Cms Trunkline Gas Co., LLC v. State of La, Thru the Dotd

CourtLouisiana Court of Appeal
DecidedApril 2, 2008
DocketCA-0007-1390
StatusUnknown

This text of Cms Trunkline Gas Co., LLC v. State of La, Thru the Dotd (Cms Trunkline Gas Co., LLC v. State of La, Thru the Dotd) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cms Trunkline Gas Co., LLC v. State of La, Thru the Dotd, (La. Ct. App. 2008).

Opinion

STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT

CA 07-1390

CMS TRUNKLINE GAS CO., LLC, ET AL.

VERSUS

STATE OF LA, THROUGH THE DOTD

**********

APPEAL FROM THE NINTH JUDICIAL DISTRICT COURT PARISH OF RAPIDES, NO. 211,534 HONORABLE JOHN C. DAVIDSON, DISTRICT JUDGE

JOHN D. SAUNDERS JUDGE

Court composed of Ulysses Gene Thibodeaux, Chief Judge, John D. Saunders, and Glenn B. Gremillion, Judges.

AFFIRMED.

Bernard Lindes Knobloch, Jr. Attorney at Law P. O. Box 94245 Baton Rouge, LA 70804 (225) 237-1341 Counsel for Defendant/Appellee: State of LA, Thru The DOTD

Christopher J. Guillory The Gray Law Firm, APLC P. O. Box 1467 Lake Charles, LA 70602-1467 (337) 494-0694 Counsel for Plaintiffs/Appellants: CMS Trunkline Gas Co., LLC Centennial Pipeline, LLC SAUNDERS, Judge.

This is a case wherein a pipeline company is attempting to recoup costs it

incurred to relocate three of its pipelines from the State of Louisiana, through the

Department of Transportation and Development (DOTD). The three pipelines were

constructed beneath Highway 28 in Rapides Parish and had to be relocated because

of a DOTD project to widen the highway. The permit granted to the pipeline company

contained the condition that should the DOTD require the pipelines to be relocated

due to a widening of the highway, their relocation would be done at the expense of

the pipeline company.

While the pipeline company concedes that it must pay for the relocations

within the DOTD’s right of way, it claims that the DOTD should pay its costs in

relocating the parts of the pipelines originally located outside the DOTD’s right of

way that it had to move to different locations outside the DOTD right of way in order

for the pipelines to function properly.

The trial court ruled in favor of the DOTD. The pipeline company appealed.

We affirm.

FACTS AND PROCEDURAL HISTORY:

The facts relevant to this case are undisputed. This case involves a claim by

CMS Trunkline Gas Company, L.L.C., and Centennial Pipeline, L.L.C. (collectively

“Trunkline”) against the DOTD. Trunkline is attempting to recoup the costs of

relocating its three pipelines that cross Gardner-Alexandria Highway 28 in Rapides

Parish. Trunkline was issued a permit to construct each of these pipelines from the

Louisiana Department of Highways, predecessor of the DOTD.

Relocation of the three pipelines beneath Highway 28 was necessitated by a the

DOTD highway widening project. Prior to beginning the project, DOTD requested that Trunkline relocate its three pipelines by burying them deeper. After reserving its

rights to seek reimbursement, Trunkline complied with the request.

Trunkline acknowledges that to the extent its pipelines were within the DOTD

right of way, it must bear the expenses incurred in relocating the three pipelines to

locations within the said right of way. However, as to the portions of the three

pipelines that were located outside the DOTD’s right of way that must be relocated

due to Trunkline burying the pipelines deeper as per the DOTD request, Trunkline

contends that it is entitled to recoup all relevant expenses incurred. DOTD disagreed,

contending that it had no financial responsibility for the costs associated with the

relocation of the three pipelines per the clear language of the permit its predecessor

granted to Trunkline.

A trial of this matter was held on May 15, 2007. In its written reasons dated

June 14, 2007, the trial court did not render any opinion with respect to whether

Trunkline could recoup its relocation costs incurred for the pipeline relocations

insofar as they were outside the DOTD’s right of way. After ruling in favor of DOTD

that a portion of the right of way had not prescribed due to non-use, the trial court

incorrectly stated that the “entire relocation took place within the 350 foot right of

way granted to (the DOTD).”

Trunkline filed a motion for new trial on June 21, 2007, contending that the

judgment of the trial court was clearly contrary to the law and evidence. A hearing on

the motion was held on August 13, 2007. On August 14, 2007, the trial court issued

its written reasons, denying Trunkline’s motion for new trial. In its written reasons,

the trial court held that so long as the DOTD did not acquire additional right of way,

it did not owe compensation to Trunkline for its relocation costs. Trunkline appealed

2 alleging one issue presented for review.

ISSUE PRESENTED FOR REVIEW:

Trunkline presented the following issue for review:

Is a natural gas pipeline company entitled to recover expenses it incurred to relocate its pipelines outside a public entity’s right-of-way, when said pipeline relocations are solely necessitated by actions taken by the public entity within the public entity’s right-of-way, and when said pipeline relocations are demanded by the public entity without just compensation?

DISCUSSION OF THE MERITS:

Trunkline argues that under the facts of this case before us, it is entitled to

recover expenses it incurred to relocate its pipelines from their original location

outside the DOTD’s right-of-way, to another location, also outside of the DOTD’s

right-of-way. For the following reasons, we do not agree.

“If the words of a contact are clear, explicit, and lead to no absurd results, it

must be interpreted by reference to the ‘four corners’ of the document and no further

interpretation can occur in search of the parties’ intent.” Hebert v. Ins. Ctr., Inc., 97-

298, p.5 (La.App. 3 Cir. 1/7/98), 706 So.2d 1007, writ denied, 98-353 (La. 3/27/98),

716 So.2d 888; (La.Civ.Code art. 2046.)

Each permit given to Trunkline contained the following provision:

SECOND: That all fixtures and appurtenances thereto, after having been erected, shall at all times be subject to inspection and the right is reserved to require such changes, additions, repairs, relocations and removal as may at anytime be considered necessary to permit the relocation, reconstruction, widening and maintaining of the highway and to provide proper safe protection to life and property on or adjacent to the highway, or in the interest of safety to traffic on the highway, and that the cost of making such changes, additions, repairs and relocations shall be borne by the applicant. (Emphasis added.)

The language of the permit is clear. All pipelines that have been erected are

subject to the DOTD specifically reserving the right to require relocations considered

3 necessary to widen the highway. The cost of those relocations are to be paid by

Trunkline.

The trial court found Tenneco Oil Co. v. Board of Commissioners for the Lake

Borgne Basin Levee District, 567 So.2d 113 (La.App. 4 Cir.), writ denied, 569 So.2d

989 (La.1990), to be on point. The Tenneco Oil case provided that compensation in

a situation such as this is due only for destruction of improvements located in any

additional servitude taken by the public entity. Trunkline argues that the reasoning

of Tenneco Oil sets forth an improper and unnecessary hurdle to just compensation

and that the cases cited therein had no such obstacle. We find no error in the trial

court’s application of Tenneco Oil to the case at bar.

Highway 28 was in existence prior to Trunkline requesting a permit from the

DOTD to pass beneath it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hebert v. Insurance Center, Inc.
706 So. 2d 1007 (Louisiana Court of Appeal, 1998)
Tenneco Oil Co. v. Board of Com'rs
567 So. 2d 113 (Louisiana Court of Appeal, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
Cms Trunkline Gas Co., LLC v. State of La, Thru the Dotd, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cms-trunkline-gas-co-llc-v-state-of-la-thru-the-dotd-lactapp-2008.