Close v. Isbell Construction Co.

471 P.2d 257, 86 Nev. 524, 1970 Nev. LEXIS 558
CourtNevada Supreme Court
DecidedJune 24, 1970
DocketNo. 6013
StatusPublished
Cited by16 cases

This text of 471 P.2d 257 (Close v. Isbell Construction Co.) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Close v. Isbell Construction Co., 471 P.2d 257, 86 Nev. 524, 1970 Nev. LEXIS 558 (Neb. 1970).

Opinion

[525]*525OPINION

By the Court,

Collins, C. J.:

This is an appeal from a judgment in favor of respondent (plaintiff below) and from an order denying appellant’s motion to alter and amend that judgment. We affirm in all respects.

Appellant, Helen Close, owned a parcel of land in Reno upon which she desired to construct a trailer park. Respondent, Isbell Construction Co., on April 24, 1965, submitted a bid form to Close for that work, proposing to furnish labor and materials in accordance with written specifications, for a lump sum of $96,586.85. Close, in writing, accepted the bid. Additional or extra work was done by Isbell for Close on her written order. On October 18, 1965, Isbell billed Close for $131,019.07, to which she objected. A conference was held, and on November 15, 1965, the billing was reduced to $119,-750.

Close failed to pay the latter sum, and on January 26, 1966, Isbell filed a mechanics lien in the recorder’s office. Close was served a copy the next day. Isbell filed suit on February 7, 1966. Close counterclaimed, alleging Isbell had failed to perform the terms of their agreement in a diligent, skillful, and workmanlike manner; that she lost rentals because the trailer spaces were not ready when agreed; that she suffered further loss because Isbell’s lack of diligence disrupted the work of other contractors on the project. Close sought damages amounting to $97,573.59.

The Isbell claim and the Close counterclaim were tried [526]*526before a jury, which, on May 15, 1968, returned verdicts in favor of Isbell for $119,750 (the exact sum of the November 15 billing) and in favor of Close on her counterclaim for $62,690.96, or a net verdict in Isbell’s favor of $57,059.04.

On October 16, 1968, after considering briefs on the issue from both parties, the lower court made an award of interest as of November 15, 1965, on the net judgment.

A motion by Close for award of an attorney’s fee against Isbell on the ground she was the prevailing party in the foreclosure of the mechanics lien issue was denied by the lower court on October 25, 1968, and judgment was entered on November 20, 1968.

On December 2, 1968, Close filed a motion to alter or amend judgment on the grounds that the judgment was for money due under a contract while Isbell had based its action on quantum meruit and had also failed to perfect its mechanics lien. On December 13, 1968, she moved to discharge the mechanics lien on the ground that the judgment awarded Isbell only a personal judgment against Close. Isbell countered the foregoing motions March 27, 1969, and moved to foreclose the mechanics lien. On May 14, 1969, the court below denied Close’s motion to alter and amend the judgment and granted Isbell leave to amend the judgment to provide for enforcement of it under the mechanics lien provisions, denied Close’s motion to discharge the mechanics lien, and denied Isbell’s motion to foreclose the lien for the reason that it had been within the issues and pleadings and no specific ruling thereon was deemed necessary.

The issues presented for our decision are these:

I. Whether the trial court properly awarded interest on its judgment from November 15, 1965, the date of the last billing?

II. Whether respondent properly perfected and proved its right to a mechanics’ lien?

III. Whether attorney fees should have been awarded to appellant because she was the prevailing party?

1. Appellant contends the court below erred in allowing interest, for the reasons that the sum was not liquidated until the jury made its award May 15, 1965, and, because respondent only alleged an action in quantum meruit and not an action based on a contract, the amount due was not definitely ascertainable by mere mathematical calculation and could only be ascertained by proof at trial.

However, the record in this case shows that Close alleged the existence of a contract in her answer and cross-complaint, [527]*527and attached a signed copy of the basic contract to those pleadings. The contract was admitted in evidence, as well as an extra work order signed by her.

Counsel for Close, in his opening statement, repeatedly referred to the “contract” or “agreement,” and indicated he would prove a breach when he said: “For these and other matters that will occur during the course of the trial, it is the defendant’s position in this case that the plaintiffs have not performed their contract, and, failing to have performed that contract, they are not entitled to any remedy or damages or judgment against Miss Close for the contract, until such time as it is completed.”

Close admitted signing the proposal bid from Isbell and an additional work authorization. She also wrote a letter to Isbell which read: “Extra work was authorized to expedite work on the Posie Post Trailer Inn that was contracted by your firm.

“Will you kindly bill in full as of today and continue as per original contract with no further extras.

“I have no quarrel with the extra billing to date, but will not be responsible for future extras.”

Regardless, therefore, of the allegations in Isbell’s complaint, the action was tried upon a theory of express contract. Unless Close could have demonstrated in what manner she had been prejudiced by a variance between the pleadings and proof, and she urged none, a recovery based upon express contract must be sustained. Burgess v. Helm, 24 Nev. 242, 51 P. 1025 (1898); Holtzman v. Bennett, 48 Nev. 274, 229 P. 1095 (1924). In United Tungsten Corp. v. Corporation Svc., Inc., 76 Nev. 329, 353 P.2d 452 (1960), appellant claimed error in that the action was brought on quantum meruit but the judgment was based upon an express contract. We there said: “This court has repeatedly given effect to the provisions of NRCP Rule 15(b)1 to the effect that when issues not raised by the pleadings are treated [sic] by express or implied consent of the parties, they shall be treated in all respects as if they had been raised in the pleadings and that, though the pleadings may be [528]*528amended to conform to the evidence, failure to amend does not affect the result of the trial of such issues.” 76 Nev. at 331. See also Whiteman v. Brandis, 78 Nev. 320, 372 P.2d 468 (1962) for the reverse of this situation, where a recovery in quantum meruit in an action on contract was upheld.

2. In Paradise Homes v. Central Surety, 84 Nev. 109, 437 P.2d 78 (1968), we eliminated “liquidated” or “unliquidated” tests for imposing pre-judgment interest. Arley v. Liberty Mut. Fire Ins. Co., 85 Nev. 541, 458 P.2d 742 (1969).

In Paradise, we said, “The amount of money to which the interest rate will be applied must be determined by the following factors: (1) if the contract breached provides for a definite sum of money, that sum; (2) if the performance called for in the contract, the value of which is stated in money or is ascertainable by mathematical calculation from a standard fixed in the contract or from established market prices of the subject matter, that sum.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nev. Direct Ins. Co. v. Torres
Nevada Supreme Court, 2018
GOLIGHTLY & VANNAH, PLLC VS. TJ ALLEN, LLC
2016 NV 41 (Nevada Supreme Court, 2016)
Honnen Equipment Co. v. Never Summer Backhoe Service, Inc.
261 P.3d 507 (Colorado Court of Appeals, 2011)
Allapattah Services, Inc. v. Exxon Corp.
157 F. Supp. 2d 1291 (S.D. Florida, 2001)
Parodi v. Budetti
984 P.2d 172 (Nevada Supreme Court, 1999)
Western Industries, Inc. v. General Insurance Co.
533 P.2d 473 (Nevada Supreme Court, 1975)
Essex v. Guarantee Insurance
517 P.2d 790 (Nevada Supreme Court, 1973)
Southdown, Inc. v. McGinnis
510 P.2d 636 (Nevada Supreme Court, 1973)
Jones v. Jones
478 P.2d 148 (Nevada Supreme Court, 1970)
Brandon v. Travitsky
472 P.2d 353 (Nevada Supreme Court, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
471 P.2d 257, 86 Nev. 524, 1970 Nev. LEXIS 558, Counsel Stack Legal Research, https://law.counselstack.com/opinion/close-v-isbell-construction-co-nev-1970.