Cluett, Peabody & Co. v. Campbell, Rea, Hayes & Large

492 F. Supp. 67, 1980 U.S. Dist. LEXIS 13774
CourtDistrict Court, M.D. Pennsylvania
DecidedJanuary 31, 1980
DocketCiv. 74-803
StatusPublished
Cited by8 cases

This text of 492 F. Supp. 67 (Cluett, Peabody & Co. v. Campbell, Rea, Hayes & Large) is published on Counsel Stack Legal Research, covering District Court, M.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cluett, Peabody & Co. v. Campbell, Rea, Hayes & Large, 492 F. Supp. 67, 1980 U.S. Dist. LEXIS 13774 (M.D. Pa. 1980).

Opinion

MEMORANDUM AND ORDER

NEALON, Chief Judge.

This matter comes before the court on defendants’ summary judgment motions. Plaintiff, Cluett, Peabody & Co., Inc. (Cluett), seeks the cost of replacing the roof on a warehouse that it had formerly leased. Defendants, the architect, general contractor and roofing contractor involved in building the warehouse, contend (a) that the applicable statute of limitations bars this suit, and (b) that the real party in interest on any claim for the cost of replacing the allegedly defective roof is not the tenant of the warehouse, Cluett, but its owner, the *69 Shamokin Area Industrial Corporation (SAIC). 1

Defendants’ motions will be granted in part and denied in part. I conclude that plaintiff’s claims concerning the construction of the roof had accrued more than six years prior to the commencement of this action and are therefore barred by the Pennsylvania six year statute of limitations, Pa.Stat.Ann. tit. 12, § 31 (1953) (Purdon). 2 Plaintiff’s claim that the roof must be replaced because defendants failed to exercise reasonable care in attempting to repair the roof, however, accrued less than six years prior to the institution of this law suit and is therefore timely. Finally, since under the lease Cluett was obligated to replace the roof, it is a real party in interest to this action. 3

I. THE FACTS

On August 19, 1965, Cluett and SAIC executed a written 20 year lease for a tract of land situated in Ralpho Township, Northumberland County, Pennsylvania. Under the terms of the lease SAIC agreed to construct by September 1, 1966 a warehouse containing approximately 250,000 square feet of floor space. (Sections 1.1 and 2.2 of the Lease) In addition to payment of rent, Cluett agreed, inter alia, to maintain the warehouse and leased realty and “make all necessary repairs, interior and exterior, structural and non-structural, ordinary and extraordinary, foreseen and unforeseen.” (Section 6.1 of the Lease)

The warehouse to be leased by Cluett was designed by defendant Campbell, Rea, Hayes & Large (hereinafter referred to as the architect). Under the terms of the agreement with SAIC dated April 22, 1965, the architect undertook to perform for SAIC professional services “consistpng] of the necessary conferences, the preparation of preliminary studies, working drawings, specifications, large scale and full size detail drawings for architectural, structural, plumbing, heating, electrical, and other mechanical work; assistance in the drafting of forms of proposals and contracts; the issuance of Certificates of Payment; the keeping of accounts, the general administration of the construction contracts, and supervision of the work.” (Article 1 of the Architect’s Contract) In consideration for the performance of such services SAIC agreed to pay the architect in installments a basic fee amounting to 4 percent of the cost of the project. (Article 3 of the Architect’s Contract) The architect’s contract did not specify a date on which the architect would be released from his contractual commitments.

The contract for the general construction work on the warehouse, which included construction of the roof, was let on August 27, 1965 to defendant C. F. King, Inc. (hereinafter referred to as the general contractor). Under the terms of this agreement, the general construction work was to be completed by February 1,1966, unless the architect granted an extension of time, (Article 2 of the general contractor’s agreement) and the general contractor was obligated to remedy any defects due to faulty materials *70 or workmanship that appeared within one year from either the date of final payment or the date of substantial usage or occupancy of the warehouse, whichever was earlier. 4 (Article 20 of the General Conditions, incorporated by reference into the general contractor’s agreement) Payments to the general contractor were to be made under “certificates for payments” issued periodically by the architect upon application by the general contractor. No termination date was set out in the general contractor’s agreement.

The general contractor on September 15, 1965 sub-let the construction of the warehouse roof to defendant Long Service Co., Inc. (hereinafter referred to as the roofing contractor). This agreement provided, inter alia, that “guarantees on sheet metal work and on all types of roofing . are limited to one year from date of completion.” The roofing contractor was to be paid on a monthly basis with the final payments due thirty days from completion of the roofing sub-contractor’s work. This agreement, like the architect’s and general contractor’s, contained no termination date.

The roof designed for the Cluett warehouse, sometimes described by the parties as a built-up roof, was constructed in layers. The bottom layer was a ribbed or fluted steel deck. A thin plastic-like sheet or vapor barrier made by third-party defendant Lexsuco was anchored to the roof deck by an adhesive also manufactured by Lexsuco. One and one-half inch thick fiberglas roof insulation, a product of third-party defendant Owens-Corning, was attached to the vapor barrier by the Lexsuco adhesive. Steep asphalt was then applied on top of the first layer of insulation board and a second layer of fiberglas roof insulation was laid. A layer of asphalt was placed on top of the insulation board and four layers of felt, a product of third-party defendant Certain-Teed, were then applied. Coal tar pitch was spread between each layer of felt and on top of the last layer of felt. The last layer of coal tar pitch was covered with gravel. The roof was constructed in six sections with each section separated by an expansion joint.

The roofing contractor completed its construction work on the built-up roof on March 24, 1966 and the certificate of final payment was issued on September 12, 1966. (Lexsuco-Farrow deposition Ex. No. 2) Money was retained from the general contractor, however, until January of 1968 (Farrow, pp. 44 — 46, 139-143) 5 and the roofing contractor did not receive final payment on its agreement until January 19, 1968. (Long, Sr., pp. 14-15)

This money had been withheld because of problems with the roof. (Farrow, pp. 44-46) Almost immediately after Cluett occupied the building in May or June of 1966 (Farrow, p. 19) the roof began to leak and blister. (Stanner, pp. 7, 8 and 12). The problems of leaks and blistering were known by a number of Cluett employees. Edward Stanner, employed in the Cluett maintenance department, observed roof leaks in various sections of the warehouse every time it rained in 1966 and reported all such leaks to Donald Turley, Cluett plant engineer and Stanner’s superior. (Stanner, pp. 7-14) In August of 1966, Turley received authorization to meet with representatives of the defendants and to inspect the roof to determine the source of the leaks. (Bannon, pp. 29-32). Turley observed that in 1966 most of the leaks were located near smoke vents installed in the roof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wiseman Oil Co. v. TIG Insurance
878 F. Supp. 2d 597 (W.D. Pennsylvania, 2012)
Caln Village Associates, LP v. Home Indem. Co.
75 F. Supp. 2d 404 (E.D. Pennsylvania, 1999)
Moyer v. White
48 Pa. D. & C.3d 487 (Dauphin County Court of Common Pleas, 1988)
Dillon County School District Number Two v. Lewis Sheet Metal Works, Inc.
332 S.E.2d 555 (Court of Appeals of South Carolina, 1985)
Hench v. Carpenter
35 Pa. D. & C.3d 401 (Perry County Court of Common Pleas, 1985)
Pittsburgh National Bank v. Welton Becket Associates
601 F. Supp. 887 (W.D. Pennsylvania, 1985)
National Housing Partnership v. Barness
38 Pa. D. & C.3d 544 (Bucks County Court of Common Pleas, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
492 F. Supp. 67, 1980 U.S. Dist. LEXIS 13774, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cluett-peabody-co-v-campbell-rea-hayes-large-pamd-1980.