Coastal Industries, LLC v. Arkel Constructors, LLC; Smith LaRock Architecture P.C. and the Leffler Group Consulting Structural Engineers, Inc.

CourtLouisiana Court of Appeal
DecidedSeptember 21, 2020
Docket2019CA1586
StatusUnknown

This text of Coastal Industries, LLC v. Arkel Constructors, LLC; Smith LaRock Architecture P.C. and the Leffler Group Consulting Structural Engineers, Inc. (Coastal Industries, LLC v. Arkel Constructors, LLC; Smith LaRock Architecture P.C. and the Leffler Group Consulting Structural Engineers, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coastal Industries, LLC v. Arkel Constructors, LLC; Smith LaRock Architecture P.C. and the Leffler Group Consulting Structural Engineers, Inc., (La. Ct. App. 2020).

Opinion

STATE OF LOUISIANA

COURT OF APPEAL

FIRST CIRCUIT

2019 CA 1586

COASTAL INDUSTRIES, LLC

VERSUS

ll' ARKEL CONSTRUCTORS, LLC, SMITH LAROCK ARCHITECTURE P. C. AND THE LEFFLER GROUP CONSULTING STRUCTURAL ENGINEERS, INC.

SEP 212020 Judgment Rendered:

On Appeal from the Nineteenth Judicial District Court In and for the Parish of East Baton Rouge State of Louisiana Trial Court No. 649, 069

The Honorable Wilson Fields, Judge Presiding

Russel W. Wray Attorneys for Plaintiff/Appellant, Jacob A. Altmyer Coastal Industries, LLC St. Francisville, Louisiana

John C. Funderburk Attorneys for Defendant/ Appellee, Thomas D. Bourgeois, Jr. Arkel Constructors, LLC Baton Rouge, Louisiana

B FCS HI GINBOTHAM, PENZATO, AND LANIER, JJ. PENZATO, J.

Appellant, Coastal Industries, LLC, ( Coastal) appeals a trial court judgment

granting a motion to lift stay and confirming an arbitration award in favor of

appellee, Arkel Constructors, LLC (Arkel) and denying Coastal' s motion to vacate,

correct and/ or modify the award of the arbitrator and ex parte motion to stay

proceedings to enforce the award. For the reasons that follow, we dismiss the

appeal.

FACTS AND PROCEDURAL HISTORY

Coastal originally filed a petition for damages against Arkel, Smith LaRock

Architecture P. C. ( Smith LaRock), and The Leffler Group Consulting Engineers,

Inc., d/ b/ a The Leffler Group ( Leffler) on June 13, 2016. Coastal sought damages

from the three defendants arising from the construction of a building at the

Marathon Petroleum Company LP ( Marathon) plant in Garyville, Louisiana ( the

Project). Arkel, the general contractor, subcontracted with Coastal to perform

certain work ( the subcontract) at the site. Coastal alleged that Smith LaRock, the

architect, was engaged by Marathon to design the Project and that Smith LaRock

contracted with Leffler to perform the structural engineering work. Coastal

claimed that Arkel breached the subcontract resulting in damages. Coastal also

asserted that Smith LaRock and Leffler breached the standard of care owed to

Coastal by providing untimely and incorrect plans, specifications, and

modifications that interfered in Coastal' s work causing damages.

On July 20, 2016, Arkel filed a dilatory exception of prematurity and

alternative motion to stay and compel arbitration, claiming that Coastal' s claims

fell within the scope of an arbitration clause contained in the subcontract. Arkel

requested that Coastal' s claims be dismissed pursuant to the exception of

2 prematurity.' Leffler and Smith LaRock both answered Coastal' s suit and filed a

joint memorandum in support of Arkel' s exception of prematurity.

On May 9, 2017, the trial court held a hearing on Arkel' s exception of

prematurity, and all three defendants argued that Arkel should be dismissed on the 2 exception of prematurity. At the conclusion of the hearing, the trial court heard

arguments concerning whether Arkel should be dismissed pursuant to the

3 exception of prematurity and took the matter under advisement. On May 16,

2017, the trial court held another hearing to issue its ruling wherein it granted the

exception of prematurity, ordered the arbitration, and issued a stay of the

proceedings. The trial court clarified in open court that it was issuing a stay rather

than dismissing Coastal' s claims. The trial court signed an order on June 13, 2017,

reflecting its oral ruling, granting the exception of prematurity and staying all

claims of Coastal against Arkel and the remaining defendants pending arbitration

between Arkel and Coastal.' No claim or party was dismissed by the June 13,

2017 order.

Following the trial court' s order, Arkel and Coastal submitted to arbitration

with the American Arbitration Association, wherein Arkel answered the arbitration

demand and asserted a counterclaim against Coastal. The arbitrator issued an

Coastal had previously filed its own " Motion to Stay Proceedings Pending Arbitration," but later filed an ex parte motion to withdraw that motion, which the trial court granted on January 24, 2017.

2 The trial court originally held a hearing on Arkel' s exception of prematurity on March 20, 2017. After determining that Coastal would be allowed to offer expert testimony, the trial court rescheduled the hearing.

3 On July 20, 2016, a notice of removal was filed with the United States District Court for the Middle District of Louisiana ( Middle District) ( which is not contained in this record but is referred to in other pleadings). Counsel for Coastal argued at the May 9, 2017 hearing that the entire case had been remanded from the Middle District and that the defendants were attempting to have Arkel dismissed, so that the remaining two defendants could return the case to the Middle District.

4 We note, however, that La. C. C.P. art. 933( A) provides, in pertinent part, " If the dilatory exception pleading prematurity is sustained, the premature action, claim, demand, issue or theory shall be dismissed." ( Emphasis added).

3 interim award on December 11, 2018, that contained certain findings. In

connection with the claims made by Coastal, the arbitrator found Coastal' s " Total

Cost Claim" to be unreasonable and denied Coastal' s claim of $972, 278. 72 for

Termination Costs." The arbitrator also found that Arkel did not unreasonably

withhold or delay payment to Coastal or breach the contract regarding payment to

Coastal. Therefore, the arbitrator denied the claims made by Coastal for payment

of penalties, interest and/ or attorneys' fees. On February 12, 2019, in his final

arbitration award, which incorporated the interim award, the arbitrator awarded

Arkel a total of $530, 574. 02 against Coastal ( final arbitration award). No award

was made to Coastal. The final arbitration award included the following language:

This Award is in full settlement of all claims and counterclaims submitted in this

Arbitration. All claims not expressly granted herein are hereby denied."

Following the final arbitration award, on February 15, 2019, Arkel filed a motion

to lift stay and confirm arbitration award ( motion to lift stay/ confirm award)

pursuant to La. R.S. 9: 42095. Coastal filed its own motion on March 14, 2019, to

vacate, correct, and/ or modify award of arbitrator and ex parte motion to stay

proceedings to enforce the award ( motion to vacate/ stay enforcement of award)

pursuant to La. R.S. 9: 4210 and La. R.S. 9: 4211. Both Coastal and Arkel opposed

the other party' s motion.

On May 6, 2019, a hearing was held on both Arkel' s motion to lift

stay/ confirm award and Coastal' s motion to vacate/ stay enforcement of award.

After arguments, the trial court took the matter under advisement. On May 20,

2019, the trial court ruled on both motions in open court and specifically ordered 5 Louisiana Revised Statute 9: 4209 provides:

At any time within one year after the award is made any party to the arbitration may apply to the court in and for the parish within which the award was made for an order confirming the award and thereupon the court shall grant such an order unless the award is vacated, modified, or corrected as prescribed in R. S. 9: 4210 and 9: 4211. Notice in writing of the application shall be served upon the adverse party or his attorney five days before the hearing thereof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carter v. Williamson Eye Center
837 So. 2d 43 (Louisiana Court of Appeal, 2002)
Best Fishing, Inc. v. Rancatore
706 So. 2d 161 (Louisiana Court of Appeal, 1997)
Herlitz Const. Co., Inc. v. Hotel Investors of New Iberia, Inc.
396 So. 2d 878 (Supreme Court of Louisiana, 1981)
Lanthier v. Family Dollar Store
836 So. 2d 5 (Supreme Court of Louisiana, 2002)
Johnson v. Mount Pilgrim Baptist Church
934 So. 2d 66 (Louisiana Court of Appeal, 2006)
Stelluto v. Stelluto
914 So. 2d 34 (Supreme Court of Louisiana, 2005)
St. George Fire Prot. Dist. No. 2 v. J. Reed Constructors, Inc.
243 So. 3d 145 (Louisiana Court of Appeal, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Coastal Industries, LLC v. Arkel Constructors, LLC; Smith LaRock Architecture P.C. and the Leffler Group Consulting Structural Engineers, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/coastal-industries-llc-v-arkel-constructors-llc-smith-larock-lactapp-2020.