Clinton County v. American Bank & Trust Co.

268 N.W.2d 367, 83 Mich. App. 259, 1978 Mich. App. LEXIS 2301
CourtMichigan Court of Appeals
DecidedMay 9, 1978
DocketDocket 77-413, 77-457
StatusPublished
Cited by2 cases

This text of 268 N.W.2d 367 (Clinton County v. American Bank & Trust Co.) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clinton County v. American Bank & Trust Co., 268 N.W.2d 367, 83 Mich. App. 259, 1978 Mich. App. LEXIS 2301 (Mich. Ct. App. 1978).

Opinion

Per Curiam.

Plaintiff brought this breach of contract action on March 8, 1973, based on defendant Smith’s refusal to perform under a contract awarded to him by plaintiff. Damages sought were $550,796.83, the difference between Smith’s low bid and the next lowest bid. Accompanying the original bid was a performance bond issued by defendant American Casualty Company of Reading, Pennsylvania in the amount of $91,277.77 (5% of the Smith bid). On January 25, 1977, after a non-jury trial, judgment was entered in plaintiff’s favor for $91,277.77. Defendants appeal.

In 1972, plaintiff was bidding the DeWitt Township Sanitary Sewer Project, Phases I and II. Plaintiff advertised for bids for the construction of this sewer system pursuant to certain specifications drawn by plaintiff’s engineering consultant firm, Mick and Rowland of Angola, Indiana. De *261 fendant Smith responded. Notice to bidders was published that bids would be opened on March 20, 1972.

Bids were in fact opened on March 30, 1972, and read by representatives of Mick and Rowland. Present at the bid opening were various members of the Board of Clinton County Department of Public Works, employees of the board, and on behalf of defendant, Smith Engineers & Contractors, the General Superintendent, Horace Jasman, and the Office Manager-Secretary, Shirley Wesley.

The bids that were opened appeared as follows:

1. Forsberg, Inc. $3,561,707.05

2. Barnhart Construction Co. 3,044,375.10

3. John Lango 3.110.000. 00

4. Parsons 2,994,226.80

5. Fraser 2.997.903.00

6. Bay Construction Company 2.875.100.00

7. Delta Construction Company 2.788.000. 00

8. Nelson 2.702.712.00

9. Fisher 2.582.707.00

10. Dunnigan 2.567.481.00

11. Ackron 2.380.647.00

12. DeWitt 2,376,352.33

13. Smith 1,825,555.50

The bid openings reflected that defendant Smith’s bid 1 was the lowest bid opened and was $550,796.83 lower than the next lowest bid. It should be noted that the third lowest bid of Ackron was only $4,294.67 higher than DeWitt’s. There were no disputed facts regarding the bid opening, the bids as submitted, nor that the bid of defendant Smith was the lowest bid presented. Further, it is not disputed that defendant Smith was unaware of any error in his bid prior to the opening.

However, defendant-appellant surety contends on *262 appeal, as below, that Mr. Smith properly notified plaintiff of an error in the bid, prior to the award of the bid on April 6, 1972. It is admitted that there was no written notification but defendant-appellant surety claims that Mr. Smith attempted to inform plaintiff of his error by a telephone conversation to Mr. Dale Chapman, Chairman of the Board, as soon as he discovered the error. Mr. Jasman claims he overheard the conversation. Mr. Chapman does not recall any such conversation.

Defendant-appellant surety further claims that Mr. Smith made a subsequent call on April 2, 1972, to Mr. Mick at his home in Indiana. In his deposition, Mr. Mick remembered receiving a telephone call. However he claims that Mr. Smith did not indicate any error in his calculations and made no indication of his desire to rescind the bid.

There is no dispute that an informal meeting was held on April 3, 1972, in Dale Chapman’s office; in attendance were Richard Mick, Lowell Smith, Dale Chapman, Paul Nobis and Bob Eldridge. Of those in attendance, testimony was taken and placed on the record of all but Lowell C. Smith, now deceased.

There is no question that Mr. Smith appeared at the gathering and did make mention of a possible mistake in his bid. What mention was made by Mr. Smith, and in what manner it was mentioned, is factually disputed. Messrs. Chapman, Nobis and Eldridge all testified that Mr. Smith exhibited a single adding machine tape, apparently to support an alleged error in his bid. All of the parties indicated that they did not personally view the tape. All parties further indicated the tape was not explained, nor expanded upon in any fashion by Mr. Smith, and that Mr. Smith made no mention at that time that the alleged error was due to his leaving out the restoration process, in its entirety, from his calculations. All par *263 ties agreed that at this informal meeting no attempt was made by Mr. Smith to rescind his bid. No minutes were taken of the informal meeting.

The bid was formally awarded at the board meeting of April 6, 1972. None of plaintiffs witnesses have any independent recollection of what transpired at that meeting. The minutes themselves do not purport to be a verbatim transcript but rather are a summary of notes made by the secretary to the board.

The April 6 minutes, Exhibit 1 at trial, indicate the following, in part:

"Mr. Chapman then presented a number of objections to accepting the low bid of Smith Engineering Co. on Phase II and asked for consideration of the matter of acceptance or rejection of the bid. Mr. Mick interjected the thought that Mr. Smith might very well accept the contract at his low bid citing the fact that the overall average per foot price as bid is $17.16 which, in his opinion, is a legitimate price. The question of the legitimacy of the bid bond was then raised and it was the expressed opinion of both attorneys present that the bond, as offered, could be enforced. After some further discussion on the matter, the following motion was offered by Member Nobis, supported by Member Chamberlain:
" 'Resolved That:
1. The contract for construction of Phase II, Clinton County Sanitary Sewage Disposal System No. 1, Township of DeWitt, be awarded to Smith Engineering and Contractors in accordance with the bid received from said contractor on 30 March 1972.
2. The contract shall not become effective until the proceeds from the sale of the bonds for this project have been received by the Department of Public Works and until it shall have given the contractor notice to proceed with performance of the contract.
3. The contract shall be submitted to the contractor for signature immediately.
A roll call vote gave the following results:
3 members voted 'aye’
*264 1 member was absent
0 members voted 'nay’
The motion was declared to be carried by the Chairman.”

A number of other matters were disposed of. Then, the minutes relate:

"Upon return to the meeting, Mr. Smith entered the room and Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Warren v. MacCabees Mutual Life Insurance
268 N.W.2d 390 (Michigan Court of Appeals, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
268 N.W.2d 367, 83 Mich. App. 259, 1978 Mich. App. LEXIS 2301, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clinton-county-v-american-bank-trust-co-michctapp-1978.