Coakley & Williams Construction, Incorporated v. Structural Concrete Equipment, Incorporated

973 F.2d 349, 1992 U.S. App. LEXIS 19414, 1992 WL 201065
CourtCourt of Appeals for the Fourth Circuit
DecidedAugust 21, 1992
Docket91-1214
StatusPublished
Cited by118 cases

This text of 973 F.2d 349 (Coakley & Williams Construction, Incorporated v. Structural Concrete Equipment, Incorporated) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coakley & Williams Construction, Incorporated v. Structural Concrete Equipment, Incorporated, 973 F.2d 349, 1992 U.S. App. LEXIS 19414, 1992 WL 201065 (4th Cir. 1992).

Opinion

OPINION

ERVIN, Chief Judge:

In 1991, Coakley & Williams, Inc. (C & W) sued Structural Concrete Equipment, Inc. (SCE) for fraudulent and negligent inducement involving the construction of a Days Inn in Timonium, Maryland. In 1989, the parties had reached a settlement and released all claims arising out of a previous lawsuit involving the same construction project. Without holding a hearing, the district court found that the parties intended the previous release to bar the fraudulent and negligent inducement claims and granted summary judgment in favor of SCE. C & W appeals, arguing that the district court erred either in not holding a hearing or in granting summary judgment. We affirm.

I

This dispute dates back to 1988 and the construction of a Days Inn. C & W was the general contractor, and SCE' contracted to construct the cast-in-place structural concrete work. SCE recommended that C & W subcontract'the work to Superior Contractors, Inc., and C & W did. Superior and SCE were closely related, as the same man was president of both companies. C & W dismissed Superior from the job site on May 26, 1988. It is not clear from the record exactly why C & W did so, but it appears that Superior either was not performing the work as required or was not financially sound. After C & W dismissed Superior, SCE sued C & W, claiming that C & W had converted the concrete forms Superior had leased from SCE. C & W counterclaimed for trespass.

On June 12, 1989, C & W wrote a settlement offer to SCE. The C & W settlement offer stated:

Without prejudice, and to settle all disputes between the parties, Coakley & Williams Construction Co., Inc. will pay Structural Concrete Equipment, Inc. the sum of $47,500.00. The parties would enter into a mutual release reserving only any claims which either Structural or Coakley may have against Superior. An order of dismissal with prejudice would be signed by counsel and filed with the court.
*351 ... [FJurther discovery in this case by way of depositions will do little to enhance the likelihood of your client recovering substantial monies. On the other hand, additional discovery may well enhance the likelihood of Coakley demonstrating at trial the relationship now perceived to exist between Superior and Structural.

J.A. at 87-88.

Soon after this offer, on June 23, 1989, the parties reached a settlement agreement and released future claims against each other. The settlement agreement first stated that C & W would pay SCE $52,000. The agreement next provided that C & W and SCE would file a Stipulation of Dismissal with Prejudice. Next was the release provision, which the parties focus on in this appeal:

STRUCTURAL and COAKLEY, do hereby mutually release ... all claims ... and demands whatsoever, in law or equity, which STRUCTURAL and COAK-LEY ever had, now have or hereinafter can, shall, or may have against one another for, upon, or by reason of any matter, cause or thing whatsoever, from the beginning of the world to and including the day of the date of this release, [next the parties deleted the words “including, without limitation, all claims”] arising out of the Complaint, First Amended Complaint and Counterclaim filed in the above litigation. PROVIDED, HOWEVER, that the mutual release as stated in this paragraph is not intended to, and shall not, release or impair the specific undertakings agreed to by STRUCTURAL and COAKLEY in this Settlement Agreement; and the release shall not, and is not intended to, release or impair any claim that either STRUCTURAL or COAKLEY ever had, now have, or hereinafter may have against Superior Contractors, Inc.

J.A. at 79-80. Two provisions later, the agreement stated that it was “intended to avoid further litigation.” After the parties reached this settlement agreement, the district court entered an order dismissing the case with prejudice.

Two years later, on June 14,1991, C & W sued SCE for fraudulent and negligent inducement. C & W sought $700,000 in compensatory damages and $250,000 in punitive damages. The basis for this action was SCE’s alleged misrepresentations that induced C & W to award the subcontract for concrete formwork to Superior. Requesting a hearing, SCE moved the district court either to dismiss C & W’s complaint or grant summary judgment in SCE’s favor, raising four alternative grounds for granting the motion: the previous release, the statute of limitations, the compulsory counterclaim rule, and res judicata. The district court decided the motion without a hearing, treated it as a motion for summary judgment, and granted summary judgment in SCE’s favor on the basis of the previous release without addressing SCE’s other arguments. The district court reasoned:

Even though the release is worded in terms of matters and causes of action “arising out of the Complaint, First Amended Complaint and Counterclaim filed in the above-captioned litigation,” it is this Court’s opinion that the intent of the parties in entering into it ..., twice expressed therein as an intent to “avoid further litigation,” was to settle all claims the parties had against each other arising out of the Days Inn job, whether they had yet been pleaded or not.
The parties’ intent was made manifest in the [settlement offer]_

J.A. at 197. C & W appeals from the district court’s entry of summary judgment.

II

The first issue in this case is whether the district court erred in ruling on SCE’s motion for summary judgment without holding a hearing. C & W argues that “there is a division of authority as to whether a motion for summary judgment may be granted without affording a hearing. The Fourth Circuit does not appear to have specifically ruled on this point....” Appellant’s Brief at 25 (emphasis added). While we have not found a Fourth Circuit case that is identical to this one, there is *352 closely analogous precedent in this circuit. See United States Fidelity and Guaranty Co. v. Lawrenson, 334 F.2d 464, 466-67 (4th Cir.), cert. denied, 379 U.S. 869, 85 S.Ct. 141, 13 L.Ed.2d 71 (1964). In Lawrenson, this court considered the same local Maryland district court rule applied here. 1 The court stated:

The district court interpreted the rule to mean that while motions “will automatically be decided on the memoranda filed unless the court or either side requests a hearing, it is still within the discretion of the court to grant or refuse a request for a hearing.” A court is, of course, the best judge of its own rules. But even more importantly, rule 78 of the Federal Rules of Civil Procedure, the source of authority for [the local rule], makes it clear that hearings on motions are to be in the discretion of the district courts....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Small v. United States
S.D. West Virginia, 2024
Mullins v. United States
S.D. West Virginia, 2024
Dale v. United States
S.D. West Virginia, 2024
Muncy v. United States
S.D. West Virginia, 2024
Bragg v. United States
S.D. West Virginia, 2024
Abner v. United States
S.D. West Virginia, 2024
Hogie v. United States
S.D. West Virginia, 2024
Kleintop v. United States
S.D. West Virginia, 2024
Cozort v. United States
S.D. West Virginia, 2024
Fedak v. United States
S.D. West Virginia, 2024
Neely v. United States
S.D. West Virginia, 2024
Blackburn v. United States
S.D. West Virginia, 2024
Marcum v. United States
S.D. West Virginia, 2024
Cain v. United States
S.D. West Virginia, 2024
Douglas v. United States
S.D. West Virginia, 2024
Sanford v. United States
S.D. West Virginia, 2024
Carter v. United States
S.D. West Virginia, 2024
Simmons v. United States
S.D. West Virginia, 2024
Bowling v. United States
S.D. West Virginia, 2024
Robinson v. United States
S.D. West Virginia, 2024

Cite This Page — Counsel Stack

Bluebook (online)
973 F.2d 349, 1992 U.S. App. LEXIS 19414, 1992 WL 201065, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coakley-williams-construction-incorporated-v-structural-concrete-ca4-1992.