise the issue. Advanced Leveling &
Concrete Solutions v. Lathan Co., Inc., 2017- 1250 ( La. App. 1st Cir. 12/ 20/ 18),
268 So. 3d 1044, 1046 ( en banc). This court' s appellate jurisdiction extends only
to " final" judgments. See La. C. C.P. art. 2083( A); DeVance v. Tucker, 2018- 1440
La. App. 1st Cir. 5/ 31/ 19), 278 So. 3d 380, 382. Under Louisiana law, a final
judgment is one that determines the merits of a controversy in whole or in part.
La. C. C. P. art. 1841.
A valid judgment must be " precise, definite, and certain." Laird v. St.
Tammany Parish Safe Harbor, 2002- 0045 ( La. App. 1 st Cir. 12/ 20/ 02), 836 So. 2d
6 The judgment refers to the final arbitration award as being attached thereto as Exhibits 1 and 2 and incorporated and adopted therein. However, we note that there are no exhibits attached to the judgment in the record.
E 364, 365- 366. Moreover, a final appealable judgment must contain decretal
language, and it must name the party in favor of whom the ruling is ordered, the
party against whom the ruling is ordered, and the relief that is granted or denied.
See Carter v. Williamson Eye Center, 2001- 2016 ( La. App. 1st Cir. 11/ 27/ 02), 837
So. 2d 43, 44. These determinations should be evident from the language of a
judgment without reference to other documents in the record, such as pleadings
and reasons for judgment. Advanced Leveling, 268 So. 3d at 1046. Thus, a
judgment that does not contain decretal language cannot be considered as a final
judgment for the purpose of an immediate appeal, and this court lacks jurisdiction
to review such a judgment. See Johnson v. Mount Pilgrim Baptist Church, 2005-
0337 ( La. App. 1st Cir. 3/ 24/ 06), 934 So. 2d 66, 67.
The main demand in this proceeding is Coastal' s demand for an award of
damages against Arkel for breach of contract and against Smith LaRock and
Leffler for breach of the standard of care owed by an architect/ engineer. The
arbitration addressed the claims between Coastal and Arkel. The judgment at issue
confirmed the final arbitration award, which resolved all claims between Coastal
and Arkel, resulting in an award of $530, 574. 02 to Arkel and no award to Coastal.
The interim award specifically denied Coastal' s claims for termination costs,
penalties, interest and attorneys' fees. Further, as noted previously herein, the final
arbitration award provided that all claims not expressly granted were denied.
However, the judgment lacks decretal language dismissing the claims of Coastal
against Arkel. The judgment does not resolve Coastal' s original claim against
Arkel, as it did not dismiss these claims, notwithstanding the findings and
provisions of the interim and final arbitration awards. See Lehman v. Benasco,
2019- 0779 ( La. App. 1st Cir. 2/ 26/ 20), 2020 WL 913508, at * 2 ( unpublished)
judgment failed to indicate that all of plaintiff' s claims were dismissed and
extrinsic sources were required to make that determination).
0 In this case, the judgment confirms the final arbitration award of
530, 574. 02 to Arkel but does not dismiss Coastal' s original damage claims
against Arkel. Therefore, in the absence of appropriate decretal language, the
judgment is defective and cannot be considered a final judgment for purposes of
appeal. Thus, this court lacks appellate jurisdiction, and we must dismiss this
appeal. See Doctors for Women Medical Center, L.L. C. v. Breen, 2019- 0584 ( La.
App. 1st Cir. 6/ 1/ 20), 2020 WL 2832627, at * 3 ( unpublished).
We recognize that this court has discretion to convert an appeal of a non -
appealable judgment to an application for supervisory writs. See Stelluto v.
Stelluto, 2005- 0074 ( La. 6/ 29/ 05), 914 So. 2d 34, 39. However, there are
limitations on this grant of authority, as set forth in the jurisprudence. Best
Fishing, Inc. v. Rancatore, 96- 2254 ( La. App. 1st Cir. 12/ 29/ 97), 706 So. 2d 161,
166. In Herlitz Construction Company, Inc. v. Hotel Investors ofNew Iberia, Inc.,
396 So. 2d 878 ( La. 1981), the Louisiana Supreme Court directed appellate courts
to consider an application for supervisory writs under their supervisory
jurisdiction, even though relief may be ultimately available to the applicant on
appeal, when the trial court judgment is arguably incorrect, when a reversal would
terminate the litigation (in whole or in part), and when there is no dispute of fact to
be resolved.
When the jurisdictional defect lies in the non -finality of a judgment ( as
opposed to an appeal from an interlocutory judgment), an appellate court will
generally refrain from the exercise of its supervisory jurisdiction when an adequate
remedy exists by appeal. Mizell v. Willis, 2019- 0141 ( La. App. 1st Cir. 11/ 15/ 19),
290 So. 3d 247, 251 n. 3.; See Simon v. Ferguson, 2018- 0826 ( La. App. 1st Cir.
2/ 28/ 19), 274 So. 3d 10, 14. In such cases, an adequate remedy by appeal will
exist upon the entry of the requisite precise, definite, and certain decretal language
necessary for appellate review. Mizell, 290 So. 3d at 251 n. 3. Accordingly, we
7 decline to exercise our discretion to convert this appeal of a judgment that is not
final for lack of precise, definite, and certain decretal language, to an application
for supervisory writs. See Advanced Leveling, 268 So. 3d at 1046; Simon, 274 So.
3d at 14; Boyd Louisiana Racing, Inc. v. Bridges, 2015- 0393 ( La. App. 1 st Cir.
12/ 23/ 15), 2015 WL 9435285, * 3- 4 ( unpublished).
CONCLUSION
For the above and foregoing reasons, we dismiss Coastal Industries, LLC' s
appeal of the August 19, 2019 judgment. All costs in this matter are assessed to
Coastal Industries, LLC.
APPEAL DISMISSED.
n. STATE OF LOUISIANA
NO. 2019 CA 1586
ARKEL CONSTRUCTORS, LLC, SMITH LAROCK ARCHITECTURE P. C. J u` AND LEFFLER GROUP CONSULTING STRUCTURAL ENGINEERS, INC. SEP 2 2 2020
HIGGINBOTHAM, J., DISSENTS AND ASSIGNS REASONS.
I respectfully disagree with the decision of the majority to dismiss the appeal
for lack of appellate jurisdiction, and I would address the merits of the appeal. The
confirmation of an arbitration award is a summary proceeding that merely makes
what is already a final arbitration award a judgment of the court. St. George Fire
Prot. Dist. No. 2 v. J. Reed Constructors, Inc., 2017- 1006 ( La. App. 1st Cir.
2/ 20/ 18), 243 So. 3d 145, 150. The pleadings before the district court in this matter
were Arkel' s motion to confirm the arbitration award, and Coastal' s motion to
vacate, correct, and/ or modify the award of the arbitrator. The August 19, 2019
judgment clearly denies Coastal' s motion to vacate the award and grants Arkel' s
motion to confirm the award " in all respects." This judgment contains the proper
decretal language, named the party in whose favor the judgment was rendered, the
party against whom the judgment was rendered, and the relief that was granted. See La. Code Civ. P. art. 1918. The judgment also addressed the merits of a controversy
and resolved all claims between Arkel and Coastal. Therefore, the judgment is a final
appealable judgment, and this court has subject matter jurisdiction on appeal. See
La. Code Civ. P. art. 1841. For these reasons, I respectfully dissent.